RM2.1b rural road overspending triggers contractor payment delays, new project freeze

The government approves an extra RM500 million to ease contractor payment arrears after rural road spending exceeded allocations by RM2.1 billion between 2023 and 2025

Updated 51 minutes ago · Published on 20 Oct 2026 9:18AM

RM2.1b rural road overspending triggers contractor payment delays, new project freeze
All new project awards are suspended as the Finance Ministry reviews funding needs - October 20, 2026

RURAL road projects have run up RM2.1 billion in spending beyond approved allocations between 2023 and 2025, prompting the government to approve an additional RM500 million and halt new project awards to contain contractor payment arrears.

Prime Minister and Finance Minister Datuk Seri Anwar Ibrahim said the Finance Ministry had identified savings in other ministries’ development expenditure to provide the additional funding to the Rural and Regional Development Ministry (KKDW).

He said KKDW had been directed on Sept 10 to suspend the issuance of new letters of acceptance (SST) for rural road projects to prevent arrears from rising further.

“KKDW has made commitments and spent beyond the original allocations approved under annual Budgets for rural road projects over several years, resulting in arrears and delays in payments to contractors,” he said in a written parliamentary reply.

Anwar said annual allocations for rural road projects had been raised to more than RM2 billion under Budget 2026 and Budget 2027, but were still insufficient to cover contracts already awarded.

The Finance Ministry has asked KKDW to prepare funding projections through the end of this year and for 2027, based on existing contractual commitments, to determine the additional financing required.

Anwar was responding to Lim Guan Eng (PH-Bagan), who asked about action against those responsible for alleged financial procedure breaches involving RM2.1 billion in expenditure exceeding allocations from 2023 to 2025.

He said rural road projects were generally awarded through open tenders and Pre-Qualification Open Tender (TTPKT), a special procedure introduced by the Finance Ministry in 2023 to speed up project implementation.

However, the Auditor-General’s Report No. 2/2025 found that TTPKT, including its use by KKDW, had failed to achieve the government’s original objectives.

“Accordingly, the Finance Ministry has also stopped approving the use of TTPKT by KKDW for new projects,” he said. - October 20, 2026

Spotlight

Malaysia

Papagomo acquitted for second time in sedition case over government, Israel claims

Malaysia

ECRL fares start at RM60, with 50% discounts for children, seniors and OKU

Malaysia

DKU seeks court action against Ismail, 16 others over Negeri Sembilan royal dispute

By Alfian Z.M. Tahir

Malaysia

Kampung Manis: Dreams of 227 families to own replacement homes draw closer

Malaysia

Fadhlina takes legal action over video of 2023 Parliament speech

By Alfian Z.M. Tahir

Malaysia

Civil servants urged to turn Selangor Sultan’s anti-graft message into action

Malaysia

Animal welfare group urges probe into alleged sexual abuse of cat in viral video

Malaysia

Macron appeals for calm after France riots: 2,400 arrested, nearly 1,000 officers injured

Malaysia

Malaysia renews offer to help Indonesia fight fires

You may be interested

Malaysia

Kampung Manis: Dreams of 227 families to own replacement homes draw closer

Malaysia

King appoints three Malaysian envoys to Canada, Belgium and Iran

Malaysia

PM orders faster rollout of Budget 2027 aid, warns against bureaucratic delays

Malaysia

ECRL fares start at RM60, with 50% discounts for children, seniors and OKU

Malaysia

Police record statements from 15 in RM231m MYEG-Zetrix probe

Malaysia

Takiyuddin’s use of ‘munafik’ sparks Dewan Rakyat row

Malaysia

Anwar: Malaysia still owes RM8.9b in 1MDB liabilities

Malaysia

Five states reopen schools as haze forces exam delays and outdoor curbs