Malaysia

Upgrading, repair of Parliament to take 14 years, supposed to be six

Many changes to job scope pushed project’s cost ceiling up by RM106.1 million, says A-G report

Updated 3 years ago · Published on 03 Aug 2022 6:05PM

Upgrading, repair of Parliament to take 14 years, supposed to be six
According to the Auditor-General’s Report 2021 Series 1 released today, the performance outcome of the project that started in 2011 also cannot be evaluated as phase 2C(ii), involving the main building and the provision of parking lots, is still in the implementation phase. – The Vibes file pic, August 3, 2022

KUALA LUMPUR – The upgrading and repair work for the Parliament building, which was supposed to take only six years, will now take 14 years to complete, taking into account phase 2C(ii) which is scheduled to be completed in 2025.

According to the Auditor-General’s Report 2021 Series 1 released today, the performance outcome of the project that started in 2011 also cannot be evaluated as phase 2C(ii), involving the main building and the provision of parking lots, is still in the implementation phase.

“Overall, the management of the project is satisfactory with six phases having been completed and one phase under construction,” it said.

The audit also found that many changes to the job scope following customer and technical requests had contributed to the increase in the project’s cost ceiling by RM106.1 million (20.4%), from RM520 million to RM626.1 million.

The project’s financial performance also showed that expenses up to December 31, 2021, amounted to RM468.45 million (74.8%), compared to the latest allocation of RM626.10 million.

Besides that, several weaknesses in terms of project management – such as value management, procurement and contract management, and governance of the Information and Communication Technology (ICT) system development in the contract – require attention from the management for remedial actions.

To overcome the weaknesses and ensure they do not recur in the future, the Auditor-General recommended that the Public Works Department (PWD) ensure comprehensive governance and effective monitoring so that the project achieved the set objectives.

In addition, Parliament and the PWD need to ensure the management of ICT system development is referred to the authorised agencies to meet the needs, interests, and security of public sector ICT.

“Parliament needs to ensure that assets procured are optimally used and are fully utilised,” the report added. – Bernama, August 3, 2022

Related News

Malaysia / 3mth

‘I feel awkward sitting next to Hamzah’ – Muhyiddin

Malaysia / 3mth

Government drafting bill to address online gambling - Fadillah

Malaysia / 3mth

Azam Baki’s alleged shareholding issue should be debated in Parliament, says Guan Eng

Malaysia / 3mth

Digital Ministry drafting AI Governance Bill to combat deepfakes - Gobind

Malaysia / 3mth

SARA spending, fraud in transactions among issues at Dewan Rakyat today

Malaysia / 4mth

Photo of meeting between Anwar, Hishammuddin steals the spotlight

Spotlight

Malaysia

Former head of a ministry's corporate communications unit acquitted of bribery charge

Malaysia

Two sisters die trapped in Johor house fire as escape routes cut off by flames

Malaysia

NS election speculation intensifies as Aminuddin granted audience with state ruler

Malaysia

Teenager who drove recklessly, causing death remanded for further investigation

Malaysia

Police looking for trio involved in violent armed robbery in Penang (video)

Malaysia

Family of five killed as car crashes into water pipe in Serian

Malaysia

'I was once spat on by a pakcik' — Marina denies fear of contesting Malay-majority seats

Malaysia

Jewellery shop among six premises destroyed in fire (video)

You may be interested

Malaysia

Man charged in Butterworth parang attack case that left victim fearing permanent disability

Malaysia

TNB central to Malaysia’s “just transition” as AI boom drives energy demand surge

Malaysia

KLIA ‘tout’ van driver detained after allegedly soliciting Indian tourists for illegal airport transfer

Malaysia

Viral list of PRN candidates is fake - BN Johor

Malaysia

Azam Baki denies threat allegations after giving statement to police

Malaysia

Family of five killed as car crashes into water pipe in Serian

Malaysia

Johor PRN: Onn Hafiz likely to be BN 'poster boy'

Malaysia

Press conference cancelled as MB has 'important business'