Sabah’s main port sees dramatic drop in layover times despite expansion delays

Ships now wait under 48 hours at Sepanggar Port following DP World takeover

Updated 1 year ago · Published on 28 Mar 2025 6:15PM

Sabah’s main port sees dramatic drop in layover times despite expansion delays
Shahelmey speaks to reporters after attending a briefing on the ongoing development at Sepanggar Bay Container Port. - March 28, 2025

by Jason Santos

OPERATIONS at Sabah’s main container terminal have improved significantly, with vessel layover times slashed from nearly two weeks to under 48 hours, Sabah deputy chief minister III Datuk Shahelmey Yahya said.

The change comes just six months after global logistics firm DP World took over the management of Sepanggar Bay Container Port in September 2024, through its subsidiary DP World Sabah Sdn Bhd.

Shahelmey who is also Sabah works minister said the improved efficiency follows a series of operational changes implemented under the new management.

“Last time the issue was about two weeks for the layover. Now, based on the latest presentation, it’s less than 48 hours,” he said during a visit to the port on Wednesday.

The port had previously experienced severe congestion. In mid-2024, ships waited up to 13 days to dock, prompting concerns about rising costs for traders and potential price increases for goods.

At the time, port operators had considered imposing a congestion surcharge, including higher demurrage fees, but this was eventually called off following intervention by local authorities and industry representatives.

The situation led to the establishment of the Sabah Logistics Council, tasked with addressing long-standing infrastructure issues, streamlining port operations, and avoiding future supply chain disruptions.

Despite operational gains, a major infrastructure upgrade to the port has fallen behind schedule.

The RM1 billion expansion project, initially expected to be completed in 2025, is now only 18% finished and has been rescheduled for completion in 2026.

“We hope there will be no further issues that could delay the project. It has already been set back quite a bit,” said Shahelmey.

The project aims to double the quay length to 1km, deepen the waterway to 15 metres, and raise the terminal’s annual capacity from 500,000 to 1.2 million twenty-foot equivalent units (TEUs).

Additional changes at the port include the relocation of roll-on/roll-off (RoRo) services from the old Kota Kinabalu Port to Sepanggar starting 1 April. The move is intended to consolidate port activities and improve vehicle handling efficiency.

Separately, ferry terminal upgrades for the Labuan–Kota Kinabalu route are also under way and are expected to be completed in the first week of May.

The Sabah government says it remains committed to enhancing logistics performance as part of a broader push to position Sepanggar as a regional transshipment hub in Southeast Asia. - March 28, 2025

Shahelmey speaks to reporters after attending a briefing on the ongoing development at Sepanggar Bay Container Port. - March 28, 2025
 


 


 


 


 


 

Related News

Malaysia / 2mth

Abang Jo: Bintulu Port strengthens Sarawak’s position as strategic maritime, industrial hub

Business / 5mth

Government urged to address operational inefficiencies at Pengerang Port

Malaysia / 1y

Zahid reaffirms Sabah Umno's decision to chart own future

Malaysia / 1y

Alternative access underway after landslide cuts off remote Nabawan village

Malaysia / 1y

Shahelmy hints at contesting in Sabah polls

Malaysia / 1y

Sabah drops crackdown on water pumps after backlash

Spotlight

Opinion

“I’m not a war criminal, I’m a patriot”: Shavendra Silva’s amnesia tour meets the receipts

By Abbi Kanthasamy

Malaysia

British management on trial – does a royal management institute deliver value?

Malaysia

Doctor among five killed in Sarawak Flying Doctor helicopter crash identified

Malaysia

Nearly 10,000 potential fire hotspots detected on RSPO-managed land

Malaysia

Undang Yang Empat produces letter allegedly confirming Tuanku Muhriz’s removal

Malaysia

Northern Malaysia must prepare for the consequences of lower rainfall

Malaysia

Helicopter crashes during flying doctor service mission in Sarawak

You may be interested

Business

Oil prices near US$100 as Middle East supply risks mount

Business

Malaysia’s East Coast secures RM61b in approved investments since 2021 - MIDA

Business

Brent hits six-week high as Hormuz risks escalate