Bukit Goh mining nod resurrects 2015 pollution horror, but lauded by locals

EIA report, Kuantan MP warn of potential environmental ruin; project supporters say villagers need income, strict SOPs will keep problems at bay

Updated 4 years ago · Published on 14 Jul 2021 9:00AM

Bukit Goh mining nod resurrects 2015 pollution horror, but lauded by locals
A map of the proposed bauxite mining area in Pahang’s Bukit Goh. – KenEp Consultancy & Services pic, July 14, 2021

by Arjun Mohanakrishnan

KUALA LUMPUR – Following an environmental impact assessment (EIA) report sighted by The Vibes, the Pahang government has approved a bauxite mining project in Bukit Goh, Kuantan.

This is despite backlash from 2015 to 2016, when an environmental disaster saw the state capital suffering water and soil pollution.

The EIA carried out by KenEp Consultancy & Services Sdn Bhd raised concerns about the project awarded to BG Mining Sdn Bhd.

The report highlights the main activities to be conducted during the mining operations, including clearing vegetation on the site; excavating bauxite ore; washing bauxite; and, loading and transporting the mineral to Kemaman Port.

These activities will have an environmental impact, said the report, among them soil erosion, and the associated sediment pollution and siltation; loss of topsoil; loss of flora, fauna and habitats; air pollution due to the dust generated and dispersed during earth-moving operations; noise pollution; and, hydrological changes.

MP voices opposition

It is due to these reasons that Kuantan MP Fuziah Salleh is against the project.

“Remember in 2015? The whole bauxite fiasco that saw Kuantan turning into another version of Mars also involved the current area in Bukit Goh where the mining project is slated to be carried out. Back then, the rivers went from Class 3 to Class 5,” she told The Vibes.

According to the Pahang Irrigation and Drainage Department, a Class 5 river is polluted to the point that its water is unusable.

Kuantan MP Fuziah Salleh reminds that the ‘bauxite fiasco’ of 2015 saw the Pahang capital resembling ‘another version of Mars’. – Fuziah Salleh Facebook pic, July 14, 2021
Kuantan MP Fuziah Salleh reminds that the ‘bauxite fiasco’ of 2015 saw the Pahang capital resembling ‘another version of Mars’. – Fuziah Salleh Facebook pic, July 14, 2021

Fuziah said such pollution is possible if raw bauxite is processed and washed on-site.

“Because the project is on Bukit Goh, the washing of bauxite could cause the (polluted) water to run downhill into nearby rivers.

“And if they decide to transport raw bauxite – meaning, it will be processed elsewhere – then there is a possibility of red earth flying around.”

The EIA lists mitigation measures, including steps to avoid river pollution.

The report recommends a “Closed-Circuit Water Recirculation System” as a primary way to prevent discharge from tailing ponds.

“The water level shall be measured at the final tailing pond to indicate the water level. An on-site environmental officer shall inspect and record the water level daily,” it said.

"When the water level reaches the benchmark during a rainfall event, immediate action shall be taken to pump water to the processing plant to prevent overspill into the nearest river.”

Bauxite dust will adversely impact forest

Former Malaysian Nature Society president Tan Sri Salleh Mohd Nor also expressed concern about the project, particularly with regard to air pollution and its impact on the nearby Bukit Kuantan Forest Reserve.

Asked about the kind of effects that air pollution caused by mining will have on flora, he said the consequences will be seen in the long term.

“Air pollution (from bauxite) will have a negative impact on photosynthesis. This is due to leaves potentially being affected by the dust.

“It will affect the flowering of plants and change their physiology in the long term.”

In turn, he said, other species, such as insects and moss, will be forced to adapt to these changes.

Some 40% of Kg Felda Bukit Goh residents have land on the proposed bauxite mining site. – KenEp Consultancy & Services pic, July 14, 2021
Some 40% of Kg Felda Bukit Goh residents have land on the proposed bauxite mining site. – KenEp Consultancy & Services pic, July 14, 2021

Mine a much-needed income source for villagers

However, the project has its supporters, too.

