Govt faces legal hurdles in axing underperforming Sabah Pan Borneo contractors

Nanta Linggi says contract termination without due process could trigger lawsuits and compensation claims

Updated 5 minutes ago · Published on 17 Nov 2026 11:33AM

Govt faces legal hurdles in axing underperforming Sabah Pan Borneo contractors
The Minister explains that delayed land acquisition and unresolved site handovers complicate efforts to speed up the highway project - November 17, 2026

THE government faces potential legal and financial liabilities if it terminates contractors involved in the delayed Sabah Pan Borneo Highway project without complying with contractual and legal requirements, says Works Minister Datuk Seri Alexander Nanta Linggi.

He said contractors could not be dismissed at will, particularly when some delays stemmed from circumstances beyond their control, including unresolved land acquisition compensation that prevented access to construction sites.

Nanta said contractors were entitled to apply for extensions of time (EOT) when project delays resulted from such circumstances.

“If the (state) department of lands and surveys has not settled land acquisition compensation, contractors cannot access the site, because landowners will not allow them to do so. In such cases, they are indeed entitled to claim an extension of time.

“We cannot simply terminate contracts at will. If we fail to comply with proper governance or legal requirements, they could take us to court and claim damages, which the government would then have to pay,” he said.

His remarks come amid concerns over the slow implementation of Sabah Pan Borneo Highway Phase 1, which was highlighted in the 2026 Auditor-General's Report.

Nanta explained that the overall progress figure covered all 35 work packages under Phases 1A and 1B, including several packages experiencing significant delays.

He said Phase 1B, comprising 19 packages that began in September 2024, had recorded 26% physical progress and 23% financial progress.

Phase 1A, comprising 15 packages that began earlier, had achieved 90% physical progress, with four packages fully completed, although he acknowledged serious implementation shortcomings.

He identified Packages 1 and 2, located near the Sarawak border, as the main problem areas, saying their delays had weighed down the combined progress figure.

Last month, Nanta cited several factors behind the project's delays, including the transition from the project delivery partner (PDP) model to the conventional implementation method, the Covid-19 pandemic, land acquisition problems, utility relocation and contractor performance.

He said the Works Ministry had accepted the findings and observations in the Auditor-General's Report and was reorganising the deployment of Sabah Public Works Department (JKR) personnel to improve project administration and implementation.

The government is targeting completion of the entire Pan Borneo Highway project by 2030. - November 17, 2026

Spotlight

Malaysia

Bersama, Bersatu fail to win a seat in Melaka, face questions over political future

By Alfian Z.M. Tahir

Malaysia

African man apologises to Malaysians over machete attack on policeman

Malaysia

Two family members to be charged with murder of elderly man in Negeri Sembilan

Malaysia

Kuching student accused of attacking teacher with a deadly weapon sent for mental observation

People

Hans Isaac engaged to former Miss Universe Malaysia Francisca Luhong in Paris proposal

Malaysia

NS Exco: Palace weighs settlement proposals as court hearing postponed

Malaysia

Police hunt answers after 15-year-old girl shot in neck in Ranau

Malaysia

Missing 74-year-old windsurfer found dead off Tanjung Bungah

You may be interested

Malaysia

Ab Rauf retains Melaka leadership

Malaysia

Scams: Fahmi wants WhatsApp to strengthen phone number verification

Malaysia

Two of five Malaysians held in Thailand over 240kg meth haul have prior drug convictions

Malaysia

Police probe claims Nigerian syndicate using student visas to recruit members in Malaysia

Malaysia

Zahid confirms BN will sit out Sarawak polls

Malaysia

Nation's economic resilience allows BNM to hold OPR at 2.75%, says Amir Hamzah

Malaysia

Anwar highlights historic transfer of executive powers under Parliamentary Services Act

Malaysia

Negeri Sembilan Palace: MB's resignation not confirmed, royal consent required