ECRL Rail Project reaches over 81 per cent completion along Kota Bharu–Selangor corridor

Major infrastructure development on track for full completion by end-2026, with testing slated to begin mid-next year

Updated 1 year ago · Published on 17 Apr 2025 4:13PM

ECRL Rail Project reaches over 81 per cent completion along Kota Bharu–Selangor corridor
The work progress of the 43-kilometre alignment in Kelantan has reached 88.86 per cent, contributing significantly to the overall advancement of the project – April 17, 2025

MALAYSIA’s flagship East Coast Rail Link (ECRL) project has passed a significant milestone, with over 81 per cent of construction completed along its 665-kilometre alignment stretching from Kota Bharu in Kelantan to Selangor, putting the project firmly on course for completion by December 2026.

Chief executive officer of Malaysia Rail Link Sdn Bhd (MRL), Datuk Seri Darwis Abdul Razak, confirmed the progress figure following an inspection of works at the Pasir Puteh ECRL Station site on Thursday. He praised the Kelantan state government for its proactive support in land acquisition and stakeholder engagement.

“The work progress of the 43-kilometre alignment in Kelantan has reached 88.86 per cent, contributing significantly to the overall advancement of the project,” he said. “Testing and commissioning activities are expected to begin in June 2026.”

Kelantan’s two ECRL stations, located in Tunjong and Pasir Puteh, are advancing steadily, with construction progress at 69 and 68 per cent respectively. Both are on track for completion by May 2025.

Darwis also reported positive developments in track-laying works throughout the 400-kilometre segment spanning Kelantan, Terengganu and parts of Pahang. Regionally, construction progress stands at 90 per cent in Terengganu and 86 per cent in Pahang.

The ECRL, one of Malaysia’s most ambitious transport infrastructure undertakings, will link the east coast states of Kelantan, Terengganu and Pahang with Selangor on the west coast, providing faster and more efficient connectivity across Peninsular Malaysia.

The project’s Kota Bharu to Gombak Integrated Terminal stretch is scheduled to be fully completed by the end of 2026 and will commence operations in January 2027.

Addressing local concerns, Darwis noted that engagement sessions with residents, the Land and District Office, local authorities and the Kelantan state government have helped resolve several issues, including recurring flash floods in Pasir Puteh.

“We are committed to resolving every issue to ensure that this project benefits the people and can be completed on schedule,” he said. – April 17, 2025

Spotlight

Malaysia

Anwar: Children’s smiles, dreams are Malaysia’s future (video)

Heritage

Penang first state to recognise Hungry Ghost Festival, cemeteries as heritage

Malaysia

Child malnutrition needs urgent action, says Charles Santiago

By Alfian Z.M. Tahir

Malaysia

Zahid: Umno, BN favour earlier GE16

World

Trump floats renaming Strait Of Hormuz ‘Trump Strait’ amid Iran conflict

Malaysia

Weak earthquake measuring 3.4 magnitude detected in Keningau

Malaysia

Stepfather held over alleged rape, sexual assault of 13-year-old in Besut

Malaysia

Toying with danger: Police tracking owner of MPV

You may be interested

Malaysia

UMNO’s future in Unity Government hangs on PAU decision

By Alfian Z.M. Tahir

Malaysia

Penang secures more than RM17b investments for first half of 2026

By Ian McIntyre

Malaysia

Accountant charged over alleged RM2.53m tax under-reporting

Malaysia

Anwar: Children’s smiles, dreams are Malaysia’s future (video)

Malaysia

Woman injured as concrete debris falls from George Town heritage building

Malaysia

SRC seeks RM42m from Najib, says he controlled company through multiple roles

Malaysia

MOF: Unsubsidised petrol, diesel prices fall five sen from Thursday

Malaysia

Former Tabung Haji COO’s charges put off after hospital admission

By Alfian Z.M. Tahir