PM inspects LCS construction in Lumut, progress reaches 72.43 per cent as of May

First Littoral Combat Ship enters setting-to-work phase, with sea trials scheduled for December 2025

Updated 1 year ago · Published on 15 Jun 2025 1:17PM

PM inspects LCS construction in Lumut, progress reaches 72.43 per cent as of May
The ministry confirmed that the first vessel, LCS1, was successfully downslipped into the water on 23 May, in accordance with the contractual schedule - June 15, 2025

PRIME MINISTER Datuk Seri Anwar Ibrahim paid a working visit to the Lumut Naval Shipyard (LUNAS) at the Royal Malaysian Navy (TLDM) base in Lumut today to review the progress of the Littoral Combat Ship (LCS) project.

Accompanied by Deputy Defence Minister Adly Zahari and Chief of Defence Forces General Tan Sri Mohd Nizam Jaffar, the Prime Minister was briefed on the status of the five LCS vessels currently under construction for TLDM.

According to a statement from the Ministry of Defence, the overall progress of the project had reached 72.43 per cent as of 25 May.

Bernama cited the ministry adding that strict monitoring involving key stakeholders including the Ministry of Finance, Ministry of Economy, Implementation Coordination Unit of the Prime Minister's Department, and the Attorney General’s Chambers is ongoing to ensure proactive intervention measures are implemented by LUNAS to keep the project on schedule.

The ministry confirmed that the first vessel, LCS1, was successfully downslipped into the water on 23 May, in accordance with the contractual schedule.

“LCS1 has entered the setting-to-work (STW) phase as of May 2025 and is scheduled to undergo its first sea sailing in December this year,” the statement said.

LCS2, which was launched into the water on 8 May, is continuing with construction and is expected to begin STW activities by September.

Construction of LCS3 through LCS5 is reportedly proceeding according to plan, with LCS3 expected to be delivered to the Royal Malaysian Navy in 2027. Each subsequent vessel will follow at intervals of eight months, with LCS5 scheduled for completion in 2029. - June 15, 2025

Spotlight

Malaysia

Four teenagers feared drowned at Tanjung Lompat

World

Thailand to halve visa-free stay to 30 days for 60 countries from Sept 15

Malaysia

Woman injured as concrete debris falls from George Town heritage building

Malaysia

Collision between tanker and ferry under investigation - PPC

By Ian McIntyre

Malaysia

Anwar’s six measures offer relief across the everyday economy

By Alfian Z.M. Tahir

Malaysia

Mahathir’s Merdeka appearance sparks social media debate

By Alfian Z.M. Tahir

You may be interested

Malaysia

FMM urges fast-track access as government expands SME micro-financing to RM6b

Malaysia

Desa ParkCity family lodged no police report over alleged love scam

Malaysia

Sarawak haze crisis deepens as five areas breach hazardous air quality levels

Malaysia

77 Malaysians brought to Kathmandu for repatriation as 55 remain unaccounted for

Malaysia

Anwar warns US-Iran escalation risks wider Middle East war

Malaysia

Reform agenda takes shape as government pushes ahead with wider changes

By The Vibes Says

Malaysia

VVIP could be first charged in Tabung Haji RCI probe

Malaysia

Zahid: Umno, BN favour earlier GE16