LCS 1 risks handover without full combat capability, readiness could slip to 2035

Auditor-General warns that LCS 1 could be handed over without completed training and weapons systems while full project readiness may not be achieved until end of 2035

Updated 2 hours ago ยท Published on 05 Oct 2026 1:09PM

LCS 1 risks handover without full combat capability, readiness could slip to 2035
he LCS project was 7.55 per cent behind schedule as at June 25 - October 5, 2026

THE first Littoral Combat Ship (LCS 1) risks being handed over to the Royal Malaysian Navy without full operational capability, with the Auditor-General warning that completion of the project’s complementary contracts could be delayed until December 2035.

The National Audit Department (JAN) said the LCS project was 7.55 per cent behind schedule as at June 25, with delays ranging from 30 to 108 days, putting the earliest physical handover (PHO) of LCS 1 at risk.

It said LCS 1 was initially scheduled for handover on Aug 26, with a revised target of Dec 26.

“If the PHO is carried out on either date, LCS 1 will be handed over without achieving full capability as training and weapon systems have yet to be completed.

“Full readiness of the LCS project is dependent on the Complementary Contracts, which can only be completed in December 2035, beyond the Main Contract’s end date of April 25, 2030. The delay in the PHO of LCS 1 will affect the PHO period for LCS 2 to LCS 5,” JAN said.

The findings were contained in the Auditor-General’s Report (LKAN) 2/2026, tabled in the Dewan Rakyat today.

JAN said the interim audit assessed the management of the LCS project in terms of physical and financial progress, contract management and payments against contractual terms and prevailing regulations.

The audit also took into account recommendations by the Public Accounts Committee (PAC) in its Oct 9, 2023 report for JAN to audit the LCS project before LCS 1 was handed over to the Navy and table the findings in Parliament.

To ensure the project is completed and handed over at the required level of readiness, JAN recommended that the Defence Ministry establish a realistic recovery plan and align all critical activities under the Main and Complementary Contracts with the LCS handover schedule.

The ministry was also urged to ensure that any conditional acceptance of the ships clearly specifies the contractor’s obligations, completion deadlines and responsibilities until the vessels achieve the required capability.

JAN further recommended stronger project monitoring, including appointing officers responsible for each critical issue and setting deadlines for their resolution until the project is completed. - October 5, 2026

Spotlight

Diary

Penang reaffirms commitment to preserve heritage sites across the state

By Ian McIntyre

Opinion

AI: A Godsend for those with dyslexia in education and careers

Malaysia

Malaysia prepares for aged nation status by 2036

Malaysia

Mentally disabled suspect remanded for 7 days over fatal hammer attack in Marang

Malaysia

Masidi urges Putrajaya to address Sabah doctor shortage in upcoming Budget 2027

Malaysia

Police rearrest motivational speaker as second woman files harassment report in Perlis

Malaysia

Anwar vows zero compromise on school safety after alleged murder of teen Irene Sofiya

Malaysia

Classmates arrested as police probe fatal assault of 16-year-old Irene Sofiya

Malaysia

Loneliness, social media drive elderly pensions into hands of cyber scammers

Malaysia

Another desperate attempt by Nadzaruddin and former Undangs

You may be interested

Malaysia

Elderly man loses RM114k after being duped by fake police investigator

Malaysia

Cable theft near Taman Equine causes severe delays on MRT Putrajaya line

Malaysia

Dewan Rakyat resumes with Tabung Haji, food security and MA63 in focus

Malaysia

Mobile phone, clothing seized from teenager remanded over Yong Peng schoolgirl murder

Malaysia

Seven-day fast-track approvals, low-interest funding to boost Indian businesses for Deepavali

Malaysia

Budget 2027 must balance cost pressures with fiscal resilience

Malaysia

Malaysia - Bahrain deepen bilateral ties on Formula 1โ€™s return to Sepang

Malaysia

Petaling Jaya parliamentary seat officially declared vacant after Lee Chean Chung quits - Speaker