Putra Heights Fire: Final pipe section to be removed within a week - Police

Three sections of pipe totalling 16 metres from the damaged pipeline have been extracted, and efforts are underway to remove the final section

Updated 1 year ago · Published on 30 Apr 2025 6:46PM

Putra Heights Fire: Final pipe section to be removed within a week - Police
Unstable soil condition due to rain is a factor which slows down operations - April 30, 2025

WORK to remove the pipeline sections affected by the gas pipeline fire in Putra Heights, Subang Jaya, on April 1 is expected to take another week, said Selangor police chief Datuk Hussein Omar Khan.

Bernama cited Hussein saying today that so far, three sections of pipe totalling 16 metres from the damaged pipeline have been extracted, and efforts are underway to remove the final section, estimated to be five metres long, for analysis.

"For the investigation at ground zero, I estimate we’ll need another week to remove the final section so that the Department of Occupational Safety and Health (DOSH) can complete its investigation.

"Specifically, DOSH will need to carry out lab analyses with the help of SIRIM for material testing and several other assessments to determine the cause of the explosion. After that, the site will be handed over to Petronas for recovery works, which are expected to take several months," he said.

He was speaking at a press conference after visiting the ground zero site with nearly 50 media personnel this afternoon.

Hussein also said unpredictable weather had complicated the ongoing investigation work at the site.

He noted that over the 28 days of investigation since April 1, it had rained on 20 of those days, disrupting progress at the scene.

“Each time it rains, the investigation work has to be paused, and we need almost half a day to pump out the water collected in the crater before we can resume excavation.

“The unstable soil condition due to rain is another factor slowing down operations,” he said.

He added that the Minerals and Geoscience Department (JMG) would also produce a report to assist DOSH, including soil sampling to assess the ground structure at the site.

Hussein also said authorities had located an excavator reported to have been buried on the day of the fire.

“Roughly, we already know its location, and it is outside the area we are currently digging. Excavating the excavator now would interfere with ongoing work at the centre of ground zero.

“We can’t dig in several areas at once, so once the pipe analysis and investigations at the centre of ground zero are completed, we will cover that area and then begin excavation at the excavator’s location,” he said. - April 30, 2025

Spotlight

Malaysia

Anwar: Children’s smiles, dreams are Malaysia’s future (video)

Heritage

Penang first state to recognise Hungry Ghost Festival, cemeteries as heritage

Malaysia

Child malnutrition needs urgent action, says Charles Santiago

By Alfian Z.M. Tahir

Malaysia

Zahid: Umno, BN favour earlier GE16

World

Trump floats renaming Strait Of Hormuz ‘Trump Strait’ amid Iran conflict

Malaysia

Weak earthquake measuring 3.4 magnitude detected in Keningau

Malaysia

Stepfather held over alleged rape, sexual assault of 13-year-old in Besut

Malaysia

Toying with danger: Police tracking owner of MPV

You may be interested

Malaysia

Child malnutrition needs urgent action, says Charles Santiago

By Alfian Z.M. Tahir

Malaysia

Rosmah solar corruption appeal sent back to High Court for fresh evidence

Malaysia

Four teenagers feared drowned at Tanjung Lompat

Malaysia

Cloud seeding targets Sarawak dams amid heat and dry spell

Malaysia

MOF: Unsubsidised petrol, diesel prices fall five sen from Thursday

Malaysia

Retiree loses RM1.4m in phone scam after fraudsters pose as authorities

Malaysia

Collision between tanker and ferry under investigation - PPC

By Ian McIntyre

Malaysia

Anwar: Children’s smiles, dreams are Malaysia’s future (video)