Company records RM226.7 million revenue, RM5.7 million profit before tax in first three months of the year

Updated 5 years ago · Published on 31 May 2021 6:16PM

MRCB’s Q1 2021 performance impacted by slower construction progress due to virus-affected lower productivity
MRCB’s 50%-owned LRT3 project joint-venture company contributed a profit after tax of RM5.9 million, compared with RM1.2 million in the corresponding period in 2020. – MRCB LRT3 website pic, May 31, 2021

KUALA LUMPUR – Malaysian Resources Corporation Bhd (MRCB) recorded a 47% decline in revenue to RM226.7 million, and a 79% decline in profit before tax to RM5.7 million, in the first three months of 2021 compared with the corresponding period in 2020, which was spared the full impact of the Covid-19 movement control order that came into force in the last two weeks of the first quarter of 2020.

The decline in Q1 2021 was further exacerbated by the residual impact of multiple construction site closures undertaken as a precautionary measure when Covid-19 cases were detected towards the end of 2020.

This not only hampered construction progress in 2020, but also had a resultant impact on construction progress and billings in Q1 2021.

The property development and investment division recorded a 44% decline in revenue to RM132.2 million, and a 46% decline in operating profit to RM13.1 million, in Q1 2021, compared with RM236.4 million and RM24.2 million, respectively, in the corresponding period in 2020.

The stronger performance recorded in 2020 was mainly due to the commencement of revenue recognition from 1060 Carnegie. However, while sales rates for the 1060 Carnegie project remain high, the speed of reaching a financial settlement for the units sold has only just started to pick up, following the lifting of travel limit restrictions in late 2020, thus impacting recognition in Q1 2021.

The division saw higher contributions from Sentral Suites at KL Sentral and TRIA 9 Seputeh, which recorded a 12% and 169% increase in revenue, respectively, in Q1 2021, compared with the corresponding period in 2020, as construction progressed further.

The division sold RM51.6 million worth of properties in Q1 2021 and had unbilled property sales of RM1.0 billion.

The engineering, construction and environment division recorded a revenue of RM84.4 million and operating loss of RM1.6 million in Q1 2021.

Revenue was mainly contributed by the Employees Provident Fund headquarters at Kwasa Sentral, Damansara-Shah Alam Elevated Highway Package CB2, Mass Rapid Transit Line 2 Package, and Sg Besi-Ulu Klang Elevated Expressway Package CA2.

The lower revenue and profit recorded in Q1 2021 was largely due to deferred revenue recognition resulting from multiple site closures at several project construction sites towards the end of 2020, as well as most of the group’s large infrastructure construction projects nearing completion, when recognition of revenue and profits are minimal.

The group’s 50%-owned Light Rail Transit Line 3 project joint-venture company contributed a profit after tax of RM5.9 million, compared with RM1.2 million in the corresponding period in 2020. – The Vibes, May 31, 2021

Related News

Malaysia / 6d

CPJ calls for withdrawal of excessive RM100m defamation suit against veteran journalist

Culture & Lifestyle / 1y

Ipoh Sentral developer urged to complete recreational park - an important green lung in Perak

Business / 3y

MRCB becomes fifth-time gold winner at Australasian Reporting Awards

Business / 3y

MRCB’s unit to dispose of Menara CelcomDigi in Petaling Jaya

Business / 3y

MRCB Q1 performance impacted by project completions

Business / 3y

EPF CEO Amir Hamzah now MRCB’s new chairman

Spotlight

World

Series of explosions, fires hit three southern Thai provinces

Opinion

One more temple falls: The destruction of Malaysia’s soul?

Opinion

Why is Israel pushing toward confrontation with Türkiye?

Malaysia

‘Uncle Anwar’ sends representative to children’s entrepreneurs day in Subang Jaya

Malaysia

‘Look at temple dispute based on facts and laws’ – DAP reps tell Rayer

By Alfian Z.M. Tahir

Malaysia

Malaysia, Brunei set deadline to demarcate boundary, enhance border security

Malaysia

Police probe indecent act allegedly targeting woman in Sungai Petani

Malaysia

Sarawak postpones three major programmes over haze concerns

You may be interested

Business

Govt rules out RM7.5b Datasonic takeover amid identity security concerns