Developers of projects delayed pre-pandemic must pay compensation: Zuraida

Exemption only applies to delayed works between March and December last year, says housing minister

Updated 5 years ago · Published on 19 Feb 2021 5:26PM

Developers of projects delayed pre-pandemic must pay compensation: Zuraida
Housing and Local Government Minister Datuk Zuraida Kamaruddin says developers are still required to pay compensation or liquidated ascertained damages to buyers for any delayed projects that were supposed to be completed before March last year. – Bernama pic, February 19, 2021

JOHOR BARU – The exemption for the extension of time (EOT) as stipulated in the Covid-19 Act (Act 829) involving the Housing Development (Control and Licensing) Act 1966 is only applicable to housing projects that were supposed to be completed between March and December last year.

Housing and Local Government Minister Datuk Zuraida Kamaruddin said for any delayed projects that were supposed to be completed before March last year, developers are still required to pay compensation or liquidated ascertained damages to buyers.

“We provide this exemption for Covid-19 from March until December 2020. Only for that period. Other than that, they have to pay compensation.

“However, for delayed projects this year, we can consider (providing exemption) but they must have solid reasons. The consideration is only up to March 2021,” she told a press conference after handing over the keys to house buyers of Taman Seri Molek Perdana Phase 1 and PPR Taman Perling, Johor, here, today.

Zuraida was commenting on whether the exemption for compensation payments allocated in Act 829 is applicable to housing projects that were supposed to be completed before the pandemic hit the country.

The Covid-19 Act involving the Housing Development (Control and Licensing) Act 1966 is part of the Temporary Measures for Reducing the Impact of Coronavirus Disease 2019 (Covid-19) Act 2020, which was passed in the Dewan Rakyat in August last year.

Under the act, developers are given temporary protection for delayed works due to the movement control order since March 18, 2020, and they cannot be sued by buyers or banks for failing to complete their projects according to schedule. – Bernama, February 19, 2021

Related News

Malaysia / 1mth

Penang CM defends move by housing board, says enforcement is last resort

Malaysia / 2mth

Young voters could decide Johor election outcome as parties battle for new electorate

Malaysia / 3mth

PH launches 'Johor For All' manifesto, focuses on jobs, housing and people's well-being

Malaysia / 4mth

Covid-19 cases in Malaysia stable, no deaths recorded this year – MOH

Business / 4mth

Higher diesel prices raise construction costs by as much as 15%

Malaysia / 4mth

PBTs urged to consider rental cuts until year-end

Spotlight

Malaysia

Do not hide school safety issues to protect reputation - IGP

World

Flydubai pilot planned to crash plane into terminal at Ben Gurion Airport

Malaysia

Sabah Pan Borneo Highway: Only 4 of 35 packages complete after a decade

Malaysia

School caning was never abolished, Minster says

Malaysia

Sepang draws record crowd as Bahrain GP puts Malaysia back on F1 map

Malaysia

Irene Sofiya died from blunt-force head injuries, post-mortem confirms

Malaysia

No CCTV at spot where Irene was killed, says Minister

Malaysia

Irene’s only focus was her studies and her dream to become a doctor - aunt

You may be interested

Malaysia

Malaysia prepares for aged nation status by 2036

Malaysia

Sabah Pan Borneo Highway: Only 4 of 35 packages complete after a decade

Malaysia

Doctor loses RM33,500 after falling victim to Facebook online loan scam

Malaysia

Irene Sofiya died from blunt-force head injuries, post-mortem confirms

Malaysia

MASFIH urges diplomatic push with Nepal and China over 54 missing Malaysians

Malaysia

Anwar vows zero compromise on school safety after alleged murder of teen Irene Sofiya

Malaysia

No CCTV at spot where Irene was killed, says Minister

Malaysia

Sepang draws record crowd as Bahrain GP puts Malaysia back on F1 map