ECRL 30% complete as of May, likely to hit 37% year-end target: Wee

Transport minister adds 23,000-strong labour force needed in peak construction period in 2023

Updated 4 years ago · Published on 23 Jun 2022 6:06PM

ECRL 30% complete as of May, likely to hit 37% year-end target: Wee
Transport Minister Datuk Seri Wee Ka Siong speaks at the opening ceremony of the construction of the Pahang ECRL Genting Tunnel in Bentong today, which was officiated by Prime Minister Datuk Seri Ismail Sabri Yaakob. – Bernama pic, June 23, 2022

BENTONG – Construction work on the East Coast Rail Link (ECRL) project has recorded overall progress of 30% as of May this year, says Transport Minister Datuk Seri Wee Ka Siong.

He said the project was likely to hit the projected 37% completion rate by the end of this year.

The development, he added, was driven by infrastructure work in four states, which included the alignments of Section A from Kota Baru to Dungun, Section B from Dungun to Mentakab and Section C from Mentakab to Port Klang.

According to Wee, the infrastructure work is running simultaneously in sections A, B and C and in more than 300 work areas along the 665-km railway line.

“The number of work areas will continue to increase towards the peak of construction in 2023, where a manpower of 23,000 will be needed to develop the ECRL project more effectively,” he said during his address at the opening ceremony of the construction of the Pahang ECRL Genting Tunnel here today, which was officiated by Prime Minister Datuk Seri Ismail Sabri Yaakob. 

He added that various vacancies in management and non-management fields would be filled, besides assuring that local manpower requirements would increase to 70% of the quota by 2023, in line with the progress of the project.

Touching on the progress of the Genting Tunnel project, Wee said the installation of the first tunnel boring machine (TBM1) was completed for pilot testing in April 2022.

The Genting Tunnel is the first ECRL tunnel to be excavated using the TBM method as opposed to the drilling and blasting method that has been used for other tunnels so far.

The cost of the ECRL Project involving 59 tunnels is estimated to reach RM50.27 billion and includes construction work in four states, namely Kelantan, Terengganu, Pahang and Selangor. – Bernama, June 23, 2022

Related News

Malaysia / 2mth

Pahang hospitals test drones to deliver blood samples

Malaysia / 2mth

Cabinet approves 17 measures to beef up KLIA security checks, controls

Malaysia / 2mth

Pahang police reject claims of drug cartel operating in Genting Highlands

Opinion / 3mth

Orang Asli in Pahang: Token gestures or genuine recognition?

Malaysia / 6mth

Private Amirul's death: Police have called 16 witnesses

Malaysia / 7mth

Be patient, exercise caution when driving home for Aidilfitri - Pahang Sultan

Spotlight

Malaysia

Asyraf denies Najib ready to pay RM50m fine for house arrest

Malaysia

Malaysia’s average household size falls to 3.8 people

Malaysia

Najib's former wife Tengku Puteri Zainah in critical condition in ICU

Malaysia

More than 117,000 harmful online posts removed as government steps up enforcement

Malaysia

1,000 families receive Deepavali aid to ensure no one misses festive celebrations

Malaysia

Mother, daughter fined RM500 each for obstructing Muar council enforcement officers

Malaysia

Kelantan records 1,446 khalwat cases in three years

Malaysia

Negeri’s deposed Undang, chieftains fail to stop committal proceedings

You may be interested

Malaysia

Anwar: Urban development must not leave ordinary Malaysians, small businesses behind

Malaysia

School warden claims trial to two charges of sexually assaulting Year Five pupil

Malaysia

Zahid given until Nov 12 to justify rural funding claims amid alleged contradictions

Malaysia

Mother, daughter fined RM500 each for obstructing Muar council enforcement officers

Malaysia

Government shields households from data centre-driven utility costs

Malaysia

Kelantan records 1,446 khalwat cases in three years

Malaysia

Jamil Khir to mount legal challenge against charges over RM860.3m Tabung Haji transactions

Malaysia

Police arrest woman over alleged assault of children aged seven and two at KL mall