PAC to table report on littoral combat ships project in next Dewan Rakyat sitting

It involves RM9.128 bil, RM6 bil paid, no ship completed, delivered, says PAC chairman

Updated 4 years ago · Published on 26 Jan 2022 4:22PM

PAC to table report on littoral combat ships project in next Dewan Rakyat sitting
PAC chairman Wong Kah Woh says the committee has held eight proceedings on the littoral combat ships project and are reaching the final stage, and shall table its report in the Dewan Rakyat sitting in March. – Wong Kah Woh Facebook pic, January 26, 2022

KUALA LUMPUR – The Public Accounts Committee (PAC) is expected to table its report on the littoral combat ships (LCS) project in the coming Dewan Rakyat sitting in March.

PAC chairman Wong Kah Woh said the committee held eight proceedings so far and called several witnesses, including Defence Minister Datuk Seri Hishammuddin Hussein and former deputy prime minister Datuk Seri Ahmad Zahid Hamidi.

Other witnesses were Defence Ministry’s chief secretary Datuk Seri Muez Abd Aziz, navy chief Admiral Tan Sri Mohd Reza Mohd Sany, former auditor-general Tan Sri Ambrin Buang and others.

“Back in Parliament today. Continue our proceeding on the LCS project.

“All witnesses have given their full cooperation to PAC. We are reaching the final stage of the proceedings and shall table our report, hopefully, in the March sitting,” said Wong.

Wong, in his Facebook post reiterated that the LCS project involves a total sum of RM9.128 billion, with RM6 billion paid, but no ship completed or delivered.

Last November, Hishammuddin was reported as saying that the navy will receive its first littoral combat ship in 2025.

He said the settlement initiatives outlined two main components, namely corporate restructuring and fundraising, which also involved discussions with the Finance Ministry and Economic Planning Unit in the Prime Minister’s Department.

He added that the government had agreed to approve the ships’ procurement application under the 10th Malaysia Plan and 11MP with a 10-year implementation period from October 3, 2013, to October 2, 2023.

However, he said as of October 31 this year, work progress on the ships is at 57.05% compared to the original work plan schedule of 96.57%. Overall, the procurement experienced a delay of 39.52%, equivalent to 43 months. – The Vibes, January 26, 2022

Related News

Malaysia / 1w

PAC set to scrutinise concerns raised by RCI over TH

Malaysia / 1mth

1MDB audit did not cover Najib’s personal accounts, court told

Malaysia / 1mth

Shafee seeks to strike out parts of Tony Pua's statement

Malaysia / 2mth

Don't repeat old mistakes, five ships must be completed according to cost and schedule – PAC

Malaysia / 2mth

PAC: GL holders charged excessively compared to cash-paying patients

Malaysia / 7mth

HRD Corp suspends 3 top executives

Spotlight

Malaysia

MP calls on US to take legal action against Hadi over ‘plot to topple government’ statement

By Ian McIntyre

Malaysia

Malaysia needs to master its own technology - PM Anwar

Malaysia

RM2.48m lost daily to investment fraud syndicates since 2023

Malaysia

Rising bond rates are a sign of rising debt

Education

Selangor to close schools if API readings exceed 200

Malaysia

Loke: Keep Anwar as PM to complete reform agenda

Malaysia

Investigations into political leaders not driven by spite or political payback - PM

You may be interested

Malaysia

The potential for a redevelopment of Port Dickson

Malaysia

Bathroom peeping allegation uncovers four-year-old molestation claim against stepfather

Malaysia

Energy reform key to investment, jobs and growth - Economy Minister

Malaysia

Malaysia faces 9GW gas power gap as data centres drive electricity demand

Malaysia

Zahid defends ministry, rejects all claims of financial recklessness

Malaysia

Jamil Khir released after seven-day remand in Tabung Haji RCI probe

Malaysia

Former Felda GM remanded five days

By Alfian Z.M. Tahir

Malaysia

Melaka CM hints at state assembly dissolution being ‘two Fridays’ away