Penang: Mutiara Light Rail Transit project: key delivery milestones achieved

Project owner and the main delivery partner - Malaysia Rapid Transit Corporation Sdn Bhd (MRT Corp) said that a series of key delivery milestones were achieved.

Updated 1 hour ago · Published on 07 Aug 2026 12:24PM

Penang: Mutiara Light Rail Transit project: key delivery milestones achieved
To date, 93% of the total land acreage required for the CMC1 package has been made available for construction activities. - August 7, 2026

by Ian McIntyre

THE RM16.8 billion Mutiara Light Rail Transit (LRT) project has gathered pace in its construction phase despite concerns over the global economy and the socio-politics of the country.

Project owner and the main delivery partner - Malaysia Rapid Transit Corporation Sdn Bhd (MRT Corp) said that a series of key delivery milestones were achieved.

It marked steady progress in the development of Penang's first metro rail system, whose construction presence is felt in many parts of the island.

As the asset owner and project manager, MRT Corp continues to lead and drive the coordination of engineering design, construction planning, land readiness and railway systems implementation to ensure the project progresses in accordance with the schedule.

MRT in a statement cited that a major focus of the project at this stage is the completion of detailed construction drawings for Civil Main Contract 1 (CMC1), covering critical infrastructure elements including pile caps, piers, viaducts and stations from the now under reclaimed Silicon Island to the state administrative complex of Komtar in George Town.

To enable construction activities to commence progressively, MRT Corp has been issuing construction reference drawings to the contractor while detailed designs continue to be finalised.

Land acquisition for the project also continues to progress well through close collaboration between the Federal Government, the Penang State Government and the relevant agencies.

To date, 93% of the total land acreage required for the CMC1 package has been made available for construction activities.

Another significant milestone has been achieved at the reclaimed Silicon Island, where soil investigation works have commenced, paving the way for future depot construction activities in this key section of the alignment.

Following the handover of the Pesta site in Sungai Nibong by the state government in April 2026, MRT Corp has completed the removal of old structures and the necessary site preparation works, enabling construction activities to commence.

With civil works continuing to advance across multiple fronts, MRT Corp is also actively managing the interface between the civil construction works and railway systems to ensure both workstreams progress in an integrated approach.

It has awarded a turnkey contract to the Malaysian Resources Corporation Berhad (MRCB) and Theta Edge Berhad joint venture (MRCB–Theta Edge JV).

The appointment will enable detailed design of the railway systems to proceed in parallel with the ongoing civil construction programme, ensuring both components remain aligned towards overall project delivery.

MRT also extended its appreciation to Penangites for their patience, understanding and cooperation throughout the construction period.

"We remain committed to carrying out the works responsibly while minimising disruption wherever possible," MRT said. - August 7, 2026.

Related News

Events / 20h

‘Fall in Love with Penang’ campaign launched to woo Malaysians to the state

Heritage / 1d

Penang defends need for newly reopened state museum

Malaysia / 2d

Penang orders owners, operators of heritage shophouses to conduct regular inspections

Malaysia / 2d

Penang: Two tourists injured by falling debris along Armenian Street

Events / 3d

Former Indonesian president in Penang next month for inaugural Peace Dialogue

Malaysia / 4d

‘We will learn from past mistakes and return stronger’ – Steven Sim

Spotlight

Malaysia

Court quashes RM313.8 million tax bill against Na’imah

Malaysia

Alternative medicine practitioner arrested on suspicion of molesting client

Malaysia

Drones, AI among measures to strengthen border security

By Alfian Z.M. Tahir

Malaysia

New NS exco line-up to be sworn in tomorrow as BN-PN government takes shape

Malaysia

MACC-Customs task force under discussion as smuggling cases pile pressure on enforcement agencies

Malaysia

JBPM taking all necessary steps to face hot weather, Super El Niño

Malaysia

Police team heads to Jakarta as Malaysia probes pilot’s alleged drug link

By Alfian Z.M. Tahir

Malaysia

Foreign management institute denies claims of any wrongdoing

Malaysia

Court orders police to probe foreign management institute

Malaysia

BN vows to defend all 21 Melaka seats ahead of state election

Malaysia

Thai border town Dan Nok fades as new border crossing diverts Malaysian traffic

You may be interested

Events

AEON, Weixin Pay to provide Chinese travellers a greater seamless payment experience

Health

KPJ Healthcare, SingHealth to collaborate on healthcare training, research

By Alfian Z.M. Tahir

Events

Penang Institute to host annual George Town Literary Festival

By Ian McIntyre

Tech

Meta AI model exploits security flaw during cyber test, raising fresh safety concerns

Events

‘Fall in Love with Penang’ campaign launched to woo Malaysians to the state

By Ian McIntyre