Gallery

[PHOTOS] Ingenuity behind ECRL megaproject

Now almost half complete, it faces tough challenge with completion of Genting tunnel

Updated 3 years ago · Published on 12 Apr 2023 10:28PM

[PHOTOS] Ingenuity behind ECRL megaproject
Construction for the first East Coast Rail Link tunnel in Genting has begun, with approval to use a tunnel boring machine for the second tunnel obtained in November. – SAIRIEN NAFIS/The Vibes pic, April 12, 2023

by Sairien Nafis

KUALA LUMPUR – A visit to the East Coast Rail Link (ECRL) Genting Tunnel construction site yesterday has shown the remarkable ingenuity behind the entire megaproject, which is now almost half complete.

At the site, Transport Minister Anthony Loke said development for the ECRL is currently 42.06% complete, in line with plans to complete works by December 2026.

However, the Seremban MP also highlighted that the ECRL project currently faces a tough challenge with the completion of the Genting ECRL tunnel, a 16.39km twin tunnel connecting Bukit Tinggi, Pahang with Gombak, Selangor.

So far, construction for the first tunnel in Genting has begun, with approval to use a tunnel boring machine for the second tunnel obtained in November.

Loke said the ECRL will likely be fully operational in early 2027 and would save travel times from Kota Baru to Gombak by three hours.

The Vibes photographer SAIRIEN NAFIS was on the ground during the visit to capture the progress of the ECRL. – The Vibes, April 12, 2023

Transport Minister Anthony Loke participates in a safety simulation exercise at the Genting ECRL tunnel construction site. – SAIRIEN NAFIS/The Vibes pic, April 12, 2023
Transport Minister Anthony Loke participates in a safety simulation exercise at the Genting ECRL tunnel construction site. – SAIRIEN NAFIS/The Vibes pic, April 12, 2023
A demonstration of safety processes in case of an emergency requiring evacuation at the Genting ECRL tunnel construction site. – SAIRIEN NAFIS/The Vibes pic, April 12, 2023
A demonstration of safety processes in case of an emergency requiring evacuation at the Genting ECRL tunnel construction site. – SAIRIEN NAFIS/The Vibes pic, April 12, 2023
The control centre of the Genting ECRL tunnel construction site. – SAIRIEN NAFIS/The Vibes pic, April 12, 2023
The control centre of the Genting ECRL tunnel construction site. – SAIRIEN NAFIS/The Vibes pic, April 12, 2023
A press staffer takes a photograph at the Genting ECRL tunnel construction site. China Communications Construction is the main contractor for the project. – SAIRIEN NAFIS/The Vibes pic, April 12, 2023
A press staffer takes a photograph at the Genting ECRL tunnel construction site. China Communications Construction is the main contractor for the project. – SAIRIEN NAFIS/The Vibes pic, April 12, 2023
Workers at the ECRL tunnel construction site in Genting. – SAIRIEN NAFIS/The Vibes pic, April 12, 2023
Workers at the ECRL tunnel construction site in Genting. – SAIRIEN NAFIS/The Vibes pic, April 12, 2023
The ECRL project currently faces a tough challenge with the completion of the Genting ECRL tunnel, a 16.39km twin tunnel connecting Bukit Tinggi, Pahang with Gombak, Selangor. – SAIRIEN NAFIS/The Vibes pic, April 12, 2023
The ECRL project currently faces a tough challenge with the completion of the Genting ECRL tunnel, a 16.39km twin tunnel connecting Bukit Tinggi, Pahang with Gombak, Selangor. – SAIRIEN NAFIS/The Vibes pic, April 12, 2023
Transport Minister Anthony Loke (centre) says development for the ECRL is currently 42.06% complete, in line with plans to complete works by December 2026. – SAIRIEN NAFIS/The Vibes pic, April 12, 2023
Transport Minister Anthony Loke (centre) says development for the ECRL is currently 42.06% complete, in line with plans to complete works by December 2026. – SAIRIEN NAFIS/The Vibes pic, April 12, 2023
Workers at the Genting tunnel construction site, where rails are being laid for the ECRL. – SAIRIEN NAFIS/The Vibes pic, April 12, 2023
Workers at the Genting tunnel construction site, where rails are being laid for the ECRL. – SAIRIEN NAFIS/The Vibes pic, April 12, 2023
Transport Minister Anthony Loke says the ECRL will likely be fully operational in early 2027 and save travel times from Kota Baru to Gombak by three hours. – SAIRIEN NAFIS/The Vibes pic, April 12, 2023
Transport Minister Anthony Loke says the ECRL will likely be fully operational in early 2027 and save travel times from Kota Baru to Gombak by three hours. – SAIRIEN NAFIS/The Vibes pic, April 12, 2023

Related News

Malaysia / 4mth

Domestic flight capacity increases ahead of Hari Raya - Loke

Malaysia / 4mth

DAP’s July 12 congress: An indication of deeper unease within the party?

Malaysia / 8mth

ECRL construction work at MRR2 temporarily halted for investigation – MRL

Malaysia / 8mth

Temporary bridge at ECRL construction at MRR2 collapses, car crushed

Malaysia / 1y

Airlines to refund consumers for flight delays soon, says Anthony Loke

Malaysia / 1y

B1, B2 licences can be upgraded to Class B now, says Anthony Loke

Spotlight

Malaysia

PRN Negeri Sembilan: The battlegrounds, big names and three-cornered fights to watch

By Alfian Z.M. Tahir

People

Woman ends up with RM500 over food bill after date with ‘doctor’

Malaysia

Love scam: Twelve China nationals arrested in Ipoh over suspected online call centres

Malaysia

ASLI to field female candidate in Jeram Padang DUN

Community

‘Furry officer’ laid to rest as Kuching traffic police mourn beloved stray cat (video)

By Alfian Z.M. Tahir

Malaysia

Father mauled by crocodile as son watches in horror in Sabah river (UPDATED)

Malaysia

Johor shuts down Forest City Network School premises

Malaysia

Singapore: Chief Justice Sundaresh Menon to retire in Feb 2027, succeeded by Justice Sushil Nair