Six major flood mitigation projects in Malaysia reported behind schedule

PETRA confirms delays in six priority Flood Mitigation Plan projects, outlining interim measures and funding of RM556.6 million to protect affected communities

Updated 7 months ago · Published on 22 Jan 2026 12:33PM

Six major flood mitigation projects in Malaysia reported behind schedule
Setbacks largely stem from land-related complications, including acquisition disputes and encroachments, as well as the need to relocate existing utilities - January 22, 2026

SIX high-priority flood mitigation projects under Malaysia’s Rancangan Tebatan Banjir (RTB) have fallen behind schedule, the Ministry of Energy Transition and Water Transformation (PETRA) confirmed in Parliament today.

Responding to a question from Tuan Shaharizukirnain Abd. Kadir, Member of Parliament for Setiu, Deputy Prime Minister Datuk Seri Fadillah Yusof detailed that of 43 nationwide RTB projects identified as high-priority, 37 are proceeding according to plan, while six projects – RTB Sungai Solok, RTB Likas, RTB Baling Phase 2, RTB Sungai Maran, RTB Sungai Klang Section 25, and RTB Sungai Damansara – have experienced delays as of December 2025.

Fadillah, who also serves as the Minister of Energy Transition and Water Transformation (PETRA). explained that these setbacks largely stem from land-related complications, including acquisition disputes and encroachments, as well as the need to relocate existing utilities.

Delays in obtaining technical approvals from multiple agencies, extreme weather conditions, and extraordinary flood events have further impacted progress at construction sites.

“PETRA takes these delays seriously and has implemented measures to improve governance of project execution,” Fadillah stated.

Initiatives include closer and more frequent monitoring of project progress, rescheduling of work plans, enforcement of contractual terms with penalties for underperforming contractors, and intensified coordination with state governments and local authorities to expedite approvals and resolve field-level issues.

While awaiting the completion of the RTB projects, PETRA, through the Department of Irrigation and Drainage (JPS), has prioritised short-term mitigation measures to protect communities in severely affected areas.

These interventions are being carried out under the River Conservation Project to Reduce Flood Risks, which encompasses river channel works, riverbank stabilisation, and upgrades to related drainage structures.

Between 2022 and 2025, a total of RM556.6 million was allocated nationwide to implement these smaller-scale mitigation works, targeting high-risk areas identified at the state level.

The ministry’s disclosure highlights both the scale of Malaysia’s flood mitigation efforts and the challenges of executing major infrastructure projects amid complex logistical, regulatory, and environmental constraints. - January 22, 2026

Spotlight

Malaysia

Elderly man admits to hitting neighbour with iron rod

Malaysia

Body found at KLIA2 in tyre storage compartment of aircraft from Japan

Malaysia

Factory operator faces rape, unnatural sex charges involving polytechnic student

Malaysia

Ismail Sabri granted RM300k bail after pleading not guilty to asset declaration charge

By Alfian Z.M. Tahir

Malaysia

Sunway Lagoon ride halted as safety probe seeks to protect public - DOSH

Malaysia

Malaysia ready to deploy military expertise for Nepal flood relief, says Defence Minister

Malaysia

Violence in Thailand: Visitors drop by almost 50 per cent

By Ian McIntyre

You may be interested

Malaysia

MACC detains former Tabung Haji chairman, Treasury sec-gen

By Alfian Z.M. Tahir

Malaysia

‘Stop playing games and get your facts right’ – Ramkarpal tells Sanusi

By Ian McIntyre

Malaysia

Kedah braces for potential hundreds of millions in gambling claims

Malaysia

PH-BN talks on Melaka election cooperation may take shape before Malaysia Day

Malaysia

PAC set to scrutinise concerns raised by RCI over TH

By Alfian Z.M. Tahir

Malaysia

Air pollution worsens as 19 areas record unhealthy readings

Malaysia

Body found at KLIA2 in tyre storage compartment of aircraft from Japan

Malaysia

Anwar orders universities to drop disciplinary cases against students over criticism