PAC to probe Sabah Pan Borneo Highway delays despite RM10.5b spent

Only four of 35 work packages have been completed despite RM10.547 billion being spent and the completion deadline pushed back to 2030

Updated 48 minutes ago · Published on 19 Oct 2026 3:11PM

PAC to probe Sabah Pan Borneo Highway delays despite RM10.5b spent
The Parliament’s Public Accounts Committee will investigate financial management, governance and construction delays in the Sabah Pan Borneo Highway Phase 1 project - October 19, 2026

THE Public Accounts Committee (PAC) will investigate how RM10.547 billion was spent on the Sabah Pan Borneo Highway Phase 1 project, with only four of its 35 work packages completed despite the project being scheduled for completion in 2021.

PAC chairman Datuk Mas Ermieyati Samsudin said the inquiry would examine project management, financial governance and physical progress, including why existing monitoring mechanisms had failed to prevent prolonged delays.

She said the committee would scrutinise how project payments were approved when construction progress on the ground did not correspond with the amount of public funds spent.

PAC will call witnesses from the Works Ministry, the Public Works Department (JKR), including JKR Sabah, as well as other relevant agencies and parties to give evidence.

“PAC will not hesitate to refer its findings to the Malaysian Anti-Corruption Commission (MACC) and the Royal Malaysia Police for further investigation if the proceedings uncover any indications of misconduct, corruption or abuse of power,” she told a press conference at Parliament today.

Mas Ermieyati said the inquiry followed findings in the Auditor-General’s Report Series 2/2026, which highlighted weaknesses in public fund management, non-compliance with financial rules, excessive expenditure linked to poor project management and significant delays.

The Sabah Pan Borneo Highway Phase 1 project comprises 35 work packages covering 706km and was originally scheduled to be completed within 69 months, with the deadline set for the end of 2021.

However, only four packages, or 11.4%, have been completed, while the remaining 31 packages, valued at RM16.319 billion, are still under implementation.

Of those remaining packages, nine have been classified as sick projects and 13 are behind schedule, while nine are ahead of schedule.

Mas Ermieyati said RM10.547 billion, equivalent to 94.6% of the RM11.153 billion allocated, had been spent between 2016 and March 31 this year despite the project’s physical progress lagging significantly.

The completion deadline has since been extended to 2030, while the overall contract cost has risen to RM18.394 billion from RM17.910 billion.

She said PAC was committed to conducting an independent, transparent and comprehensive inquiry to ensure public funds were spent prudently, responsibly and in accordance with regulations. - October 19, 2026

Spotlight

Malaysia

Papagomo acquitted for second time in sedition case over government, Israel claims

Malaysia

ECRL fares start at RM60, with 50% discounts for children, seniors and OKU

Malaysia

DKU seeks court action against Ismail, 16 others over Negeri Sembilan royal dispute

By Alfian Z.M. Tahir

Malaysia

Kampung Manis: Dreams of 227 families to own replacement homes draw closer

Malaysia

Fadhlina takes legal action over video of 2023 Parliament speech

By Alfian Z.M. Tahir

Malaysia

Civil servants urged to turn Selangor Sultan’s anti-graft message into action

Malaysia

Animal welfare group urges probe into alleged sexual abuse of cat in viral video

Malaysia

Macron appeals for calm after France riots: 2,400 arrested, nearly 1,000 officers injured

Malaysia

Malaysia renews offer to help Indonesia fight fires

You may be interested

Malaysia

Tun M says grief still weighs on him after Siti Hasmah’s death

Malaysia

Kampung Manis: Dreams of 227 families to own replacement homes draw closer

Malaysia

Sarawak deputy premier warns of increasing threats of vaping

Malaysia

Ab Rauf: BN to weigh public sentiment before deciding Melaka election pact

Malaysia

Woman arrested after headless baby found in Terengganu drain

Malaysia

Drug cases involve 75% of Malaysia’s 90,000 prison inmates - Home Minster

Malaysia

Man remanded for allegedly chasing wife with 62cm parang

Malaysia

UM denies disciplinary action against student over Najib, Tabung Haji remarks