Penang aims to settle undersea tunnel feasibility study by Q2 2021

Once state exco, committee clears it, detailed design of mega project will start, says Zairil Khir Johari

Updated 5 years ago · Published on 21 Jan 2021 2:10PM

Penang aims to settle undersea tunnel feasibility study by Q2 2021
A feasibility study for Penang's undersea tunnel project started in December 2014 and was supposed to be completed in 2016 but was delayed due to various reasons. – MATHIS SARAWANAN/The Vibes pic, January 21, 2021

by Sofia Nasir

GEORGE TOWN – The Penang government wants all matters related to the approval of a feasibility study for the controversial RM6.3 billion undersea tunnel project to be sorted out before the second quarter of this year.

State Transport and Infrastructure Committee chairman Zairil Khir Johari said the project delivery partner for the tunnel and three highways projects, Consortium Zenith Construction (CZC), had completed the study last month.

However, the presentation of the study to the state executive council and technical committee has been postponed due to the implementation of movement control order (MCO).

“It should be presented to the technical committee first, but because of the MCO, there is a slight delay,” he said.

"I hope all matters related to this feasibility study can be completed before the second quarter of 2021," he told The Vibes.

"After completing the feasibility study, we will continue with the detailed design of the undersea tunnel."

The feasibility study started in December 2014 and was supposed to be completed in 2016 but had been delayed due to various reasons.

CZC presented the draft feasibility report in September 2019 and it was amended with improvements based on reviews by various agencies.

In July last year, the Malaysian Anti-Corruption Commission (MACC) reopened its investigation into the undersea tunnel project in Penang, following new evidence linked to the matter.

The mega project has courted various objections, particularly involving the RM305 million feasibility study and delay of its original scheduling.

Based on the original plan, the project includes four main components, namely three main roads along a 30km stretch and the undersea tunnel between Gurney Drive on the island and Bagan Ajam on the mainland. – The Vibes, January 21, 2021

Related News

People / 21h

Prevention and early detection vital to reduce NCD rates, says Penang Exco

Community / 3d

More attention needed to care for the aged, says consumer association

Malaysia / 3d

Declining birth rate among the Chinese community worrying, says Penang Exco

Community / 5d

Penang introduces self-service cutlery return initiative at food court

Community / 5d

Penang urged to plant new trees before felling those deemed rotten

Community / 6d

Burst pipe affects 130,790 consumers in Penang

Spotlight

Malaysia

Papagomo acquitted for second time in sedition case over government, Israel claims

Malaysia

ECRL fares start at RM60, with 50% discounts for children, seniors and OKU

Malaysia

DKU seeks court action against Ismail, 16 others over Negeri Sembilan royal dispute

By Alfian Z.M. Tahir

Malaysia

Kampung Manis: Dreams of 227 families to own replacement homes draw closer

Malaysia

Fadhlina takes legal action over video of 2023 Parliament speech

By Alfian Z.M. Tahir

Malaysia

Civil servants urged to turn Selangor Sultan’s anti-graft message into action

Malaysia

Animal welfare group urges probe into alleged sexual abuse of cat in viral video

Malaysia

Macron appeals for calm after France riots: 2,400 arrested, nearly 1,000 officers injured

Malaysia

Malaysia renews offer to help Indonesia fight fires

You may be interested

Malaysia

DKU seeks court action against Ismail, 16 others over Negeri Sembilan royal dispute

By Alfian Z.M. Tahir

Malaysia

Fifty-four missing Malaysians’ families may get relief as Nepal weighs faster death certificates

Malaysia

Housewife loses RM472k in phone scam after fraudsters threaten arrest

Malaysia

M40 cost-of-living aid, online safety among key questions in Parliament

Malaysia

Tun M says grief still weighs on him after Siti Hasmah’s death

Malaysia

Animal welfare group urges probe into alleged sexual abuse of cat in viral video

Malaysia

Selangor palace urges public to verify royal links amid alleged land, luxury car scam

Malaysia

Father, daughter killed after container crushes car in Sabah