Malaysia

LCS project delayed by 7.55 per cent; Guan Eng again questions Zahid's role

A handwritten note attributed to Ahmad Zahid on the letter read: “SUB [Division Secretary] Procurement, please implement.”

Updated 1 month ago · Published on 06 Oct 2026 6:54PM

LCS project delayed by 7.55 per cent; Guan Eng again questions Zahid's role
Will the technology within the LCS will be obsolete and outdated in the high-tech realm of weaponry? – October 6, 2026

by Ian McIntyre

THE RM11.22 billion Littoral Combat Ship (LCS) project continues to face delays, with overall progress lagging by 7.55 per cent as of June 25, reigniting questions regarding the procurement process.

Bagan MP Lim Guan Eng stated that this latest development also brings to mind the controversy surrounding the LCS procurement during Datuk Seri Ahmad Zahid Hamidi’s tenure as Defence Minister, including the handwritten note "Please implement" (Sila dilaksanakan) on a letter concerning the project.

“Ahmad Zahid remains haunted by the scandal involving the purchase of five LCS vessels for RM11.22 billion since 2011, a deal under which the government has paid RM6.1 billion without a single LCS vessel being delivered to date,” he said in a statement today.

Lim also referred to a July 8, 2010 letter from Boustead Naval Shipyard (BNS) to Ahmad Zahid, then defence minister, seeking a letter of intent from the government for the LCS project.

A handwritten note attributed to Ahmad Zahid on the letter read: “SUB [Division Secretary] Procurement, please implement.”

He noted that the letter contained a request for the government's mandate and endorsement for the LCS project.

In the latest development, the Auditor-General’s Report (LKAN) 2/2026 found that the LCS project was lagging by 7.55 per cent, with delays ranging from 30 to 108 days.

The delay risks affecting the Physical Handover (PHO) of LCS 1, which is currently targeted for this coming December 26.

Of greater concern, the National Audit Department has indicated that if the PHO proceeds, LCS 1 will be handed over without achieving full operational capability, as training and weapons systems have yet to be finalised.

Full operational readiness for the programme depends on a supplementary contract that is expected to be completed in December 2035, beyond the April 25, 2030 expiry of the main contract.

Furthermore, the audit report found that the delay affecting LCS 1 would impact the delivery timelines for LCS 2 through LCS 5, while cumulative payments under the main contract have already reached RM8.557 billion—or 76.22 per cent of the RM11.227 billion contract value.

Lim also noted that this timeline raises questions about whether the technology used in the vessels will be obsolete and outdated by the time the project achieves full operational readiness.

“Beyond the loss of billions of ringgit, a 24-year delay in LCS delivery—stretching to 2035 for an order placed in 2011—inevitably raises the question of whether the technology within the LCS will be obsolete and outdated in the high-tech realm of weaponry,” he said. – October 6, 2026

Related News

Malaysia / 3d

Padang Rengas dispute exposes challenge facing possible BN-PN pact

Malaysia / 3d

Zahid: One name submitted for new Negeri MB

Opinion / 5d

The Melaka state election was a non-event, but ...

Malaysia / 6d

Melaka PRN: Zahid announces Ab Rauf as Melaka CM for second term

Malaysia / 1w

UMNO prepared to disclose details of RM50m collected for Najib house arrest

Malaysia / 2w

Let the US election results be a reminder to us – Guan Eng

Spotlight

World

Singaporean extradited to US over alleged global insider trading network

Malaysia

Malaysia will not bow to external pressure in deepening China ties, says Anwar

Opinion

When those entrusted to defend the country are accused of drug smuggling

By The Vibes Says

Malaysia

Palace tells Ismail to prove majority support before new exco appointments

By Alfian Z.M. Tahir

Malaysia

Man who sodomised, killed baby under his care sentenced to death by hanging

Malaysia

Ismail vows to resign if state government breaches undertaking to Tuanku Muhriz

Malaysia

Ismail Lasim to remain as Negeri MB

Heritage

No development at Mount Erskine burial site: land is for cemetery-related purposes

By Ian McIntyre

You may be interested

Malaysia

Police uncover alleged air route used to smuggle drugs to Sabah, 11 arrested

Malaysia

Najib has been given a second chance. But where is the accountability to Malaysians?

By The Vibes Says

Malaysia

Malaysians urged to update phones to avoid missing emergency alerts

Malaysia

Malaysia will not bow to external pressure in deepening China ties, says Anwar

Malaysia

Father of deceased boarding school student calls for transparent, thorough probe

Malaysia

Oil prices head for 3rd weekly loss as supply outlook offsets Iran tensions

Malaysia

Two toddlers killed in fire at converted office building in Kedah

Malaysia

Palace tells Ismail to prove majority support before new exco appointments

By Alfian Z.M. Tahir