Pan Borneo Highway: 16 work packages now 75% complete

Deputy works minister says two packages now open to road users while 13 will be ready early 2025

Updated 3 years ago · Published on 06 Jun 2023 3:14PM

Pan Borneo Highway: 16 work packages now 75% complete
Deputy Works Minister Datuk Seri Abdul Rahman Mohamad has told the Parliament that 16 work packages in Phase 1 of the Pan Borneo Highway are being implemented at they are at 75% completion. – Bernama pic, June 6, 2023

KUALA LUMPUR – A total of 16 work packages in Phase 1 of the Pan Borneo Highway project are being implemented and currently, the progress status is at 75%, the Dewan Rakyat heard today.

Deputy Works Minister Datuk Seri Abdul Rahman Mohamad said of the total, two work packages are already opened to road users, while 13 work packages are expected to be completed by early 2025. 

“As for the status of a new work package, namely Work Package 9 involving the route from Serusop to Pituru, it is expected to be implemented as early as the second quarter of 2023, as such, 16 work packages are being implemented for now. 

“The government is committed to ensuring that the Pan Borneo Highway project continues to be implemented and to that end, RM2 billion has been allocated each year where RM1 billion goes to the Sabah Pan Borneo Highway and Sarawak Pan Borneo Highway projects respectively,” he said 

He said this in reply to a question from Mordi Bimol (Mas Gading-PH) who wanted to know the latest status, the time taken to complete the Pan Borneo Highway project in Sabah and Sarawak, as well as the government’s commitment to reduce accidents along the route under construction. 

For the 10 work packages from Sematan to Miri, Abdul Rahman said the entire alignment would be completed in November 2023 except for some sections in Miri that need to be reconstructed which could only be completed in 2025. 

In addition, he said the remaining 19 work packages (Phase 1B) that have yet to start would be financed in a hybrid manner using development allocations and through the issuance of sukuk or bonds by DanaInfra Nasional Berhad. 

“This Pan Borneo Highway Sabah Phase 1B project will be implemented with a construction period of 5 years, and is expected to start as early as in the third quarter of 2023, subject to the approval of the central agency,” he said. 

On the government’s commitment to reduce accidents along the routes under construction, he said the Works Ministry and the Public Works Department of Sabah and Sarawak would continue to monitor the areas to ensure the safety and comfort of road users. – Bernama, June 6, 2023

Related News

Opinion / 3w

The Malaysia Agreement 1963: Grievances and expectations in Sabah and Sarawak

Malaysia / 4w

Budget 2027: Sabah, Sarawak to receive RM34.9b in federal allocations next year

Events / 1mth

Sarawak and Sabah play key roles in weathering climate change

Malaysia / 1mth

Address security concerns and let concert proceed – former Sabah CM

Malaysia / 1mth

A message from our publisher and chairman

Malaysia / 1mth

Sabah leaders condemn priest and nun joke at UMNO PAU

Spotlight

Business

Ringgit gains as oil prices plunge on hopes of Iran conflict de-escalation

Events

UKM to establish academic research platform named after Dr Wan Azizah

Malaysia

Deepavali preparations destroyed as flash floods inundate Sungai Buloh homes

Malaysia

Melaka polls: Calm campaign puts focus on what parties can offer voters

Malaysia

Anwar challenges Hadi over ‘Dajjal’ label

Malaysia

Shuhaily remains AKPS chief pending official transfer order, says lawyer

Malaysia

Najib's former wife Tengku Puteri Zainah passes away

Malaysia

Matrade exposes scam involving fake procurement orders, advance payment demands

By Alfian Z.M. Tahir

Malaysia

“Don’t panic,” Govt assures stable essential goods supply amid geopolitical tensions, monsoon threat

You may be interested

Malaysia

Three held after viral video of elderly man's fatal beating in Seremban

Malaysia

Petron, Caltex offer goodwill payments for verified RON95-related vehicle damage claims

Malaysia

Najib's RM50m fine paid by Umno, paving way for his house arrest

Malaysia

Kuala Pilah MP calls for PAC oversight of ministries’ excess spending

By Alfian Z.M. Tahir

Malaysia

Loke: Total of 21,232 foreign drivers caught without valid driving licences in eight months

Malaysia

Loke’s resignation pledge back in focus after Najib fine paid

Malaysia

Govt agrees to restore RM730,300 in Muar allocations under settlement with Syed Saddiq

Malaysia

Drug syndicates target Malaysian youths with lucrative overseas job offers