Putra Heights gas pipe explosion: Repair, reconstruction work between 22 – 24 per cent, says MB

Repair work involves an allocation of RM40 million approved by the Cabinet, in addition to RM6 million to improve public infrastructure.

Updated 1 year ago · Published on 08 Jul 2025 4:04PM

Putra Heights gas pipe explosion: Repair, reconstruction work between 22 – 24 per cent, says MB
The MB said the current progress level is between 22 and 24 percent. - July 8, 2025

THE repair and reconstruction work on houses destroyed and damaged due to the gas pipe explosion incident in Putra Heights last April is currently at a progress level of between 22 and 24 percent.

Selangor Menteri Besar, Datuk Seri Amirudin Shari, said the work involves 81 houses that were destroyed and 138 houses that were damaged in Kampung Kuala Sungai Baru and is expected to be completed this October.

“For the houses in Taman Putra Harmoni, the completion period is set for 24 months, which is until June 2027,” he said during the Selangor State Legislative Assembly (DUN) session today.

According to him, the implementation of the repair work involves an allocation of RM40 million that has been approved by the Cabinet, in addition to RM6 million to improve public infrastructure.

“Syarikat Perumahan Nasional Berhad (SPNB) has been tasked by the Ministry of Housing and Local Government to manage the repair and reconstruction of houses in Kampung Kuala Sungai Baru.

“All this work commenced since May 1,” he said.

The Cabinet has also decided that Sime Darby Property, as the original developer, be given the responsibility to rebuild and repair the affected houses in the area.

“So far, based on the Ecosystem Assessment Unit Test (UPE) for the reconstruction in Taman Putra Harmoni, three units will be rebuilt, while 46 units will be repaired and the remaining 46 units are currently in the final process of crack and structural testing.

“As for Kampung Kuala Sungai Baru, 17 units are involved; of that total, 11 units will be rebuilt while six more units will be repaired,” he said. – July 8, 2025

Related News

Malaysia / 6d

10 PH assemblymen, 2 DUN coordinators ordered to return allocations – Negeri MB

Malaysia / 2w

Putra Heights tragedy report expected to be released as early as October

Events / 3w

Selangor turns focus to AI, semiconductors as Techsphere Summit returns

Malaysia / 4w

Selangor MB apologises for police escort's behaviour towards road user (video)

Malaysia / 4w

Negeri Sembilan mulls deputy Exco posts as Ismail settles new state cabinet

Malaysia / 1mth

NS Exco to be decided after discussions with UMNO president - MB

Spotlight

Malaysia

Four teenagers feared drowned at Tanjung Lompat

World

Thailand to halve visa-free stay to 30 days for 60 countries from Sept 15

Malaysia

Woman injured as concrete debris falls from George Town heritage building

Malaysia

Collision between tanker and ferry under investigation - PPC

By Ian McIntyre

Malaysia

Anwar’s six measures offer relief across the everyday economy

By Alfian Z.M. Tahir

Malaysia

Mahathir’s Merdeka appearance sparks social media debate

By Alfian Z.M. Tahir

You may be interested

Malaysia

Woman injured as concrete debris falls from George Town heritage building

Malaysia

Malaysia to bring in 200,000 Bangladeshi workers in six-month intake

Malaysia

Sarawak haze crisis deepens as five areas breach hazardous air quality levels

Malaysia

Container lorry plunges 20 metres into Gua Musang ravine, driver killed

Malaysia

Anwar’s six measures offer relief across the everyday economy

By Alfian Z.M. Tahir

Malaysia

3-year-old injured after leg run over by fire dept vehicle during Merdeka parade

Malaysia

Penang, Thai cops seize drugs worth over RM4m in joint operation

By Ian McIntyre

Malaysia

Collision between tanker and ferry under investigation - PPC

By Ian McIntyre