Audit report: management of school construction projects inefficient, ineffective

This due to weaknesses at planning, pre-building, implementation stages, says auditor-general

Updated 3 years ago · Published on 03 Aug 2022 3:55PM

Audit report: management of school construction projects inefficient, ineffective
To overcome the weaknesses raised and to ensure the mistakes are not repeated in the future, the auditor-general proposes that the Education Ministry conducts engagement sessions with all the parties involved at the federal and state levels, and to also finalise the project sites before the projects are tabled for approval by the Economic Planning Unit to reduce the risk of delays in implementation. – Wikimedia Commons pic, August 3, 2022

KUALA LUMPUR – The management of school construction projects was found to be inefficient and ineffective based on the scope and audit samples covering the construction of 19 new schools during the 2016-2021 period in Kuala Lumpur, Selangor, Melaka and Negri Sembilan.

According to the Auditor-General’s Report 2021 Series 1, this was due to weaknesses at the planning, pre-construction and implementation stages of the projects by the Education Ministry, consultants and contractors.

“There was also poor coordination with the state governments, local authorities and utility companies, besides the issue of preparedness of the project sites, which contributed to the delay in implementing the projects.

“This situation made the projects’ objectives of accommodating the surplus of students through the building of new schools and having one-session schools difficult to achieve,” said the report.

The audit was conducted to evaluate if the management of the school construction projects had been properly planned and implemented prudently, efficiently and effectively to achieve the two objectives. 

To overcome the weaknesses raised and to ensure the mistakes are not repeated in the future, the auditor-general has proposed that the ministry conduct engagement sessions with all the parties involved at the federal and state levels, and to also finalise the project sites before the projects are tabled for approval by the Economic Planning Unit to reduce the risk of delays in implementation.

The ministry must ensure that land handed over as education reserves by developers are suitable for construction and do not require additional complex groundwork.

According to the report, the ministry must also streamline the school construction procedures and processes for more organised project management and ensure compliance with all the current regulations, while it should also conduct a review to identify the current requirements of the scope of school construction projects where the implementation is delayed. – Bernama, August 3, 2022

Related News

Malaysia / 1y

Grants worth RM39.74 billion used to repay debts related to 1MDB, says auditor general

Education / 1y

MOE, MOHE to ensure places for top SPM students

Malaysia / 2y

Independent commission needed to review education system, says group

Malaysia / 2y

MoE vows full cooperation with authorities after teacher accused of sexual misconduct

Education / 2y

Govt to introduce literacy, numeracy early intervention programme for Year 1 pupils

Malaysia / 2y

Canteen operations during Ramadan won’t hurt students’ faith, MCA tells PAS

Spotlight

Malaysia

Motorcyclist dies in head-on crash, driver tests positive for drugs

Malaysia

61-year-old woman mistakenly presses gas pedal, Porsche crashes into hotel lobby

Opinion

The constitutional framework of justice: Balancing adat

Malaysia

DAP to contest 17 seats in Johor state election - Loke

Malaysia

Terengganu enforces syariah caning sentences as five offenders receive 20 strokes in total

Malaysia

Survivor hiker recounts 14-day forest ordeal after being found alive in Perak jungle (video)

Malaysia

Rafizi’s new party rejects alliances, prepares independent Johor election challenge

Malaysia

Former Kedah assemblyman found drowned in river after early-morning search operation