THE government faces potential legal and financial liabilities if it terminates contractors involved in the delayed Sabah Pan Borneo Highway project without complying with contractual and legal requirements, says Works Minister Datuk Seri Alexander Nanta Linggi.
He said contractors could not be dismissed at will, particularly when some delays stemmed from circumstances beyond their control, including unresolved land acquisition compensation that prevented access to construction sites.
Nanta said contractors were entitled to apply for extensions of time (EOT) when project delays resulted from such circumstances.
“If the (state) department of lands and surveys has not settled land acquisition compensation, contractors cannot access the site, because landowners will not allow them to do so. In such cases, they are indeed entitled to claim an extension of time.
“We cannot simply terminate contracts at will. If we fail to comply with proper governance or legal requirements, they could take us to court and claim damages, which the government would then have to pay,” he said.
His remarks come amid concerns over the slow implementation of Sabah Pan Borneo Highway Phase 1, which was highlighted in the 2026 Auditor-General's Report.
Nanta explained that the overall progress figure covered all 35 work packages under Phases 1A and 1B, including several packages experiencing significant delays.
He said Phase 1B, comprising 19 packages that began in September 2024, had recorded 26% physical progress and 23% financial progress.
Phase 1A, comprising 15 packages that began earlier, had achieved 90% physical progress, with four packages fully completed, although he acknowledged serious implementation shortcomings.
He identified Packages 1 and 2, located near the Sarawak border, as the main problem areas, saying their delays had weighed down the combined progress figure.
Last month, Nanta cited several factors behind the project's delays, including the transition from the project delivery partner (PDP) model to the conventional implementation method, the Covid-19 pandemic, land acquisition problems, utility relocation and contractor performance.
He said the Works Ministry had accepted the findings and observations in the Auditor-General's Report and was reorganising the deployment of Sabah Public Works Department (JKR) personnel to improve project administration and implementation.
The government is targeting completion of the entire Pan Borneo Highway project by 2030. - November 17, 2026