Penang’s water cut ends, but its battle against ageing infrastructure continues

Over RM1 bil set aside to modernise water system, undertake contingency measures, says CM.

Updated 2 years ago · Published on 14 Jan 2024 8:00PM

Penang’s water cut ends, but its battle against ageing infrastructure continues
Penang Chief Minister Chow Kon Yeow meets consumers in Balik Pulau. – IAN MCINTYRE/The Vibes pic, January 14, 2024.

by Ian McIntyre

THE UNPRECEDENTED scheduled water disruption that lasted up to four days in some parts of Penang ended at about 4.30am today after the Penang Water Supply Corporation (PBAPP) restored supply to all of the 590,000 accounts affected earlier.

However, there are still some areas, particularly in Balik Pulau, which continue to encounter low pressure due to inhouse pumping issues and the fact that the underwater pipe at Sg Perai is only pumping at mid-level due to another leak along the line at the bottom of the river.

Chief Minister Chow Kon Yeow and state executive councillor Zairil Khir Johari, who oversees the infrastructure portfolio, were busy visiting areas in Balik Pulau affected by low pressure due to the Sg Perai incident.

They visited the Flat Lily, Flat Taman Sri Indah, Flat Focus Height dan Flat Hijau at Taman Desa Genting to ensure that despite the low pressure, residents there were getting help from water tankers and Fire and Rescue Department volunteer groups.

Chow said that the full restoration came as the Hindu community celebrated the Ponggal festival, a symbolic celebration of harvest, today.

“I hope that this disruption would not dampen the celebrations for Ponggal, and soon we are set to celebrate Thaipusam and Chinese New Year. We hope that this resumption amidst the crisis we just weathered wouldn’t dampen the spirits of Penangites.”

The immediate goal of PBAPP now is to install two pipes to divert water from the riverbed pipe to one above the water surface, running parallel to the Ampang Jajar Bridge in Butterworth, Chow said.

The riverbed pipe continues to function temporarily pending the major water works of installing the two pipes.

He expects the repair works to be completed within the next 21 days.

More remedial works

Chow stressed that the battle to produce reliable water delivery services is at the top of the state’s agenda with over RM1 billion set aside to modernise its water system and to undertake contingency measures in view of a disruption to the raw water intake.

But the National Water Services Commission (SPAN) is urging Penang to undertake more remedial works on its aged piping and to actively source for alternative sources.

SPAN chairman Charles Santiago spoke of rainwater harvesting, reclaiming of wastewater and storage of pond water.

He also urged Penangites to lower their consumption, which is the highest in the country, as conservation is the way forward in fighting climate change.

The scheduled water cuts for crucial repairs and upgrading received much criticism by community leaders and civil society alike but eventually, Penang prevailed as it went without a glitch, except for the constant leakage of the riverbed pipeline at Sg Perai.

PBAPP pulled out all stops to upgrade two 1,200mm main valves at the Sg Dua main water treatment plant and conducted ancillary works at 22 other locations.

However, it is learnt that all is not rosy at PBAPP, as there was a difference of opinion over how to mitigate the pipe leaks at Sg Perai.

A former state executive councillor lamented that Penang is mired with too much bureaucracy and shifting of blame.

This may hamper future dealings of the PBAPP, which must now upgrade its services to meet the growing demand amidst higher public expectations after the 96-hour water cut, the former executive councillor said. – The Vibes, January 14, 2024

Related News

Tech / 1d

Penang’s Tech Dome celebrates 10th anniversary with opening of new space gallery

Malaysia / 4d

No further delays for water tariff hike in Penang - CM

People / 5d

Penang: Greater efforts needed to record historical events, says nonagenarian

People / 5d

Penang: Eurasian association mourns sudden loss of its president

Malaysia / 5d

Penang signs landmark Perak water deal to secure 40-year supply from 2032

Malaysia / 6d

Penang: Sandbags as temporary measure to curb erosion at Batu Ferringhi

Spotlight

Malaysia

After Johor, the uncomfortable question for Anwar’s critics: Were we too impatient?

By The Vibes Says

Malaysia

Network School's business licences revoked, to cease operations tomorrow

Opinion

Orang Asli in Pahang: Token gestures or genuine recognition?

Malaysia

Tuition teacher sentenced to 105 years in prison and 70 lashes for raping daughter

Malaysia

Azam Baki denies involvement in RM178.29 million contract linked to brother’s company

Malaysia

Aminuddin urges NS voters to weigh manifesto promising benefits for M40 and B40 groups

Malaysia

No need to resign, PM has absolute power if there is doubt – Ahmad Zahid

World

Gaza’s water crisis deepens as families face thirst, disease and collapsing sanitation systems

You may be interested

Malaysia

Anwar: Malaysia’s debt ratio is falling, but legacy debt payments remain a heavy burden

Malaysia

Who is Sarah? What we know about the Malaysian lawyer at the centre of the Karim Khan case

Malaysia

eFishery loss will not jeopardise KWAP’s finances or pension payments - Tengku Zafrul

Malaysia

Tengku Ampuan Pahang offers land to Orang Asli families affected by Sungai Cot land dispute

Malaysia

Sabah seeks additional RM1.61b allocation to fund state operations and development needs

Malaysia

Federal Govt passes RM83.46m in flood mitigation, coastal protection projects to Selangor

Malaysia

Man killed in hit-and-run crash while installing party flags in Rantau

Malaysia

Saifuddin: Immigration Dept on track to exceed RM5b revenue target this year