7 years on, RM2.3 bil Sabah dam only on paper

Contractor lacks money for preliminary job in Upper Padas despite Putrajaya’s RM569 million soft loan

Updated 5 years ago · Published on 01 Oct 2020 9:00AM

7 years on, RM2.3 bil Sabah dam only on paper
The Padas river passes through the interiors of Beaufort, Keningau and Tenom. The Upper Padas hydroelectric project is earmarked at the Padas basin around Kuala Tomani in Tenom. – Pic courtesy of Uwe Aranas/Wikipedia, October 1, 2020

by Emmanuel Samarathisa

KOTA KINABALU – A RM2.3 billion small hydroelectric dam in Sabah that was scheduled to be completed last year has yet to be built as the appointed contractor tasked to undertake preliminary work lacked funds, people familiar with the matter tell The Vibes.

The Upper Padas hydroelectric project was mooted in 2013 under then energy, green technology and water minister Datuk Seri Maximus Ongkili and was scheduled for completion by 2019. Then Sabah chief minister was Tan Sri Musa Aman.

Putrajaya also approved a RM569 million soft loan for state utility company Sabah Electricity Sdn Bhd (SESB) for an equity injection into a special purpose vehicle or consortium tasked to undertake the project.

But initial work has yet to kick off, sources say. 

“No physical work has been done because the contractor does not have enough money to start the project.” 

The source declined to name the said contractor. It is also not known whether this contract was awarded directly or through open tender.

Sources said many parties had been lobbying for shares if a consortium was set up and that SESB’s role was only for preliminary work. The utility company would then sell the concession to a third party, but “the project has stalled for some time”, an insider said.

The project is supposed to be at the Padas basin around Kuala Tomani in Tenom. The plant would have a capacity of 180MW and involve a water catchment area of only 590ha or 2.3ha per megawatt.

A map of the hydroelectric master plan for Sabah. – The Vibes pic, October 1, 2020
A map of the hydroelectric master plan for Sabah. – The Vibes pic, October 1, 2020

For comparison, in Sarawak, the Bakun hydroelectric project requires up to 29ha per megawatt of power generated and the Murum dam needs 26ha per megawatt.

Power generation in Malaysia’s easternmost state has been challenging on all fronts. Aside from topography, which naturally impedes the construction of large-scale hydroelectric dams, insiders said other problems such as corruption, theft and politics have scuttled any meaningful discussions for reforms.

Sabah has the highest power disruption in the country with a system average interruption disruption index (Saidi) of 267 minutes/year/customer compared to 50 m/y/c and 112 m/y/c in Peninsular Malaysia and Sarawak respectively, according to Energy Commission data.

Interruptions are its worst in the remote corners of Sabah, such as Pitas and Tambunan, which happen to be among the poorest areas, with a Saidi of 302.63 m/y/c.

SESB is also financially distressed. The utility company’s current liabilities (RM2.11 billion) have exceeded its current assets (RM1.91 billion) for FY19, a red flag for a business to continue as a going concern.

Further, SESB defaulted on an RM304.9 million loan with Putrajaya as at December 31, therefore accruing a RM13.1 million penalty. SESB is currently negotiating with the federal government on the delay and penalty.

It also lacks sufficient cash or assets to fund its short-term debt. SESB held RM285.99 million of dry powder at the end of December last year, which is insufficient to even cover operating expenses at RM1.79 billion. – The Vibes, October 1, 2020

Related News

Malaysia / 4d

Sabah embarks on five-year initiative to document multiethnic heritage - Hajiji

Malaysia / 5d

Anwar - Sabah's special grant interim payment increased from RM600m to RM1.5b

Malaysia / 6d

Anwar to clarify Sabah 40 pct entitlement talks tomorrow

Malaysia / 1w

Sabah: GRS confident government will agree to review revenue entitlement rate 

Malaysia / 1w

Main Sandakan-Lahad Datu road in Sukau collapses, thousands of users affected

Malaysia / 3w

SLS supports Sabah's move to delay implementation of border control law

Spotlight

Business

Tycoon Vincent Tan trims BCorp stake further in RM115m share sale

Malaysia

UMNO’s solo gamble in Johor: A show of strength or risky miscalculation?

By The Vibes Says

Malaysia

Nik Aziz’s grandson allegedly slapped by senator: Father ready to take case to court

Malaysia

Lorry driver jailed a day, fined for making obscene gestures, dangerous driving (video)

Malaysia

PKR leader defends MyKhas access suspension for PJ, Subang MPs, cites ‘political choices’

Opinion

Social media set to dominate Johor polls as election kingmaker

Malaysia

Man charged in Butterworth parang attack case that left victim fearing permanent disability

Malaysia

Teen mothers must return to school, says Fadhlina as education remains priority

Malaysia

Penang water tariffs to increase from July 1 after year-long deferment

You may be interested

Malaysia

King Sultan Ibrahim urges new MACC chief to uphold highest integrity in fight against corruption

Malaysia

Minor earthquake shakes Kundasang as residents report feeling tremors

Malaysia

PKR leader defends MyKhas access suspension for PJ, Subang MPs, cites ‘political choices’

Malaysia

Police capture wanted organised crime suspect in cross-border operation with India and Thailand

Malaysia

Woman pleads guilty to causing death of newborn daughter

Malaysia

King calls for people-centred development in KL

Malaysia

Man who wanted to borrow RM500k, scammed of over RM400k

Malaysia

Lorry driver jailed a day, fined for making obscene gestures, dangerous driving (video)