Baling floods: temporary bridge at Kg Iboi ready for use tomorrow

Construction did not involve any cost, says Works Ministry sec-gen

Updated 4 years ago · Published on 08 Jul 2022 12:22PM

Baling floods: temporary bridge at Kg Iboi ready for use tomorrow
Works Ministry secretary -general Datuk Wan Ahmad Uzir Wan Sulaiman says the 90-ft-long and 18-ft-wide temporary bridge in Kg Iboi in Baling could accommodate loads of up to five tonnes. – Bernama pic, July 8, 2022

BALING – The temporary bridge being built in Kg Iboi here to replace the bridge that collapsed in the floods and water surge phenomenon last Monday is expected to be ready for use tomorrow.

Works Ministry secretary -general Datuk Wan Ahmad Uzir Wan Sulaiman said installation of the steel “Old Bailey Bridge” began yesterday by 20 staff from the Road Division and Mechanical Works Branch of the Kedah Public Works Department (JKR) and assisted by 10 members of the Malaysian Armed Forces (ATM).

“Residents have requested us to complete the temporary bridge as soon as possible before Aidiladha so that they can make preparations to celebrate the festival,” he said when contacted here today.

He said the 90-ft-long and 18-ft-wide bridge could accommodate loads of up to five tonnes.

All the heavy machinery materials used in building the bridge belonged to or were obtained from the JKR store. Therefore, its construction did not involve any cost, he said.

Meanwhile, Kg Iboi Development and Security Committee chairman Abu Hasan Samah, 62, said the construction of the temporary bridge would facilitate the daily affairs of about 3,000 residents from several villages in the area.

He said the bridge, which collapsed last Monday, served as a link for residents from Kg Masjid Iboi, Kg Bok Bak, Kg Tanjung Luas and Kg Tanjung Nering to go to the town, and since then, they were forced to take the longer route.

"Residents in Kg Iboi also use the bridge to go to the mosque across the river, and we are indeed grateful to the government for providing us with the temporary bridge and hope it will be ready soon,” he added. – Bernama, July 8, 2022

Related News

Malaysia / 3y

17 Kg Iboi yellow zone families to get new homes: Sanusi

Malaysia / 4y

Environment Ministry to let Kedah decide on Gunung Inas reservoirs

Malaysia / 4y

Baling floods saw losses of around RM28 mil: Sanusi

Malaysia / 4y

Baling floods: one evacuation centre closes, 94 victims still sheltering at another

Malaysia / 4y

Man braves Baling floodwater to save siblings, neighbour

Malaysia / 4y

Baling flood returns, 130 victims evacuated to relief centres

Spotlight

Malaysia

Haze: Schools in Johor, Melaka, and Negeri Sembilan to close tomorrow

Malaysia

Tun Mahathir’s health improves, but not ready to leave hospital

Malaysia

LPT3 row puts Kelantan’s infrastructure priorities under scrutiny

Malaysia

Terengganu royal family member sues two banks over RM1.99m missing from savings

Malaysia

Irene Sofiya murder probe referred to Johor prosecutors for review

Malaysia

Teacher denies negligence charges over fatal school SUV crash in Kota Bharu

Malaysia

Sulaiman Md Ali opts out of Melaka polls, will not defend Lendu

You may be interested

Malaysia

Johor, Sarawak top unhealthy air readings as 20 stations breach threshold

Malaysia

Sarawak projects record RM15.09b revenue, budgets RM10.1b for development in 2027

Malaysia

Driver monitoring aims to stop commercial vehicle crashes before they happen

Malaysia

Express bus crashes into school surau at site of fatal SUV accident

Malaysia

RM5b JENDELA allocation to expand internet access in rural Malaysia

Malaysia

Govt to push ASEAN for stronger action on transboundary haze as schools shut across four states

Malaysia

RM2,000 minimum wage: Firms with sales below RM50m exempt from 2027 hike

Malaysia

Sinkhole mapping to be stepped up through Federal-state cooperation