Malaysia

New KL air traffic control centre cost extra RM4.88 mil due to invalid contract

A-G’s Report also says choice to administer agreement on hybrid basis breached financial regulations

Updated 3 years ago · Published on 07 Aug 2022 8:00AM

New KL air traffic control centre cost extra RM4.88 mil due to invalid contract
Pictured here is Kuala Lumpur’s new Air Traffic Control Centre, which commenced operations on August 31 last year after the project experienced five extensions of more than two years. – Civil Aviation Authority of Malaysia Facebook pic, August 7, 2022

by Qistina Nadia Dzulqarnain

KUALA LUMPUR – Putrajaya had to fork out an extra RM4.88 million for the New Air Traffic Control Centre and Related Systems for Kuala Lumpur Flight Information Region (New KL ATCC) project, according to the Auditor-General’s Report 2021 Series 1. 

The report detailed that the extension of the Independent Checker Consultant (ICC) contract period was deemed invalid due to it being made after the original contract period expired. 

This resulted in excess payments amounting to RM4.88 million being made, with RM63.21 million paid to the ICC as of December 31, 2021. 

However, valid contract costs only amounted to RM58.33 million since the original ICC contract was valued at RM52.39 million, while the first additional ICC agreement cost RM5.94 million. 

“Based on the first additional ICC agreement, the contract period was extended for two months until August 10, 2021. The ICC service period was then extended for a second time beginning August 18 until April 17, 2022 through a second additional agreement,” the report said. 

“The ICC contract was terminated on August 10 because there was no contract extension for the period between August 11 to 17. Since the first additional agreement ended, the extension of the contract period through the second additional agreement is invalid.” 

It said the original project allocation approved in the 11th and 12th Malaysia Plans was RM650.37 million while on May 17 this year, the Economic Planning Unit had approved an increase in the project ceiling to RM665.19 million. 

Pictured here is a scale model of the New KL ATCC building. The Auditor-General’s Report states that weaknesses in the physical security aspects of the building and access to the system have exposed its operations to the risk of intrusion, modifications and data loss. – Pena Celoreng Facebook pic, August 7, 2022
Pictured here is a scale model of the New KL ATCC building. The Auditor-General’s Report states that weaknesses in the physical security aspects of the building and access to the system have exposed its operations to the risk of intrusion, modifications and data loss. – Pena Celoreng Facebook pic, August 7, 2022

Additionally, the report recorded that a payment of RM5.33 million to the ICC could not be verified to be in order while noting that the project involved the wastage of public funds amounting to RM2.18 million. 

“The cases involved are related to failure to collect fines and impose penalties on contractors, as well as the cost of reimbursement to the consultant being included in the contract despite it being a violation of the circular.” 

Besides that, the report stated that the Transport Ministry’s decision to administer the contract on a hybrid basis did not guarantee the protection of the government’s interest, claiming that the call saw a breach of financial regulations. 

It added that weaknesses in the physical security aspects of the building and access to the system have exposed the operations of the New KL ATCC to the risk of intrusion, modifications and data loss. 

Recommending that the ministry review all terms and conditions of the contract, the report also urged the ministry and the Malaysian Civil Aviation Authority to ensure that contractors perform all scopes of maintenance services accordingly and impose appropriate penalties. 

The New KL ATCC project commenced operations on August 31 last year after five extensions of more than two years, or 898 days. – The Vibes, August 7, 2022

Related News

Malaysia / 4mth

New regulations to curb RON95 leakage, especially at borders from April 2026

Malaysia / 6mth

KLIA Terminal 1 experiences water leakages amid heavy storm

Malaysia / 2y

PM Anwar credits public services teamwork for Germany visit's remarkable success

Malaysia / 2y

Penang’s LRT alignment headed for revamp as Transport Ministry takes over

Malaysia / 2y

Putrajaya, Penang partnering for free ferry, bus rides during Thaipusam

Malaysia / 2y

Driving licence, road tax renewal can be done via MyJPJ app from Feb 1

Spotlight

Business

Tycoon Vincent Tan trims BCorp stake further in RM115m share sale

Malaysia

UMNO’s solo gamble in Johor: A show of strength or risky miscalculation?

By The Vibes Says

Malaysia

Nik Aziz’s grandson allegedly slapped by senator: Father ready to take case to court

Malaysia

Lorry driver jailed a day, fined for making obscene gestures, dangerous driving (video)

Malaysia

PKR leader defends MyKhas access suspension for PJ, Subang MPs, cites ‘political choices’

Opinion

Social media set to dominate Johor polls as election kingmaker

Malaysia

Man charged in Butterworth parang attack case that left victim fearing permanent disability

Malaysia

Teen mothers must return to school, says Fadhlina as education remains priority

Malaysia

Penang water tariffs to increase from July 1 after year-long deferment

You may be interested

Malaysia

Ex-employee held over RM83,000 theft of phones, apple watches and cash

Malaysia

King calls for people-centred development in KL

Malaysia

Malaysians may soon be able to get a 10-year passport for RM350

Malaysia

Azam Baki denies threat allegations after giving statement to police

Malaysia

Teenager who drove recklessly, causing death remanded for further investigation

Malaysia

Viral list of PRN candidates is fake - BN Johor

Malaysia

Woman pleads guilty to causing death of newborn daughter

Malaysia

‘What wrong did I do?’ – asks PKR MP after loss of MyKhas access