Malaysia

Hot wheels: Johor Baru’s BRT ready to go by 2025

Cost for Iskandar Rapid Transit to be ten times cheaper than Klang Valley LRT lines

Updated 2 years ago · Published on 15 Sep 2023 8:30AM

Hot wheels: Johor Baru’s BRT ready to go by 2025
Map of the three lines and 22 stations of the Iskandar Rapid Transit or Bus Rapid Transit in Johor Baru. Deemed as the backbone of the Iskandar region’s revamped public transport system, the 55km high-capacity dedicated bus lane is set to feature three lines, namely Iskandar Puteri with 15km stretch, Skudai (18km), and Tebrau (22km). – SHAHRIM TAMRIN/The Vibes pic, September 15, 2023

by Shahrim Tamrin

KOTA ISKANDAR – After much delay over the years, Johor Baru’s Bus Rapid Transit (BRT) is targeted for stage-one operation rollout by the third quarter of 2025.

Deemed as the backbone of the Iskandar region’s revamped public transport system known as Iskandar Rapid Transit (IRT), the 55km high-capacity dedicated bus lane is set to feature three lines, namely Iskandar Puteri with 15km stretch, Skudai (18km), and Tebrau (22km).

The Iskandar Regional Development Authority (IRDA) has allocated solar-powered 22 stations on the three BRT lines, comprising ten stations on Tebrau as well as eight and four stations on Skudai and Iskandar Puteri respectively.

It is forecast that the rebranded IRT network will record 302,824 passengers daily by 2030, and are more economical than the construction and operation expenditures of the LRT lines in Klang Valley.

In the next 25 months, it will be the third BRT system in the country after the elevated line in Sunway and Kuching Urban Transportation System, which is currently conducting a trial of its autonomous rail transit vehicle. 

At present, 187 cities worldwide have adopted the BRT system.

A model of Perling BRT Station. It is forecast that the rebranded Iskandar Rapid Transit network will record 302,824 passengers daily by 2030, and are more economical than the construction and operation expenditures of the LRT lines in Klang Valley. – SHAHRIM TAMRIN/The Vibes pic, September 15, 2023
A model of Perling BRT Station. It is forecast that the rebranded Iskandar Rapid Transit network will record 302,824 passengers daily by 2030, and are more economical than the construction and operation expenditures of the LRT lines in Klang Valley. – SHAHRIM TAMRIN/The Vibes pic, September 15, 2023

On Monday, Prime Minister Datuk Seri Anwar Ibrahim announced in Parliament that the expansion of IRT, which includes the BRT and intra-city bus services in Johor Baru, is part of the eleven new logistic and transportation projects under the 12th Malaysia Plan.

The federal-funded BRT transit development in the Iskandar region may cost up to RM2.5 billion, a total combination of the expenditure for infrastructure (RM1.2 billion) and procurement for the new high-capacity electric buses and systems (RM1.3 billion).

It is learned that the infrastructure cost took into account the RM180 million land acquisitions for the 65 acres in UTM Skudai, Desa Jaya, Medini and some pockets of spaces along Skudai Highway.

IRDA has also designated three interchange stations at Taman Tasek, Komtar and Sultanah Aminah Hospital.

It is understood that the Public Works Department and Works Ministry have given greenlight for the low-floor stations – 80m in length and 7m wide – to be constructed on the three federal roads.

With the exception of the Komtar station at 150m length, this will be the main transit point, with a stone’s throw distance to the proposed Rapid Transit Station at Bukit Chagar, eight minutes from the Customs, Immigration and Quarantine complex at the Sultan Iskandar Building and a 170m connection to the Johor Baru Sentral Railway Station.

The proposed site of Anjung BRT station. It is learned that the infrastructure cost took into account the RM180 million land acquisitions for the 65 acres in UTM Skudai, Desa Jaya, Medini and some pockets of spaces along Jalan Skudai. – SHAHRIM TAMRIN/The Vibes pic, September 15, 2023
The proposed site of Anjung BRT station. It is learned that the infrastructure cost took into account the RM180 million land acquisitions for the 65 acres in UTM Skudai, Desa Jaya, Medini and some pockets of spaces along Jalan Skudai. – SHAHRIM TAMRIN/The Vibes pic, September 15, 2023

Cost-effective 

The Johor Baru BRT system is regarded as a cost-effective high-impact project in comparison to the rail-based projects in Greater Kuala Lumpur, such as the RM30 billion MRT1 or RM577 mil/km and LRT3 at RM489 mil/km.

