Construction of 3 schools halted over dubious contractors

Education Ministry chose firms with sketchy financials, Parliament told 

Updated 5 years ago · Published on 02 Dec 2020 2:54PM

Construction of 3 schools halted over dubious contractors
A view of the SMK Bandar Saujana Putra construction site in December 2017. – Facebook pic, December 2, 2020

by The Vibes Team

KUALA LUMPUR – The construction of three public schools has ground to a halt due to the Education Ministry appointing contractors with sketchy financials, effectively wasting millions in taxpayer funds, according to December 1 parliamentary replies.

The construction of national-type school SMK Bandar Saujana Putra and primary school SK Bandar Saujana Putra had to be delayed after the contractor was found insolvent and had to wind up, the ministry said a written reply to Kuala Langat MP Xavier Jayakumar.

SMK Bandar Saujana Putra involved the construction of 30 classrooms and other facilities for a total of RM38 million. The project began on January 5, 2017, with the estimated completion date being January 3 last year, but was extended to September 30.

SK Bandar Saujana Putra involved the construction of 24 classrooms and other amenities for RM28 million. The project commenced January 11, 2018, with the original estimated completion date being July 11, 2019, but received an extension up to January 18, 2020.

But the contractor for both projects had to be terminated on January 20 this year after becoming insolvent and had to wind up. As of that date, the progress for the high school and primary school stood at 95.8% and 45%.

The ministry will be re-tendering both projects, with submission calls for SMK Bandar Saujana Putra and SK Bandar Saujana Putra to be advertised in December and January. The high school is expected to be completed in March 2022 while the primary school is expected to be ready by August that same year.

Meanwhile, SJK (T) Heawood was allocated RM13.88 million to build 12 classrooms and other amenities but the Tamil national-type primary school remains unfinished as the contractor failed to complete the project according to stipulated milestones, the Education Ministry said in a written reply to Sg Siput MP Kesavan Subramaniam.

The school’s construction was supposed to begin in June 2017, and was supposed to be completed by March 23, 2019, after an 108-day extension was granted.

But the contractor failed to show progress and was terminated on August 20 last year with only 42% of works completed. The Education Ministry will be re-tendering the project next year with the school expected to be completed by 2022. – The Vibes, December 2, 2020

Related News

Education / 2y

MOE, MOHE to ensure places for top SPM students

Malaysia / 2y

Independent commission needed to review education system, says group

Malaysia / 2y

MoE vows full cooperation with authorities after teacher accused of sexual misconduct

Education / 2y

Govt to introduce literacy, numeracy early intervention programme for Year 1 pupils

Malaysia / 2y

Canteen operations during Ramadan won’t hurt students’ faith, MCA tells PAS

Education / 2y

Fadhlina, education officials chided over lapses during Tamil school visit in Penang

Spotlight

Malaysia

PRNNS: Loke: 'We must win all 11 seats to help PH form state government'

Sports & Fitness

Spain ends Argentina’s World Cup reign with extra-time triumph to reclaim global crown

World

Cat found alive after being buried under Venezuela quake rubble for days (video)

Malaysia

“Resign if you attack fellow Unity Government partners,” Anwar enforces discipline

Malaysia

PH youth wing calls on BN ministers to quit cabinet over PN electoral alliance

Malaysia

Rosmah asks for prayers as Najib prepares for medical procedure

Malaysia

Woman at a loss after fake Hong Kong lawyer offers to recover money from previous scam

You may be interested

Malaysia

PH offers more comprehensive manifesto, benefits all groups

Malaysia

Millions may gain from broader Sara Aid expansion to combat rising costs

Malaysia

AirBorneo an important ‘air bridge’ between Sarawak, Peninsular Malaysia – Abang Jo

Malaysia

Sara Aid expands to 13,700 stores as Govt widens access for rural communities

Malaysia

Syed Saddiq completes 170km Thanksgiving Charity Run after acquittal, surpassing fundraising target

Malaysia

PM holds final authority on cabinet appointments - Minister

Malaysia

eFishery loss will not jeopardise KWAP’s finances or pension payments - Tengku Zafrul

Malaysia

Negeri Sembilan PRN: Police record one report over supporters’ verbal dispute