Malaysia

ECRL Rail Project reaches over 81 per cent completion along Kota Bharu–Selangor corridor

Major infrastructure development on track for full completion by end-2026, with testing slated to begin mid-next year

Updated 1 year ago · Published on 17 Apr 2025 4:13PM

ECRL Rail Project reaches over 81 per cent completion along Kota Bharu–Selangor corridor
The work progress of the 43-kilometre alignment in Kelantan has reached 88.86 per cent, contributing significantly to the overall advancement of the project – April 17, 2025

MALAYSIA’s flagship East Coast Rail Link (ECRL) project has passed a significant milestone, with over 81 per cent of construction completed along its 665-kilometre alignment stretching from Kota Bharu in Kelantan to Selangor, putting the project firmly on course for completion by December 2026.

Chief executive officer of Malaysia Rail Link Sdn Bhd (MRL), Datuk Seri Darwis Abdul Razak, confirmed the progress figure following an inspection of works at the Pasir Puteh ECRL Station site on Thursday. He praised the Kelantan state government for its proactive support in land acquisition and stakeholder engagement.

“The work progress of the 43-kilometre alignment in Kelantan has reached 88.86 per cent, contributing significantly to the overall advancement of the project,” he said. “Testing and commissioning activities are expected to begin in June 2026.”

Kelantan’s two ECRL stations, located in Tunjong and Pasir Puteh, are advancing steadily, with construction progress at 69 and 68 per cent respectively. Both are on track for completion by May 2025.

Darwis also reported positive developments in track-laying works throughout the 400-kilometre segment spanning Kelantan, Terengganu and parts of Pahang. Regionally, construction progress stands at 90 per cent in Terengganu and 86 per cent in Pahang.

The ECRL, one of Malaysia’s most ambitious transport infrastructure undertakings, will link the east coast states of Kelantan, Terengganu and Pahang with Selangor on the west coast, providing faster and more efficient connectivity across Peninsular Malaysia.

The project’s Kota Bharu to Gombak Integrated Terminal stretch is scheduled to be fully completed by the end of 2026 and will commence operations in January 2027.

Addressing local concerns, Darwis noted that engagement sessions with residents, the Land and District Office, local authorities and the Kelantan state government have helped resolve several issues, including recurring flash floods in Pasir Puteh.

“We are committed to resolving every issue to ensure that this project benefits the people and can be completed on schedule,” he said. – April 17, 2025

Spotlight

Malaysia

Man found dead on massage chair

Education

Haze: Schools in Johor to reopen this Monday

Malaysia

Police looking for owner and driver of car spotted with two men on it

Malaysia

Farhash files defamation suit against Rafizi

Malaysia

Melaka PRN: Only seven seats for PAS-PN, says Zahid

Community

Sim reaches out to man who needed a wheelchair in Kelantan

By Ian McIntyre

Malaysia

Selangor Sultan urges younger generation to unite, become knowledgeable individuals

World

UK MP seeks legal safeguards against AI likenesses created without consent

World

Seven dead, 34 injured in church attack in southern Jordan

You may be interested

Malaysia

Serian records Malaysia’s highest API reading as haze hits Sarawak and Johor

Malaysia

Farhash files defamation suit against Rafizi

Malaysia

Post-mortem finds no internal injuries on man who died in police custody

Malaysia

Melaka PRN: Only seven seats for PAS-PN, says Zahid

Malaysia

Anwar: US$50b tech investment could create higher-value jobs for Malaysians

Malaysia

Minister urges police reports over upside-down Jalur Gemilang protest in Australia

Malaysia

Indonesia seizes 1.16 tonnes of ketamine from tanker in Strait of Malacca

Malaysia

Perak headmaster transferred amid probe into alleged inappropriate messages to student