For example, residents of Kg Felda Bukit Goh who have land on the project site are promised by the state government a cut of the mining proceeds.

Village head Jefri Salim said so far, there is no timeline for when the project will start.

“Villagers have no source of income as the oil palm trees are old and can’t be harvested any more. So, they are hoping for the mining project (to take off).”

There are some 600 people living in Kg Felda Bukit Goh, he said, and 40% of them have land in the mining area.

Despite hopes for operations to begin, Jefri said there are still concerns.

“It seems like the Pahang State Development Corp (PKNP), which is the trustee of the project and a state government company, is focused only on the EIA and contractor.

“The project covers 3,642ha and PKNP has elected BG Mining as the contractor, but they shouldn’t focus on having just one contractor for such a big project.”

Sg Lembing rep Datuk Md Sohaimi Mohamed Shah believes strict SOPs on mining operations will prevent environmental issues from arising. – Dato Hj Md Sohaimi Facebook pic, July 14, 2021
Sg Lembing rep Datuk Md Sohaimi Mohamed Shah believes strict SOPs on mining operations will prevent environmental issues from arising. – Dato Hj Md Sohaimi Facebook pic, July 14, 2021

Sg Lembing assemblyman Datuk Md Sohaimi Mohamed Shah said he would like mining to continue in Bukit Goh.

“A lot of them (Kg Felda Bukit Goh residents) are affected because they can’t get an income from palm oil.”

Even if the site is suitable to replant oil palm trees, he said, this is impossible as the land is legally tied to mining.

On environmental worries, he believes strict standard operating procedures (SOPs) are enough to prevent problems from arising.

“Before this, there were a lot of gaps and weaknesses that caused issues, leading to complaints from the public.

“So, if mining is to resume, it must be done with strict SOPs in place.”

He said if raw bauxite is to be transported by lorries, it must be guaranteed that red earth and other debris are not released into the environment.

“In terms of water, I think we have a system. If the rivers are affected, steps must be taken immediately to rectify the issue.” – The Vibes, July 14, 2021

Related News

Malaysia / 1mth

Private Amirul's death: Police have called 16 witnesses

Malaysia / 2mth

Be patient, exercise caution when driving home for Aidilfitri - Pahang Sultan

Malaysia / 2mth

King drives over 45km to inspect environment in Mersing

Malaysia / 4mth

Doctor loses RM285k in phone scam

Malaysia / 4mth

Do not turn a blind eye to environmental issues, cautions former minister

Our Planet / 6mth

Green activist urges hotels to adopt Asean Green Ratings

Spotlight

Business

Tycoon Vincent Tan trims BCorp stake further in RM115m share sale

Malaysia

UMNO’s solo gamble in Johor: A show of strength or risky miscalculation?

By The Vibes Says

Malaysia

Nik Aziz’s grandson allegedly slapped by senator: Father ready to take case to court

Malaysia

Lorry driver jailed a day, fined for making obscene gestures, dangerous driving (video)

Malaysia

PKR leader defends MyKhas access suspension for PJ, Subang MPs, cites ‘political choices’

Opinion

Social media set to dominate Johor polls as election kingmaker

Malaysia

Man charged in Butterworth parang attack case that left victim fearing permanent disability

Malaysia

Teen mothers must return to school, says Fadhlina as education remains priority

Malaysia

Penang water tariffs to increase from July 1 after year-long deferment

You may be interested

Malaysia

Minor earthquake shakes Kundasang as residents report feeling tremors

Malaysia

Retiree loses nearly RM100k in TikTok investment scam after fraudsters target pension savings

Malaysia

Toh Puan Na'imah’s legal team cautions against ‘dangerous’ application of SOSMA

Malaysia

METMalaysia urges calm after tremors felt across Sabah, Sarawak following minor earthquakes

Malaysia

'I was once spat on by a pakcik' — Marina denies fear of contesting Malay-majority seats

Malaysia

King calls for people-centred development in KL

Malaysia

Bersama to join the battle in Johor state election

Malaysia

NS election speculation intensifies as Aminuddin granted audience with state ruler