Malaysia

Pan Borneo Highway: 16 work packages now 75% complete

Deputy works minister says two packages now open to road users while 13 will be ready early 2025

Updated 3 years ago · Published on 06 Jun 2023 3:14PM

Pan Borneo Highway: 16 work packages now 75% complete
Deputy Works Minister Datuk Seri Abdul Rahman Mohamad has told the Parliament that 16 work packages in Phase 1 of the Pan Borneo Highway are being implemented at they are at 75% completion. – Bernama pic, June 6, 2023

KUALA LUMPUR – A total of 16 work packages in Phase 1 of the Pan Borneo Highway project are being implemented and currently, the progress status is at 75%, the Dewan Rakyat heard today.

Deputy Works Minister Datuk Seri Abdul Rahman Mohamad said of the total, two work packages are already opened to road users, while 13 work packages are expected to be completed by early 2025. 

“As for the status of a new work package, namely Work Package 9 involving the route from Serusop to Pituru, it is expected to be implemented as early as the second quarter of 2023, as such, 16 work packages are being implemented for now. 

“The government is committed to ensuring that the Pan Borneo Highway project continues to be implemented and to that end, RM2 billion has been allocated each year where RM1 billion goes to the Sabah Pan Borneo Highway and Sarawak Pan Borneo Highway projects respectively,” he said 

He said this in reply to a question from Mordi Bimol (Mas Gading-PH) who wanted to know the latest status, the time taken to complete the Pan Borneo Highway project in Sabah and Sarawak, as well as the government’s commitment to reduce accidents along the route under construction. 

For the 10 work packages from Sematan to Miri, Abdul Rahman said the entire alignment would be completed in November 2023 except for some sections in Miri that need to be reconstructed which could only be completed in 2025. 

In addition, he said the remaining 19 work packages (Phase 1B) that have yet to start would be financed in a hybrid manner using development allocations and through the issuance of sukuk or bonds by DanaInfra Nasional Berhad. 

“This Pan Borneo Highway Sabah Phase 1B project will be implemented with a construction period of 5 years, and is expected to start as early as in the third quarter of 2023, subject to the approval of the central agency,” he said. 

On the government’s commitment to reduce accidents along the routes under construction, he said the Works Ministry and the Public Works Department of Sabah and Sarawak would continue to monitor the areas to ensure the safety and comfort of road users. – Bernama, June 6, 2023

Related News

Malaysia / 13h

Sabah does not agree to 200-litre diesel quota, forms special committee - Masidi

Malaysia / 1mth

Tsunami alert: Stay calm and obey instructions from the authorities – Hajiji (video)

Malaysia / 1mth

Sabah embarks on five-year initiative to document multiethnic heritage - Hajiji

Malaysia / 1mth

Anwar - Sabah's special grant interim payment increased from RM600m to RM1.5b

Malaysia / 1mth

Anwar to clarify Sabah 40 pct entitlement talks tomorrow

Malaysia / 1mth

Sabah: GRS confident government will agree to review revenue entitlement rate 

Spotlight

Malaysia

After Johor, the uncomfortable question for Anwar’s critics: Were we too impatient?

By The Vibes Says

Malaysia

Network School's business licences revoked, to cease operations tomorrow

Opinion

Orang Asli in Pahang: Token gestures or genuine recognition?

Malaysia

Tuition teacher sentenced to 105 years in prison and 70 lashes for raping daughter

Malaysia

Azam Baki denies involvement in RM178.29 million contract linked to brother’s company

Malaysia

Aminuddin urges NS voters to weigh manifesto promising benefits for M40 and B40 groups

Malaysia

No need to resign, PM has absolute power if there is doubt – Ahmad Zahid

World

Gaza’s water crisis deepens as families face thirst, disease and collapsing sanitation systems

You may be interested

Malaysia

Azam Baki denies involvement in RM178.29 million contract linked to brother’s company

Malaysia

Zahid denies BN-PN-GPS-GRS meeting rumours, reaffirms Unity Government commitment

Malaysia

140 Palestinian NGOs support Khan over denial of due process

By Abbi Kanthasamy

Malaysia

Police probe possible online group influence behind Banting school stabbing incident

Malaysia

Activist charged over alleged desecration of Hindu sacred object at Langkawi temple site

Malaysia

PM holds final authority on cabinet appointments - Minister

Malaysia

BN-PH ties strained by grassroots reality, not Putrajaya pact, says analyst

By Alfian Z.M. Tahir

Malaysia

Sabah seeks additional RM1.61b allocation to fund state operations and development needs