ECRL ahead of schedule, Dewan Negara told

Deputy transport minister says project’s overall construction progress nearly 1% ahead of time

Updated 5 years ago · Published on 22 Dec 2020 3:36PM

ECRL ahead of schedule, Dewan Negara told
The Dewan Negara was told today that Section B of the East Coast Rail Link project, which links Dungun to Temerloh, is now over 2% ahead of schedule after resuming construction in July 2019. – ECRL pic, December 22, 2020

KUALA LUMPUR – Construction of the East Coast Rail Link (ECRL) project continues to advance beyond its original schedule, said Deputy Transport Minister Hasbi Habibollah.

Hasbi said as of November 30, the overall construction of the project achieved actual progress of 19.69% compared to the original schedule of 18.78%.

He said for Section A from Kota Baru to Dungun which includes the construction of six stations namely Kota Baru, Pasir Putih, Jerteh, Bandar Permaisuri, Kuala Terengganu and Dungun, physical work progress was 0.27% ahead of schedule.

Hasbi said for Section B from Dungun to Temerloh, construction which resumed in July last year, physical work progress has reached 7.54% compared to the schedule of 5.24%, covering earthworks and tunnel construction in Dungun, Paka and Kuantan.

“Preliminary works for the construction of tunnels in Gambang, Sri Jaya, Gedung Siam and Paya Pasir have begun,” he said, when winding up the debate on the 2021 Supply Bill at the Dewan Negara today.

As for Section C from Temerloh to Port Klang, he said the government was studying the best alignment to ensure ECRL gave maximum economic impact when completed and it would be announced when the study is completed.

On the status of the Sultan Ismail Petra Airport upgrade project in Kelantan, he said the project, which was implemented through a pre-qualifying open tender, was in the final stages of tender evaluation and was expected to be completed this month.

“The appointment of a contractor is scheduled for early next year and the project is expected to be completed in December 2023,” he said.

Hasbi said the airport is expected to accommodate four million passengers a year, an increase of 2.5 million passengers compared to the current capacity of 1.5 million passengers a year.

The total capacity of the landing aircraft will be increased from three to eight 4C code aircraft as well as from two ATR 72s to three ATR 72s. – Bernama, December 22, 2020

Spotlight

Malaysia

Geopolitical tensions must not derail regional economic integration - Anwar

Malaysia

Najib has been given a second chance. But where is the accountability to Malaysians?

By The Vibes Says

Malaysia

PAS joins BN in sitting out Sarawak polls

Malaysia

PAC to probe possible financial breaches, abuse of power in Sabah Pan Borneo project

Malaysia

Landowners cannot demolish unauthorised places of worship themselves, says Nga

By Alfian Z.M. Tahir

Malaysia

Najib’s house arrest: Differing views do not constitute treason – lawyer

Malaysia

Suspected criminal shot dead in exchange of fire with police in Perak

You may be interested

Malaysia

Nation's economy expands 5.6%, a first over nine months of 2026

Malaysia

Teenager pleads guilty to three sexual offence charges involving 14-year-old girl

Malaysia

36 foreigners held in Kuantan raids on love scam call centres targeting Vietnam

Malaysia

'I was beaten, ordered to strip naked while in remand' – wife of ex-ESSCOM officer tells court

Malaysia

No large-scale cyberattack causing Malaysian data leak reported, says Fahmi

Malaysia

MMA seeks urgent probe into claim Sabah doctor used phone torch during procedure

By Alfian Z.M. Tahir

Malaysia

Enforcement agencies, politicians top corruption perception list in Malaysia – survey

Malaysia

Negeri MB expected to seek audience with Tuanku Muhriz soon?