Upgrading, repair of Parliament to take 14 years, supposed to be six

Many changes to job scope pushed project’s cost ceiling up by RM106.1 million, says A-G report

Updated 4 years ago · Published on 03 Aug 2022 6:05PM

Upgrading, repair of Parliament to take 14 years, supposed to be six
According to the Auditor-General’s Report 2021 Series 1 released today, the performance outcome of the project that started in 2011 also cannot be evaluated as phase 2C(ii), involving the main building and the provision of parking lots, is still in the implementation phase. – The Vibes file pic, August 3, 2022

KUALA LUMPUR – The upgrading and repair work for the Parliament building, which was supposed to take only six years, will now take 14 years to complete, taking into account phase 2C(ii) which is scheduled to be completed in 2025.

According to the Auditor-General’s Report 2021 Series 1 released today, the performance outcome of the project that started in 2011 also cannot be evaluated as phase 2C(ii), involving the main building and the provision of parking lots, is still in the implementation phase.

“Overall, the management of the project is satisfactory with six phases having been completed and one phase under construction,” it said.

The audit also found that many changes to the job scope following customer and technical requests had contributed to the increase in the project’s cost ceiling by RM106.1 million (20.4%), from RM520 million to RM626.1 million.

The project’s financial performance also showed that expenses up to December 31, 2021, amounted to RM468.45 million (74.8%), compared to the latest allocation of RM626.10 million.

Besides that, several weaknesses in terms of project management – such as value management, procurement and contract management, and governance of the Information and Communication Technology (ICT) system development in the contract – require attention from the management for remedial actions.

To overcome the weaknesses and ensure they do not recur in the future, the Auditor-General recommended that the Public Works Department (PWD) ensure comprehensive governance and effective monitoring so that the project achieved the set objectives.

In addition, Parliament and the PWD need to ensure the management of ICT system development is referred to the authorised agencies to meet the needs, interests, and security of public sector ICT.

“Parliament needs to ensure that assets procured are optimally used and are fully utilised,” the report added. – Bernama, August 3, 2022

Related News

Malaysia / 2w

MP to raise commingled oil cargo tax uncertainty in Parliament

Malaysia / 1mth

No discussions yet regarding general election – Zahid

Malaysia / 1mth

BNPL users hit eight million as outstanding balances reach RM5.3b

Malaysia / 2mth

Speaker reminds MPs not to skip parliamentary sessions

Malaysia / 2mth

Hamzah back in the saddle as opposition leader after brief shake-up

Malaysia / 2mth

Muhyiddin's seat in Dewan Rakyat moved to Block E

Spotlight

Malaysia

Penang CM defends move by housing board, says enforcement is last resort

By Ian McIntyre

World

Anak Krakatau’s six eruptions recorded

Malaysia

Delivery rider's compassion turns RM14.50 meal into wave of public generosity

Malaysia

Sanusi’s gambling stance puts PAS manifesto under scrutiny

By Alfian Z.M. Tahir

Malaysia

Zahid’s game plan is opening up

Malaysia

Chew Jetty fire: Business owners lose everything in the blink of an eye

By Ian McIntyre

Malaysia

SMART Team leaves for Nepal today as search for 55 Malaysians continues

Diary

Mother Teresa - one of the foremost humanitarian figures of the 20th century died today, 29 years ago

You may be interested

Malaysia

Sultan Nazrin calls for wider access, stronger action in fight against cancer

Malaysia

Negeri Sembilan MB reaffirms loyalty to Tuanku Muhriz amid throne dispute

Malaysia

Death sentence for deaf, mute man who killed family of four upheld

Malaysia

Chew Jetty fire: Business owners lose everything in the blink of an eye

By Ian McIntyre

Malaysia

PAS calls Unity Government unstable, demands Parliament dissolution

Malaysia

Zahid: No PM candidate talks until parliament dissolved

Malaysia

UiTM student dies, eight hospitalised after heat-related incident

Malaysia

Eleven held over revenge machete attack on man in Perak