Malaysia

Sarawak to retender construction of Ba’kelalan CIQ complex: DCM

Datuk Awang Tengah Ali Hasan says project also needs review to rectify various issues

Updated 4 years ago · Published on 12 Nov 2021 10:53AM

Sarawak to retender construction of Ba’kelalan CIQ complex: DCM
Datuk Awang Tengah Ali Hasan says the Ba’kelalan Customs, Immigration, and Quarantine Complex is important as it serves as a gateway for the country, especially with Indonesia planning to shift its capital to Kalimantan. – Bernama pic, November 12, 2021

BA’KELALAN – Construction of the Ba’kelalan Customs, Immigration, and Quarantine (CIQ) Complex, which has been left abandoned since two years ago, will be retendered to get the project completed, said Sarawak Deputy Chief Minister Datuk Awang Tengah Ali Hasan.

He said the project, which was supposed to be completed in April 2019, also needed to be reviewed as several issues needed to be rectified, including weaknesses in the proposed building layout and slope safety issues.

“This is a really sick project…what is surprising is that there is no quarantine facility at the CIQ. There are also issues of slope safety, the parking area, and so on.

 “I hope the retendering process for this project will be decided quickly and the project can be continued and completed,” he said.

He said this when inspecting the project site in conjunction with his recent working visit to Ba’kelalan, which was also attended by Deputy Transport Minister Datuk Henry Sum Agong.

Awang Tengah said it was important that the project plan be reviewed to ensure all important agencies related to services at the country’s border could be located there.

“The original plan of the project only houses the Immigration office, the Customs Department, the Malaysian Volunteer Department and police, but there is no quarantine centre and also the Veterinary Department, which are very important.

“I hope this matter can be taken into account. This is a very important service and I want this project to facilitate travel to and from the Malaysia-Indonesia border,” he said.

He said the Ba’kelalan CIQ is important as it serves as a gateway for the country, especially with Indonesia planning to shift its capital to Kalimantan.

Based on the project plan under the 10th Malaysia Plan, involving an allocation of more than RM14 million, the Ba’kelalan CIQ will house an administrative block and a two-storey quarters, and was scheduled for completion in May 2019.

In April 2019, the project was classified as a sick project, as the work progress was delayed by 46.58%, following which the contractor was issued a termination notice in December 2020. – Bernama, November 12, 2021 

Related News

Malaysia / 2d

Haze in Serian enters emergency phase

Malaysia / 4d

Malaysia Day celebration to move indoors amid Sarawak haze

Malaysia / 6d

Haze: Emergency only in areas with API of 500, not the whole of Sarawak

Malaysia / 6d

Sarawak: EC to display proposed 17 new state assembly seats tomorrow

Malaysia / 6d

Air quality in 4 Sarawak areas hit hazardous levels

Opinion / 1w

Merdeka: This is our Malaysia – and you will not take it from us

Spotlight

Malaysia

Penang CM defends move by housing board, says enforcement is last resort

By Ian McIntyre

World

Anak Krakatau’s six eruptions recorded

Malaysia

Delivery rider's compassion turns RM14.50 meal into wave of public generosity

Malaysia

Sanusi’s gambling stance puts PAS manifesto under scrutiny

By Alfian Z.M. Tahir

Malaysia

Zahid’s game plan is opening up

Malaysia

Chew Jetty fire: Business owners lose everything in the blink of an eye

By Ian McIntyre

Malaysia

SMART Team leaves for Nepal today as search for 55 Malaysians continues

Diary

Mother Teresa - one of the foremost humanitarian figures of the 20th century died today, 29 years ago

You may be interested

Malaysia

US Embassy denies attempt to influence Malaysia’s political leadership

Malaysia

Electoral momentum, political pressure may be behind Zahid’s push for early polls, says analyst

By Alfian Z.M. Tahir

Malaysia

Zahid’s game plan is opening up

Malaysia

Loke: Keep Anwar as PM to complete reform agenda

Malaysia

Firefighters contain blaze near George Town’s Chew Jetty saving nearby petrol station

Malaysia

Eleven held over revenge machete attack on man in Perak

Malaysia

Serian air quality remains hazardous with API reading at 376

Malaysia

Driver allegedly failed to notice cyclists before fatal car crash