Left in the dark: Villagers say Banggi solar projects abandoned 

Under the Rural and Regional Development Ministry, Sabah Bersatu demands answers why projects left abandoned 

Updated 1 year ago · Published on 24 May 2025 4:02PM

Left in the dark: Villagers say Banggi solar projects abandoned 
The only thing that’s making their nights bright are diesel generators and candles. - May 24, 2025

by Jason Santos

VILLAGERS in Pulau Banggi and Pulau Balambangan near Kudat say they’re still waiting for the lights to come on - nearly eight years after a hybrid solar project was launched with the promise of powering their homes.

But today, the only thing that’s making their nights bright are diesel generators and candles. 

And even those don’t last long.

What’s left behind from the multi-million ringgit solar project are rusting panels, idle control rooms, and questions no one in authority seems to want to answer.

Sabah Bersatu now wants those questions addressed – starting with why the projects were left to rot.

The state women’s chief Rahimah Majid, who recently visited the affected sites, said the system was never fully installed and has since fallen into disrepair.

“The people have waited long enough. They were told the project would bring light. What they got was silence and scrap metal,” she said.

The projects – involving sites in Pulau Tanjung Manawali, Pulau Tigabu, Kampung Kok Simpul and Kampung Selamat – were supposed to bring hybrid solar energy to the remote island communities. 

Villagers say the works began around 2017 or 2018, but they have remained incomplete ever since.

The Rural and Regional Development Ministry is now led by Umno president and Deputy Prime Minister Datuk Seri Ahmad Zahid Hamidi – but Rahimah said the problem predates his time.

“The question is not who started it, but why it wasn’t finished,” she said. 

It cannot be ascertained but the projects may have begun during the tenure of either Datuk Seri Ismail Sabri Yaakob or Datuk Seri Rina Harun – who held the portfolio between 2015 and 2020.

“Zahid might not have started it, but he’s now responsible. It’s his ministry. If no one is answering the people, then who will?” said Rahimah. 

Pulau Banggi and Balambangan, located off the northern coast of Sabah, are some 180km from Kota Kinabalu. 

Both islands fall within the Kudat parliamentary constituency, long known for infrastructure gaps and persistent rural poverty.

Rahimah said the condition of the abandoned equipment is a “visible reminder” of how rural Sabah often falls off Putrajaya’s radar.

“The panels are there. The wiring is there. But nothing works. And no one’s maintaining it,” she said.

She’s now demanding that the ministry issue a full report – including project costs, contractor names, reasons for the delays, and a timeline for when the systems will finally be operational.

“This is public money. The people have a right to know how it was used – or wasted.”

Rahimah also called for a review of contractor performance and for punitive action to be taken if any elements of the project were mismanaged or abandoned without just cause.

“This isn’t about politics. It’s about accountability. The people of Banggi and Balambangan deserve better than half-baked promises and broken infrastructure.”

Zahid, in a recent statement, pledged to prioritise Sabah’s rural development. But Sabah Bersatu says that won’t mean much if unresolved failures like this continue to be ignored.

“Before you promise new projects, finish the ones you already started,” Rahimah said. - May 24, 2025 

Related News

Malaysia / 2w

Rosmah's solar project graft appeal postponed again

Malaysia / 1mth

After years of abandonment, Highland Towers to be demolished before year end

Malaysia / 3mth

Welfare homes almost full, government prioritises the elderly, destitute and abandoned

Malaysia / 4mth

175 babies saved from being abandoned from 2022 to 2025

Malaysia / 8mth

Penang CM shoots down talk that Penang Undersea Tunnel Project abandoned

Malaysia / 8mth

Typhoon Kalmaegi detected 405km northwest Of Kudat, Sabah - MetMalaysia

Spotlight

Malaysia

PRN Negeri Sembilan: The battlegrounds, big names and three-cornered fights to watch

By Alfian Z.M. Tahir

People

Woman ends up with RM500 over food bill after date with ‘doctor’

Malaysia

Love scam: Twelve China nationals arrested in Ipoh over suspected online call centres

Malaysia

ASLI to field female candidate in Jeram Padang DUN

Community

‘Furry officer’ laid to rest as Kuching traffic police mourn beloved stray cat (video)

By Alfian Z.M. Tahir

Malaysia

Father mauled by crocodile as son watches in horror in Sabah river (UPDATED)

Malaysia

Johor shuts down Forest City Network School premises

Malaysia

Singapore: Chief Justice Sundaresh Menon to retire in Feb 2027, succeeded by Justice Sushil Nair

You may be interested

Malaysia

Elderly fathers plead for help as sons vanish in suspected Southeast Asia scam networks

Malaysia

Dragon dance, drums welcome Tok Mat at nomination centre

Malaysia

PRN Negeri Sembilan: Four seats in focus, battle expected to be tougher than Johor

Malaysia

BN-PN pact in Negeri Sembilan polls centred on stability and full 36-seat victory target

Malaysia

Love scam: Twelve China nationals arrested in Ipoh over suspected online call centres

Malaysia

Johor shuts down Forest City Network School premises

Malaysia

Network School postpones new investments in Malaysia, seeks government guarantee

Malaysia

Negeri Sembilan polls enter race mode as 36-seat battle begins

By Alfian Z.M. Tahir