Selangor govt okays RM40 mil for urgent flood mitigation

Committee chairman says work expected to be completed in stages by April next year

Updated 4 years ago · Published on 11 Nov 2021 5:40PM

Selangor govt okays RM40 mil for urgent flood mitigation
State infrastructure and agriculture committee chairman Izham Hashim says immediate action will enable the Selangor Irrigation and Drainage Department to carry out flood mitigation works in a short period of time. – Izham Hashim Instagram pic, November 11, 2021 

SHAH ALAM – The Selangor government has approved nearly RM40 million in allocation for urgent implementation of flood mitigation works in 50 areas categorised as flood “hotspots”.

State infrastructure and agriculture committee chairman Izham Hashim said the projects will start next month, and work is expected to be completed in stages by April next year.

He said RM25.67 million will cover the implementation of 35 projects, including the dredging and deepening of rivers; construction and upgrading of bunds; pump installations; and the demolition of illegal structures on river reserves.

“Besides that, there is a project to build the Bluewater Retention Pond in Seri Kembangan at an estimated cost of RM4 million, and RM10 million for building a flood retention pond on the Grand Shapadu Highway next to Taman Mutiara Bukit Raja that will be implemented immediately,” he told a press conference here today.

Izham said immediate action will enable the Selangor Irrigation and Drainage Department to carry out flood mitigation works in a short period of time, whereby designing will be carried out internally by the department.

For long-term measures, he said the federal government had approved a budget of RM455 million, adding that it had applied for another RM1.35 billion under the 12th Malaysia Plan (12MP) for a holistic solution involving five flood mitigation projects.

He said for short- and long-term action using the state development allocation, RM250 million has been approved under 12MP and the projects are being implemented in stages until 2024. – Bernama, November 11, 2021 

Related News

Malaysia / 2w

Putra Heights tragedy report expected to be released as early as October

Events / 3w

Selangor turns focus to AI, semiconductors as Techsphere Summit returns

Malaysia / 1mth

Selangor MB apologises for police escort's behaviour towards road user (video)

Malaysia / 1mth

Tengku Permaisuri Selangor: ‘No form of cruelty to animals will be accepted or tolerated’

Malaysia / 1mth

Selangor reviewing need for by-election following unconfirmed reports of ADUN’s bankruptcy

Malaysia / 2mth

Johor polls should be contest of ideas, not division – Selangor PKR election director

Spotlight

Malaysia

Penang CM defends move by housing board, says enforcement is last resort

By Ian McIntyre

World

Anak Krakatau’s six eruptions recorded

Malaysia

Delivery rider's compassion turns RM14.50 meal into wave of public generosity

Malaysia

Sanusi’s gambling stance puts PAS manifesto under scrutiny

By Alfian Z.M. Tahir

Malaysia

Zahid’s game plan is opening up

Malaysia

Chew Jetty fire: Business owners lose everything in the blink of an eye

By Ian McIntyre

Malaysia

SMART Team leaves for Nepal today as search for 55 Malaysians continues

Diary

Mother Teresa - one of the foremost humanitarian figures of the 20th century died today, 29 years ago

You may be interested

Malaysia

Kepong MP challenges government over proposed hybrid SST-GST model

Malaysia

PM warns fertiliser firms of potential contract cancellations, orders MACC review

Malaysia

Malaysia’s SMART Team begins HADR mission in Nepal

Malaysia

HSA warns against interference in sexual harassment probe

Malaysia

Police probe alleged abuse of two-year-old at Mentakab nursery

Malaysia

Driver allegedly failed to notice cyclists before fatal car crash

Malaysia

Budget 2027 may bring new relief for squeezed M40

Malaysia

Puteri Umno distances itself from viral Threads post

By Alfian Z.M. Tahir