S’wak govt vows to rescue all sick, abandoned infra projects by year-end

State deputy minister says contractors who failed to deliver being replaced

Updated 3 years ago · Published on 20 Jun 2023 4:41PM

S’wak govt vows to rescue all sick, abandoned infra projects by year-end
Long Busang Clinic, in the remote Belaga settlement of Long Busang, has been left uncompleted for the past eight years. – Pic courtesy of Abun Sui Anyit, February 3, 2023

by Stephen Then

MIRI – The Sarawak government has promised to rescue all sick and abandoned infrastructure projects in the state by the end of this year.

State Deputy Infrastructure Development and Ports Minister Aidel Lariwoo today said the state government aims to hire rescue contractors to complete these delayed projects.

Speaking at a press conference today in Kuching after a ministry event, he said by next year, the state aims for “zero sick project” status.

“We are terminating the contracts of contractors who had failed to deliver their projects. We are appointing rescue contractors for these sick projects,” he said.

“There is a long list of infrastructure projects in the state that have been delayed or abandoned.”

He said that the projects eyed for “rescue” are divided into two categories – under the state and under the federal government – and involve public infrastructure like bridges and roads.

Aidel stressed that the ministry had already replaced numerous contractors of failed projects with rescue contractors.

“These rescue contractors are doing a good job so far,” he said.

Many contractors had failed to deliver after being hit by escalating costs of raw materials like sand and steel, he explained. “The costs of these raw materials keep rising all the time. These contractors also faced problems caused by labour shortages.”

“During the Covid-19 period, many workers stopped working. The foreign workers left the state and they did not return even until now.

“So, there is a serious shortage of workers now and this makes the situation even more difficult,” he explained.

In August last year, the Public Works Department (PWD) had revealed in Kuching that it had identified 95 crucial projects worth RM10.357 billion throughout Sarawak that have been critically delayed or abandoned.

These projects included important infrastructure projects like government clinics, schools, teachers’ quarters, village roads and bridges, and also four packages of the Pan Borneo Highway.

The PWD, in a press statement, had then indicated the statistics above were current as of end of June last year.

The contractors for 18 of these delayed projects had been terminated from the work packages.

Among the crucial projects delayed was the Long Busang Clinic.

On July 12 last year, The Vibes had reported that the Long Busang Clinic, a crucial government clinic project that was launched eight years ago for the thousands of natives living in the upstream of the mega Bakun Dam in central Sarawak, had been abandoned and apparently forgotten.

Sarawak PKR information chief Abun Sui had told The Vibes the clinic was said to have cost RM3 million in government allocations.

The project was launched way back in 2015 by local politicians from the ruling government. The allocation came from the federal Health Ministry, but the construction was given to a local Sarawak contractor appointed by the PWD, he had said. – The Vibes, June 20, 2023

Related News

Education / 2w

Digital divide persists in Tamil schools despite Malaysia’s digital push, survey finds

Malaysia / 1mth

Abang Jo: Bintulu Port strengthens Sarawak’s position as strategic maritime, industrial hub

Malaysia / 1mth

Minister: Sarawak made right decision to reject entry of Rohingya refugees in 2017

Malaysia / 1mth

Sarawak seeks China collaboration to fix growing doctor shortage

Malaysia / 1mth

What matters: Policies that truly understand the rakyat

Malaysia / 2mth

Sarawak wants to take over several more strategic entities from the Federal Government

Spotlight

Malaysia

Anwar, Zahid project unity at Putrajaya amid PH-BN differences during state polls

By Alfian Z.M. Tahir

Malaysia

Police looking for two robbery suspects who kicked elderly woman (video)

Malaysia

Malaysia will not bow to US congressional pressure over Israeli nationals’ issue - Loke (UPDATED)

Malaysia

Deaf e-hailing driver sues government, police over alleged assault, seeks disability access reforms

By Alfian Z.M. Tahir

Malaysia

Johor appoints 10 deputy exco to strengthen administration

Malaysia

Suspended police corporal charged with sexual assault of 11-year-old daughter

Malaysia

Magnitude 5.7 earthquake off northern Sumatra felt across west coast of Peninsular Malaysia

World

Trump approves potential US-Saudi nuclear deal allowing uranium enrichment capability

Malaysia

Network School moves to Kazakhstan

You may be interested

Malaysia

Govt aligns GLIC investments with national development through GEAR-uP programme

Malaysia

Muhyiddin rejects Khaled’s 'kacau daun' jibe, says Bersatu is in Negeri to win

Malaysia

Govt embarks on RM1.49B flood mitigation projects in Sabah as high-risk areas receive priority

Malaysia

UMNO-Amanah spar over BN-PN ties as Unity Government tensions escalate

Malaysia

Magnitude 5.7 earthquake off northern Sumatra felt across west coast of Peninsular Malaysia

Malaysia

Sabah assembly approves RM1.6b Supplementary Supply Bill to fund additional spending

Malaysia

Tuition teacher sentenced to 105 years in prison and 70 lashes for raping daughter

Malaysia

Hajiji withdraws remark against Kapayan rep following request in Sabah assembly