ECRL land-clearing: enforcement due to SOP breach, says S’gor MB’s aide

This was despite construction firm having secured permit for such works, Jay Jay Denis highlights

Updated 3 years ago · Published on 06 Feb 2023 9:00AM

ECRL land-clearing: enforcement due to SOP breach, says S’gor MB’s aide
A spokesman for China Communications Construction Company (M) Sdn Bhd tells The Vibes that the company had obtained all necessary approvals and permits from the relevant authorities to proceed with the land-clearing works for the East Coast Rail Link project. – Pic courtesy of Rimba Disclosure Project, February 6, 2023

by Qistina Nadia Dzulqarnain

KUALA LUMPUR – A Chinese construction company behind land-clearing works in Selangor’s forest reserves for the East Coast Rail Link (ECRL) project faced enforcement action last year for not abiding by standard operating procedures, according to state government staffer Jay Jay Denis.

China Communications Construction Company (M) Sdn Bhd (CCCC) had indeed secured a permit to work on the ECRL, but began work for that portion of the project in Selangor in December last year before receiving approval from the state Forestry Department.

“They (CCCC) thought that they could go ahead with work just because they have the permit, but they actually needed to make an application to the department to notify authorities that they will be starting work.

“This is so that the department can send personnel to the site to ensure that correct parts of the forests are being carved out,” he told The Vibes when contacted.

The special officer to Selangor Menteri Besar Datuk Seri Amirudin Shari added that the enforcement action taken against the company in December included a fine and a stop-work order which has since been lifted. 

“The company was notified in December that they will have to go through the right procedural channels to begin work in the future. 

“If (CCCC) had no permit to operate then, there would definitely have been further legal action, but the issue then was just that they did not provide a notice (to the department),” he said.

Selangor Menteri Besar Datuk Seri Amirudin Shari (pic) had earlier said that the land-clearing works in Selangor’s forest reserves were done ‘without approval’. Clarifying the matter, his aide Jay Jay Denis says that Amirudin was referring to a lack of approval from the state Forestry Department to begin clearing state land, not the absence of a permit to work on the project. – Bernama pic, February 6, 2023
Selangor Menteri Besar Datuk Seri Amirudin Shari (pic) had earlier said that the land-clearing works in Selangor’s forest reserves were done ‘without approval’. Clarifying the matter, his aide Jay Jay Denis says that Amirudin was referring to a lack of approval from the state Forestry Department to begin clearing state land, not the absence of a permit to work on the project. – Bernama pic, February 6, 2023

Denis’ comments come after state executive councillor Hee Loy Sian yesterday said that the department had issued a use permit in July 2022 for the implementation of the ECRL project in the permanent forest reserve area. 

The state Environment, Green Technology, Tourism and Orang Asli Affairs Committee chairman also said that the approval of the environmental impact assessment report for Section C2 (Gombak-Serendah-Port Klang) was obtained by Malaysia Rail Link Sdn Bhd, the Finance Ministry entity administering the ECRL project, on November 30, 2021. 

Amirudin, however, had earlier said that the land-clearing works in the state’s forest reserves were done “without approval”, noting that a police report was lodged against CCCC last December.  

Clarifying the matter, Denis said that Amirudin was referring to a lack of approval from the state Forestry Department to begin clearing state land, not the absence of a permit to work on the project.

Amirudin and Hee had been responding to environmental watchdog group Rimba Disclosure Project, which raised an alarm over the land clearing.

A spokesman for CCCC told The Vibes that the company had obtained all necessary approvals and permits from the relevant authorities to proceed with the project.

On December 21, Prime Minister Datuk Seri Anwar Ibrahim announced that the overall cost to complete the ECRL project is now RM74.96 billion, a RM11.01 billion reduction from the originally set price of RM85.97 billion when the project was launched in 2017.  

He said that the government will proceed with the project to construct the 665km-long rail system from Kota Baru in Kelantan to Port Klang in Selangor. – The Vibes, February 6, 2023

Related News

Malaysia / 1w

Selangor postpones National Sports Day celebrations due to haze

Malaysia / 1w

Bersama’s Selangor target difficult to achieve if party goes solo, says analyst

Malaysia / 3w

27 stations record unhealthy API readings; six locations in Selangor affected

Education / 1mth

Selangor to close schools if API readings exceed 200

Malaysia / 2mth

Putra Heights tragedy report expected to be released as early as October

Events / 2mth

Selangor turns focus to AI, semiconductors as Techsphere Summit returns

Spotlight

World

Kim Jong Un appears in state media photos after unverified death rumours

Malaysia

Anwar challenges Rafizi over corporate crime, asks why he stayed silent as minister

Malaysia

AKPS chief Mohd Shuhaily to be charged over alleged assault on two policemen

Malaysia

Year One pupil dies after breathing difficulties in Dengkil classroom

Malaysia

College student remanded for three days over alleged rape of underage girl

Sports & Fitness

Lee Zii Jia settles dispute with father, sister over company affairs

By Alfian Z.M. Tahir

Malaysia

Online scam call centres: Police detain 31 people targeting foreign victims in Pahang crackdown

Malaysia

Guan Eng proposes RM1,000 tax rebate for purchase of air purifiers

By Ian McIntyre

You may be interested

Malaysia

Tun M says grief still weighs on him after Siti Hasmah’s death

Malaysia

DKU seeks court action against Ismail, 16 others over Negeri Sembilan royal dispute

By Alfian Z.M. Tahir

Malaysia

Schools to reopen in 3 states as usual, outdoor activities suspended

Malaysia

MCMC warns cyberbullies, AI disinformation offenders as online safety comes under scrutiny

Malaysia

Husband of slain border agency officer has 16 previous criminal records

Malaysia

Hajiji urges GRS leaders to put Sabah first, warns against infighting

Malaysia

RM2.1b rural road overspending triggers contractor payment delays, new project freeze

Malaysia

PM orders faster rollout of Budget 2027 aid, warns against bureaucratic delays