From lizards to water, eco-bumps snag Tesla Berlin plant

Campaigners want to stop its planned sprawling 300ha gigafactory

Updated 5 years ago · Published on 18 Apr 2021 12:50PM

From lizards to water, eco-bumps snag Tesla Berlin plant
An excavator operating as work continues on US electric car giant Tesla’s European gigafactory in Gruenheide, near Berlin. – AFP pic, April 18, 2021

BERLIN – In the green forest outside Berlin, a David and Goliath-style battle is playing out between electric carmaker Tesla and environmental campaigners who want to stop its planned “gigafactory”.

“When I saw on TV that the Tesla factory was going to be built here, I couldn’t believe it,” said Steffen Schorch, driving his trusty German-made car.

The 60-year-old from Erkner village in the Berlin commuter belt has become one of the faces of the fight against the US auto giant’s first European factory, due to open in the Brandenburg region near here in July.

“Tesla needs far too much water, and the region does not have this water,” said the environmental activist, a local representative of the Nabu ecologist campaign group.

Announced in November 2019, Tesla’s gigafactory project was warmly welcomed as an endorsement of the “Made in Germany” quality mark – but was immediately met with opposition from local residents.

Demonstrations, legal action, open letters – residents have done everything in their power to delay the project, supported by powerful environmental campaign groups Nabu and Gruene Liga.

Tesla was forced to temporarily suspend forest clearing last year after campaigners won an injunction over threats to the habitats of resident lizards and snakes during their winter slumber.

And now, they have focused their attention on water consumption – which could reach up to 3.6 million cubic metres a year, or around 30% of the region’s available supply, according to the ZDF public broadcaster.

The extra demand could place a huge burden on a region already affected by water shortages and hit by summer droughts for the past three years.

Local residents and environmentalists are also concerned about the impact on the wetlands, an important source of biodiversity in the region.

Tesla Street 

“The water situation is bad, and will get worse,” Heiko Baschin, a spokesman for the neighbourhood association IG Freienbrink, told AFP.

Brandenburg’s Environment Minister Axel Vogel sought to play down the issue, saying last month that “capacity has not been exceeded for now”.

But the authorities admit that “the impact of droughts is significant” and have set up a working group to examine the issue in the long term.

The gigafactory is set to sprawl over 300ha – equivalent to approximately 560 football fields – southwest of the German capital.

Tesla is aiming to produce 500,000 electric vehicles a year at the plant, which will also be home to “the largest battery factory in the world”, according to group boss Elon Musk.

In a little over a year and a half, swathes of coniferous forest have already been cleared to make way for vast concrete rectangles on a red earth base, accessed via the already iconic Tesla Strasse (Tesla Street).

German bureaucracy 

The new site still has only provisional construction permits, but Tesla has been authorised by local officials to begin work at its own risk.

Final approval depends on an assessment of the project’s environmental impact – including the issue of water.

In theory, if approval is not granted, Tesla will have to dismantle the entire complex at its own expense.

But “pressure is being exerted (on the regulatory authorities), linked to Tesla’s significant investment”, Gruene Liga’s Michael Greschow told AFP.

In early April, Tesla said it was “irritated” by the slow pace of German bureaucracy, calling for exceptions to the rules for projects that help the environment.

Economy Minister Peter Altmaier agreed earlier this month that his government “had not done enough” to reduce bureaucracy, lauding the gigafactory as a “very important project”.

Despite Germany’s reputation for efficiency, major infrastructure projects are often held up by bureaucracy criticised as excessive by the business community.

Among the most embarrassing examples are Berlin’s new airport, which opened last October after an eight-year delay and Stuttgart’s new train station, which has been under construction since 2010.

Brandenburg’s economy minister, Joerg Steinbach, raised the possibility in February that the Tesla factory could be delayed beyond its July planned opening for the same reason. – AFP, April 18, 2021

Related News

Malaysia / 11mth

CRV gets clamped for parking in Tesla charging bay at KL mall

Culture & Lifestyle / 1y

Malaysian quartet drive VWs in road trip to Germany

Malaysia / 2y

Malaysian youth’s stint with Tesla opens doors

Business / 2y

Malaysia secures RM46 billion potential investments from trade and investment mission to Germany, France

Malaysia / 2y

PM Anwar credits public services teamwork for Germany visit's remarkable success

Malaysia / 2y

Anwar touts RM45.4 bil in potential investment during Germany trip

Spotlight

Malaysia

Bersatu-PH tie-up a possibility as coalition seeks Malay support, analyst says

By Alfian Z.M. Tahir

Malaysia

Woman molested on her way home from work (video)

Malaysia

Court allows Daim's daughter to permanently keep passport

Malaysia

Santiago pokes holes in data centre hype, asks: Who really benefits?

By Alfian Z.M. Tahir

Malaysia

Jeweller vows to pursue Rosmah until ‘every penny’ is recovered as RM67.5m battle enters enforcement phase

Malaysia

Ambulance carrying two injured men crashes en route to hospital after MPV collision in Besut

Malaysia

Man blames 'lack of love' for sexual assault on teens

Business

BNM's OPR to stay at 2.75 pcent in 2026 amid strong domestic demand - Kenanga IB

Malaysia

Missing jewellery: Rosmah ordered to pay RM67.5 million

You may be interested

Business

BNM's OPR to stay at 2.75 pcent in 2026 amid strong domestic demand - Kenanga IB

Business

Ringgit holds firm despite US inflation shock as markets brace for Federal Reserve decision

Business

Kami Builders secure RM300 million ASEAN sustainability sukuk, channels Islamic capital into QIU campus development

Business

Unemployment rate rises to 3.0 per cent in April 2026 - DOSM

Business

Ringgit surges as Iran deal optimism weighs on US dollar and oil prices

Business

AI should support human thinking, not replace it - MDEC CEO