Penang: Mutiara Light Rail Transit project: key delivery milestones achieved

Project owner and the main delivery partner - Malaysia Rapid Transit Corporation Sdn Bhd (MRT Corp) said that a series of key delivery milestones were achieved.

Updated 1 month ago · Published on 07 Aug 2026 12:24PM

Penang: Mutiara Light Rail Transit project: key delivery milestones achieved
To date, 93% of the total land acreage required for the CMC1 package has been made available for construction activities. - August 7, 2026

by Ian McIntyre

THE RM16.8 billion Mutiara Light Rail Transit (LRT) project has gathered pace in its construction phase despite concerns over the global economy and the socio-politics of the country.

Project owner and the main delivery partner - Malaysia Rapid Transit Corporation Sdn Bhd (MRT Corp) said that a series of key delivery milestones were achieved.

It marked steady progress in the development of Penang's first metro rail system, whose construction presence is felt in many parts of the island.

As the asset owner and project manager, MRT Corp continues to lead and drive the coordination of engineering design, construction planning, land readiness and railway systems implementation to ensure the project progresses in accordance with the schedule.

MRT in a statement cited that a major focus of the project at this stage is the completion of detailed construction drawings for Civil Main Contract 1 (CMC1), covering critical infrastructure elements including pile caps, piers, viaducts and stations from the now under reclaimed Silicon Island to the state administrative complex of Komtar in George Town.

To enable construction activities to commence progressively, MRT Corp has been issuing construction reference drawings to the contractor while detailed designs continue to be finalised.

Land acquisition for the project also continues to progress well through close collaboration between the Federal Government, the Penang State Government and the relevant agencies.

To date, 93% of the total land acreage required for the CMC1 package has been made available for construction activities.

Another significant milestone has been achieved at the reclaimed Silicon Island, where soil investigation works have commenced, paving the way for future depot construction activities in this key section of the alignment.

Following the handover of the Pesta site in Sungai Nibong by the state government in April 2026, MRT Corp has completed the removal of old structures and the necessary site preparation works, enabling construction activities to commence.

With civil works continuing to advance across multiple fronts, MRT Corp is also actively managing the interface between the civil construction works and railway systems to ensure both workstreams progress in an integrated approach.

It has awarded a turnkey contract to the Malaysian Resources Corporation Berhad (MRCB) and Theta Edge Berhad joint venture (MRCB–Theta Edge JV).

The appointment will enable detailed design of the railway systems to proceed in parallel with the ongoing civil construction programme, ensuring both components remain aligned towards overall project delivery.

MRT also extended its appreciation to Penangites for their patience, understanding and cooperation throughout the construction period.

"We remain committed to carrying out the works responsibly while minimising disruption wherever possible," MRT said. - August 7, 2026.

Related News

Places / 1d

Penang hoteliers lose patience over growing number of short-term rentals, homestays

Diary / 3d

A leader's role is not just about issuing statements and making headlines – Penang CM

Health / 4d

Tourism players in Penang call for urgent action to overcome haze situation

Malaysia / 5d

No more political value for UMNO to be part of Penang administration, says Guan Eng

Education / 5d

Penang: Schools may be ordered to close if air quality worsens

Diary / 6d

RM30m gold refinery facility opens in Penang

Spotlight

Malaysia

Bersatu-PAS cooperation ends, Muhyiddin says, as PN rift deepens

Malaysia

Calls grow for arrest of Nadzaruddin, Exco, for treason

Malaysia

Loke offers to resign as Transport Minister following Pardons Board decision

Malaysia

UMNO’s fundraiser for Najib draws sharp criticism on social media

Malaysia

Home Ministry yet to receive formal order on Najib house arrest

By Alfian Z.M. Tahir

Malaysia

PH Melaka, Bersatu in talks for wider election pact

You may be interested

Our Planet

Singapore solar investments save US$97m in fuel costs amid Hormuz crisis

Our Planet

Indonesia’s haze returns as fire prevention gaps persist a decade after 2015

Places

Penang hoteliers lose patience over growing number of short-term rentals, homestays

By Ian McIntyre