Penang govt, Gerakan clash over cost of Bukit Kukus highway

Latest project expenditure stands at RM545 mil, almost twice as high as original quote

Updated 5 years ago · Published on 23 Oct 2021 8:29PM

Penang govt, Gerakan clash over cost of Bukit Kukus highway
Penang Infrastructure and Transport exco Zairil Khir Johari says the Penang Island City Council will incur RM275 million and this cost has not increased despite the project’s delay. – Roketkini.com pic, October 23, 2021.

GEORGE TOWN – The Penang government and opposition Gerakan have locked horns over the cost of the Paya Terubong Twin Road (Jalan Bukit Kukus) project.

State infrastructure and transport exco Zairil Khir Johari today lashed back at state Gerakan chief Oh Tong Keong for not being “eloquent” about the matter.

This was after Oh had earlier in a statement accused Zairil of trying to hide the facts regarding the highway expenditure and criticised the state government for not being transparent when announcing the cost.

“In May 2014, the former Penang chief minister Lim Guan Eng announced that MBPP (Penang Island City Council) and private developers would jointly bear the project cost of RM300 million. Zairil recently announced that the cost of the project is RM545 million. 

“Isn’t the cost estimate announced by Zairil almost twice as high as the cost estimate announced by Lim Guan Eng?” questioned Oh. 

He said people are confused and wonder if there is any ulterior motive to why there is a different cost for the project each time an announcement is made.

In his rebuttal, Zairil explained that it is a three-part project implemented by different parties, namely PLB Land Sdn Bhd, Geo Valley Sdn Bhd and MBPP. 

“In terms of cost, the MBPP division will incur RM275 million and this cost has not increased despite the project’s delay,” he said in a statement.

“RM545 million is the total cost of the project, including the parts implemented by the private sector.”

Zairil, who is DAP assemblyman for Tg Bungah, responded that Oh does not understand the description of the construction project in terms of percentage calculated based on time and quantity of work set. 

“If the work completion period is extended via EOT (extension of time), then of course the percentage of work progress will also change. This calculation is common in all construction projects,” he said in a statement.

To date, the progress level under the MBPP division is at 96% and is expected to be completed by year-end.

The latest EOT until the end of the year has been given to contractors due to issues such as land acquisition, slope stabilisation work, utility diversion, landslides at worksites, and problems related to the movement control order since 2020. 

Thus, part of Jalan Bukit Kukus built by MBPP is expected to be open to road users by year-end. – The Vibes, October 23, 2021

Related News

Malaysia / 20h

PRN Melaka: DAP set to retain four Melaka seats, unofficial results show

Malaysia / 3d

Clean your own backyard first before asking others to clean theirs – DAP MPs tell UMNO

Malaysia / 2w

Sarawak’s snap polls: A clean sweep for Abang Jo’s GPS?

Malaysia / 1mth

Loke slams 10 Negeri Exco members for ‘backstabbing’ Tuanku Muhriz

Malaysia / 1mth

BN planning for a ‘walkover’ in the coming Melaka election?

Malaysia / 1mth

Anwar asks Loke to reconsider resignation over Najib pardon

Spotlight

Malaysia

Loke urges PM to focus on reforms, not early election pressure

Malaysia

Melaka declares special holiday tomorrow, in recognition of the people's mandate

Malaysia

Ab Rauf retains Melaka leadership

Malaysia

Mahathir makes first major party appearance since Hasmah's death at Pejuang AGM

Malaysia

Perak Sultan warns against shielding rulers from people's grievances

Malaysia

Retiree loses RM80k after WhatsApp investment scam demands RM50k to release profits

Health

Selangor health clinics prioritise emergency cases regardless of patients’ nationality

Malaysia

Some 243,501 undocumented migrants sent home under Malaysia's repatriation programme

Malaysia

Police hunt 38-year-old man over fatal stabbing in Kota Kinabalu

You may be interested

Malaysia

Police probe into alleged Nvidia chip diversion launched in April 2025 – Saifuddin

Malaysia

Negeri MB confirms withdrawal of letter to  Malay Rulers

Malaysia

MCMC warns public against scams involving impersonation of commission officials

Malaysia

Magnitude 5.2 earthquake hits off Sumatra coast

Malaysia

Malaysians face RM10 annual penalty for late first MyKad applications

Malaysia

23 million vehicles do not have flood insurance - PIAM

Malaysia

IGP: Police arrest nearly 97,000 foreigners for crimes over 33 months

Malaysia

Selective outrage over corruption puts political, religious principles under scrutiny