Paperwork dogs Penang South Islands plan, revised EMP to be submitted

Without the documents, works cannot take place as scheduled on Island B, followed by A and C

Updated 5 years ago · Published on 02 Jun 2021 8:00PM

Paperwork dogs Penang South Islands plan, revised EMP to be submitted
The EMP is part of the EIA’s approval requirements for the Penang South Islands project that requires the appointed contractor to comply with prescribed environmental control measures and programmes. – Unstudio.com pic, June 2, 2021

by Sofia Nasir

GEORGE TOWN – The biggest hurdle for the Penang South Islands project (formerly Penang South Reclamation) has turned out to be mismatched paperwork, amid the tug-of-war between the state government and activists over the massive development plan.

The snag here is the Environmental Impact Assessment (EIA), which states that the plan is to start work on Island B, followed by Islands A and C. However, the Environmental Management Plan (EMP) submitted to the federal Department of Environment (DoE) on January 6 had an error.

Now, Deputy Chief Minister 1 Datuk Ahmad Zakiyuddin Abd Rahman told The Vibes that a revised EMP will be submitted to the DoE later this month.

Without the EIA and EMP, works cannot take place. It is learnt that the EMP approval takes around 90 days.

While the EIA is set to expire this month, the DoE has already extended the approval until April 10, 2022.

The EMP is part of the EIA’s approval requirements for the PSI project that requires the appointed contractor to comply with prescribed environmental control measures and programmes.

Zakiyuddin also said the state government will revert to its EIA plan, which is to start work on Island B, and the revised EMP should reflect that.

“Yes, we will build Island B first. Regarding the agreement with the developer, I understand it has not been finalised and is still at the level of mutual understanding.

“However, the distance between Island A and B is not far, so we will probably first build part of Island B which is close to Island A. Whatever it is, we’ll wait.”

The PSI project will start with building the 4.45 sq km Island B first, to take up to seven years, followed by the 9.3 sq km Island A, which will take about eight years, followed by the 3.23 sq km Island C to be completed in seven years. – Twitter pic, June 2, 2021
The PSI project will start with building the 4.45 sq km Island B first, to take up to seven years, followed by the 9.3 sq km Island A, which will take about eight years, followed by the 3.23 sq km Island C to be completed in seven years. – Twitter pic, June 2, 2021

The DoE had, in a statement in May, denied it was considering an EMP for the Penang mega reclamation project.

Its director-general, Norlin Jaafar, had said this was because the Penang DoE had not received the EMP, which is in line with the concept of the project.

It is understood that the EMP report submitted to the DoE previously did not follow the original sequence of works as submitted in the EIA report that was approved by the DoE on June 25, 2019.

Through the public presentation of the the EIA report in April 2019, it said that the PSI project would start with building the 4.45 sq km Island B first, which is estimated to take up to seven years.

During this period, the developer will also build the 9.3 sq km Island A that will take about eight years, followed by the 3.23 sq km Island C that is expected to be completed in seven years.

However, in March, the Penang government announced changes to the financing plan for Island A that would be made through a private financing initiative without involving state funds, in a 30:70 stake with SRS Consortium.

Chow had said that preliminary works or Phase 1 of the reclamation works would be on Island A, and expected to take five years and cost RM3.8 billion.

The implementation of the PSI with an area of ​​almost 17 sq km involves the development of three artificial islands with an area of ​​1,700ha in the waters of Permatang Damar Laut, near Bayan Lepas.

It is part of the Penang Transport Master Plan (PTMP) worth RM46 billion. – The Vibes, June 2, 2021

Related News

Community / 4h

Penang: Ratepayers Association calls for immediate solution to worsening congestion

People / 1d

Prevention and early detection vital to reduce NCD rates, says Penang Exco

Community / 3d

More attention needed to care for the aged, says consumer association

Malaysia / 3d

Declining birth rate among the Chinese community worrying, says Penang Exco

Community / 5d

Penang introduces self-service cutlery return initiative at food court

Community / 6d

Penang urged to plant new trees before felling those deemed rotten

Spotlight

World

Kim Jong Un appears in state media photos after unverified death rumours

Malaysia

Anwar challenges Rafizi over corporate crime, asks why he stayed silent as minister

Malaysia

AKPS chief Mohd Shuhaily to be charged over alleged assault on two policemen

Malaysia

Year One pupil dies after breathing difficulties in Dengkil classroom

Malaysia

College student remanded for three days over alleged rape of underage girl

Sports & Fitness

Lee Zii Jia settles dispute with father, sister over company affairs

By Alfian Z.M. Tahir

Malaysia

Online scam call centres: Police detain 31 people targeting foreign victims in Pahang crackdown

Malaysia

Guan Eng proposes RM1,000 tax rebate for purchase of air purifiers

By Ian McIntyre

You may be interested

Malaysia

Sungai Pinang flood mitigation project to be completed by September 2027

Malaysia

Teresa Kok’s defamation suit: Akmal Saleh ordered to pay RM300,000

Malaysia

Over 300 schoolgirls may be victims of AI-edited nude images, lawyer says

Malaysia

Property agent loses over RM79k after being scammed twice

Malaysia

Fadhlina takes legal action over video of 2023 Parliament speech

By Alfian Z.M. Tahir

Malaysia

PN faces deregistration after RoS rejects its appeal to retain status

Malaysia

Police record statements from 15 in RM231m MYEG-Zetrix probe

Malaysia

Civil servants urged to turn Selangor Sultan’s anti-graft message into action