Pan Borneo Highway: 16 work packages now 75% complete

Deputy works minister says two packages now open to road users while 13 will be ready early 2025

Updated 2 years ago · Published on 06 Jun 2023 3:14PM

Pan Borneo Highway: 16 work packages now 75% complete
Deputy Works Minister Datuk Seri Abdul Rahman Mohamad has told the Parliament that 16 work packages in Phase 1 of the Pan Borneo Highway are being implemented at they are at 75% completion. – Bernama pic, June 6, 2023

KUALA LUMPUR – A total of 16 work packages in Phase 1 of the Pan Borneo Highway project are being implemented and currently, the progress status is at 75%, the Dewan Rakyat heard today.

Deputy Works Minister Datuk Seri Abdul Rahman Mohamad said of the total, two work packages are already opened to road users, while 13 work packages are expected to be completed by early 2025. 

“As for the status of a new work package, namely Work Package 9 involving the route from Serusop to Pituru, it is expected to be implemented as early as the second quarter of 2023, as such, 16 work packages are being implemented for now. 

“The government is committed to ensuring that the Pan Borneo Highway project continues to be implemented and to that end, RM2 billion has been allocated each year where RM1 billion goes to the Sabah Pan Borneo Highway and Sarawak Pan Borneo Highway projects respectively,” he said 

He said this in reply to a question from Mordi Bimol (Mas Gading-PH) who wanted to know the latest status, the time taken to complete the Pan Borneo Highway project in Sabah and Sarawak, as well as the government’s commitment to reduce accidents along the route under construction. 

For the 10 work packages from Sematan to Miri, Abdul Rahman said the entire alignment would be completed in November 2023 except for some sections in Miri that need to be reconstructed which could only be completed in 2025. 

In addition, he said the remaining 19 work packages (Phase 1B) that have yet to start would be financed in a hybrid manner using development allocations and through the issuance of sukuk or bonds by DanaInfra Nasional Berhad. 

“This Pan Borneo Highway Sabah Phase 1B project will be implemented with a construction period of 5 years, and is expected to start as early as in the third quarter of 2023, subject to the approval of the central agency,” he said. 

On the government’s commitment to reduce accidents along the routes under construction, he said the Works Ministry and the Public Works Department of Sabah and Sarawak would continue to monitor the areas to ensure the safety and comfort of road users. – Bernama, June 6, 2023

Related News

Malaysia / 4d

Sabah embarks on five-year initiative to document multiethnic heritage - Hajiji

Malaysia / 5d

Anwar - Sabah's special grant interim payment increased from RM600m to RM1.5b

Malaysia / 6d

Anwar to clarify Sabah 40 pct entitlement talks tomorrow

Malaysia / 1w

Sabah: GRS confident government will agree to review revenue entitlement rate 

Malaysia / 1w

Main Sandakan-Lahad Datu road in Sukau collapses, thousands of users affected

Malaysia / 3w

SLS supports Sabah's move to delay implementation of border control law

Spotlight

Business

Tycoon Vincent Tan trims BCorp stake further in RM115m share sale

Malaysia

UMNO’s solo gamble in Johor: A show of strength or risky miscalculation?

By The Vibes Says

Malaysia

Nik Aziz’s grandson allegedly slapped by senator: Father ready to take case to court

Malaysia

Lorry driver jailed a day, fined for making obscene gestures, dangerous driving (video)

Malaysia

PKR leader defends MyKhas access suspension for PJ, Subang MPs, cites ‘political choices’

Opinion

Social media set to dominate Johor polls as election kingmaker

Malaysia

Man charged in Butterworth parang attack case that left victim fearing permanent disability

Malaysia

Teen mothers must return to school, says Fadhlina as education remains priority

Malaysia

Penang water tariffs to increase from July 1 after year-long deferment

You may be interested

Malaysia

Care home worker jailed 36 years and caned for sexual offences against five boys

Malaysia

Press conference cancelled as MB has 'important business'

Malaysia

Woman pleads guilty to causing death of newborn daughter

Malaysia

KLIA ‘tout’ van driver detained after allegedly soliciting Indian tourists for illegal airport transfer

Malaysia

Man charged in Butterworth parang attack case that left victim fearing permanent disability

Malaysia

MACC officer tells court Penang Tunnel bidder allegedly gained early edge through private briefings

Malaysia

Jewellery shop among six premises destroyed in fire (video)

Malaysia

Minor earthquake shakes Kundasang as residents report feeling tremors