Six major flood mitigation projects in Malaysia reported behind schedule

PETRA confirms delays in six priority Flood Mitigation Plan projects, outlining interim measures and funding of RM556.6 million to protect affected communities

Updated 7 months ago · Published on 22 Jan 2026 12:33PM

Six major flood mitigation projects in Malaysia reported behind schedule
Setbacks largely stem from land-related complications, including acquisition disputes and encroachments, as well as the need to relocate existing utilities - January 22, 2026

SIX high-priority flood mitigation projects under Malaysia’s Rancangan Tebatan Banjir (RTB) have fallen behind schedule, the Ministry of Energy Transition and Water Transformation (PETRA) confirmed in Parliament today.

Responding to a question from Tuan Shaharizukirnain Abd. Kadir, Member of Parliament for Setiu, Deputy Prime Minister Datuk Seri Fadillah Yusof detailed that of 43 nationwide RTB projects identified as high-priority, 37 are proceeding according to plan, while six projects – RTB Sungai Solok, RTB Likas, RTB Baling Phase 2, RTB Sungai Maran, RTB Sungai Klang Section 25, and RTB Sungai Damansara – have experienced delays as of December 2025.

Fadillah, who also serves as the Minister of Energy Transition and Water Transformation (PETRA). explained that these setbacks largely stem from land-related complications, including acquisition disputes and encroachments, as well as the need to relocate existing utilities.

Delays in obtaining technical approvals from multiple agencies, extreme weather conditions, and extraordinary flood events have further impacted progress at construction sites.

“PETRA takes these delays seriously and has implemented measures to improve governance of project execution,” Fadillah stated.

Initiatives include closer and more frequent monitoring of project progress, rescheduling of work plans, enforcement of contractual terms with penalties for underperforming contractors, and intensified coordination with state governments and local authorities to expedite approvals and resolve field-level issues.

While awaiting the completion of the RTB projects, PETRA, through the Department of Irrigation and Drainage (JPS), has prioritised short-term mitigation measures to protect communities in severely affected areas.

These interventions are being carried out under the River Conservation Project to Reduce Flood Risks, which encompasses river channel works, riverbank stabilisation, and upgrades to related drainage structures.

Between 2022 and 2025, a total of RM556.6 million was allocated nationwide to implement these smaller-scale mitigation works, targeting high-risk areas identified at the state level.

The ministry’s disclosure highlights both the scale of Malaysia’s flood mitigation efforts and the challenges of executing major infrastructure projects amid complex logistical, regulatory, and environmental constraints. - January 22, 2026

Spotlight

Malaysia

Bersatu-PAS cooperation ends, Muhyiddin says, as PN rift deepens

Malaysia

Calls grow for arrest of Nadzaruddin, Exco, for treason

Malaysia

Loke offers to resign as Transport Minister following Pardons Board decision

Malaysia

UMNO’s fundraiser for Najib draws sharp criticism on social media

Malaysia

Home Ministry yet to receive formal order on Najib house arrest

By Alfian Z.M. Tahir

Malaysia

PH Melaka, Bersatu in talks for wider election pact

You may be interested

Malaysia

Bangladeshi man sent for psychiatric evaluation after KLIA disturbance

Malaysia

Najib’s house arrest does not end other legal battles, MACC probe to continue

By Alfian Z.M. Tahir

Malaysia

Abdul Azeez and children ordered to declare assets within a month

Malaysia

Unhealthy air quality hits 23 areas as haze spreads across Malaysia

Malaysia

Malaysia Airlines jumps to 21st globally, scores major service gains in Skytrax Awards

Malaysia

Misleading online health ads to be referred to MCMC for action

Malaysia

Home Ministry yet to receive formal order on Najib house arrest

By Alfian Z.M. Tahir

Malaysia

Three motorcyclists killed, nine injured in 15-vehicle crash in Ipoh