According to the IRDA, the cost to build BRT networks that include infrastructure, buses and supporting systems is estimated at RM50 million per km or between seven to 10 times lower than the rail mode.

The Vibes understands that the IRT revamped bus network is aiming for 90% penetration with the target to reach 2.25 million population in 2030 and beyond.  

IRDA’s head of infrastructure for the IRT project, Ezani Mohamad, delivered a briefing for G7-grade interested contractors vying for the contracts of the Package 2 and 3 at the Sultan Ismail Building here recently.

“We will also be organising outreach programmes for the stakeholders situated within the 500m radius of the proposed stations,” he told The Vibes.

A model of Perling BRT Station. It is stipulated that 60 companies have bid for the construction of BRT Package 1 (lane and stations) that will commence work in November on the Sultan Iskandar Highway. – SHAHRIM TAMRIN/The Vibes pic, September 15, 2023
A model of Perling BRT Station. It is stipulated that 60 companies have bid for the construction of BRT Package 1 (lane and stations) that will commence work in November on the Sultan Iskandar Highway. – SHAHRIM TAMRIN/The Vibes pic, September 15, 2023

Ezani said park and ride facilities have been identified at UTM, Medini, Anjung, and Desa Jaya, with several malls and public parking lots along the three lines.

It is stipulated that 60 companies have bid for the construction of BRT Package 1 (lane and stations) that will commence work in November on the Sultan Iskandar Highway.

A briefing session for Package 4 and 5 will be held on 20 September, with a closing date in the second week of October.

“Works shall begin one and a half month after the closing date of each package,” Ezani added. – The Vibes, September 15, 2023

Related News

Malaysia / 2y

TikTok user raises ire, mocks musical performance

Malaysia / 2y

JB woman loses RM350,000 to investment scam

Malaysia / 3y

Nepali man drowns after falling into lake while collecting golf balls

Malaysia / 3y

Govt seeks location for non-subsidised fuel station in JB

Malaysia / 3y

Johor Baru, Kluang districts to get two new PPRs this year

Malaysia / 3y

Wee steps down as Johor Baru MCA head

Spotlight

Malaysia

Aminuddin denies abandoning Sikamat

Malaysia

BN-PN cooperation talks revive questions over political loyalty as PAS shifts closer to Umno

By The Vibes Says

Malaysia

Malaysian teen held in Hong Kong with RM260k cannabis haul believed to be drug mule

World

Starmer bids farewell as UK PM ahead of Labour leadership handover

Malaysia

BNPL users hit eight million as outstanding balances reach RM5.3b

Malaysia

KWAP fell victim to eFishery scam, invested nearly RM200 million - PM Anwar

Malaysia

Penang signs landmark Perak water deal to secure 40-year supply from 2032

Malaysia

PRN Negeri Sembilan: Hopes of KJ becoming MB dashed as name not on candidate list

World

US strikes Iranian missile sites as Tehran warns of wider energy disruption

Malaysia

Bersatu to contest Negeri polls under own logo as Muhyiddin blasts PAS-BN tie-up

Malaysia

“There are traitors among us waiting to topple Aminuddin” - Loke

You may be interested

Malaysia

Police seek Interpol Red Notice for Tamim Dahri over religious provocation probe

Malaysia

Police detect shift in Rohingya entry routes as small boats target coastal areas

Malaysia

Sabah Education Dept probes Tawau student brawl as police detain eight teens

Malaysia

KWAP fell victim to eFishery scam, invested nearly RM200 million - PM Anwar

Malaysia

Dewan Rakyat passes National Trust Fund Bill 2026

Malaysia

BN-PN cooperation talks revive questions over political loyalty as PAS shifts closer to Umno

By The Vibes Says

Malaysia

Govt assesses nuclear, biomass and geothermal options to strengthen low-carbon energy security

Malaysia

Dewan Rakyat passes Statistics Bill 2026 to strengthen data governance, evidence-based policymaking