PM inspects LCS construction in Lumut, progress reaches 72.43 per cent as of May

First Littoral Combat Ship enters setting-to-work phase, with sea trials scheduled for December 2025

Updated 1 year ago · Published on 15 Jun 2025 1:17PM

PM inspects LCS construction in Lumut, progress reaches 72.43 per cent as of May
The ministry confirmed that the first vessel, LCS1, was successfully downslipped into the water on 23 May, in accordance with the contractual schedule - June 15, 2025

PRIME MINISTER Datuk Seri Anwar Ibrahim paid a working visit to the Lumut Naval Shipyard (LUNAS) at the Royal Malaysian Navy (TLDM) base in Lumut today to review the progress of the Littoral Combat Ship (LCS) project.

Accompanied by Deputy Defence Minister Adly Zahari and Chief of Defence Forces General Tan Sri Mohd Nizam Jaffar, the Prime Minister was briefed on the status of the five LCS vessels currently under construction for TLDM.

According to a statement from the Ministry of Defence, the overall progress of the project had reached 72.43 per cent as of 25 May.

Bernama cited the ministry adding that strict monitoring involving key stakeholders including the Ministry of Finance, Ministry of Economy, Implementation Coordination Unit of the Prime Minister's Department, and the Attorney General’s Chambers is ongoing to ensure proactive intervention measures are implemented by LUNAS to keep the project on schedule.

The ministry confirmed that the first vessel, LCS1, was successfully downslipped into the water on 23 May, in accordance with the contractual schedule.

“LCS1 has entered the setting-to-work (STW) phase as of May 2025 and is scheduled to undergo its first sea sailing in December this year,” the statement said.

LCS2, which was launched into the water on 8 May, is continuing with construction and is expected to begin STW activities by September.

Construction of LCS3 through LCS5 is reportedly proceeding according to plan, with LCS3 expected to be delivered to the Royal Malaysian Navy in 2027. Each subsequent vessel will follow at intervals of eight months, with LCS5 scheduled for completion in 2029. - June 15, 2025

Spotlight

Off beat

Afdlin Shauki, family trapped for five hours amid Paris unrest

Malaysia

10 former Negeri Excos file application in Federal Court to challenge revocation of appointments

Malaysia

Perlis MB Abu Bakar suspended from Bersatu for two election terms

Malaysia

Shuhaily says public support gives him strength as he faces two charges

Malaysia

Mohd Shuhaily pleads not guilty to assaulting 2 cops

Places

Penang makes National Geographic list of top 25 cities worldwide to visit

By Ian McIntyre

Malaysia

Two held after 16-year-old girl rescued in suspected sex exploitation case

Malaysia

Takiyuddin blames Bersatu for PN deregistration

Malaysia

Interpol issues Red Notice for Serba Dinamik CEO, Anwar says

You may be interested

Malaysia

No bailout commitment for AirAsia despite fuel-cost pressures, Putrajaya says

Malaysia

Government open to RCI into KWAP, EPF if evidence warrants probe

Malaysia

College student remanded for three days over alleged rape of underage girl

Malaysia

Father arrested over suspected rape of 13-year-old daughter in Ranau

Malaysia

Woman’s RM4,000 childbirth bill drops to RM130 with blood donor benefits

Malaysia

Interpol issues Red Notice for Serba Dinamik CEO, Anwar says

Malaysia

Ship fuel emissions: ‘Do not overlook public health’ – experts

Malaysia

Lecturer takes RM218k in loans before losing RM269,993 to phone scam