Malaysia

Fault lines at Bukit Kukus construction site slows down highway project

Estimated completion date of highway’s first section pushed back to October

Updated 5 years ago · Published on 09 Apr 2021 9:00AM

Fault lines at Bukit Kukus construction site slows down highway project
State executive councillor for infrastructure and transport Zairil Khir Johari says that the movement control order has also contributed to the delay. – Twitter pic, April 9, 2021

by Rachel Yeoh

GEORGE TOWN – Geological fault lines have been discovered at certain sections of the hilly area over which the Bukit Kukus Highway on the island is being constructed, contributing to delays in the project’s completion.

It is estimated that the fault lines, found after some hill cutting was done, have led the project to only be ready in October this year.

It was originally supposed to have been completed by May.

The highway is meant to link Lebuh Bukit Jambul to Jalan Tun Sardon and Jalan Paya Terubong in the interior of the island.

State executive councillor for infrastructure and transport Zairil Khir Johari said that the movement control order has also contributed to the delay.

He told a press conference yesterday that necessary works are being undertaken, including slope repairs and protection works, construction of retaining wall and installation of a T-beam on the “main line”.

He explained that geologists who had surveyed the soil and rocks at the hill-cutting stage determined that certain redesigning had to be done at a few sections for safety reasons.

“These issues would not have been known until the cutting of the slope was completed – even if you did soil investigation beforehand, which was done. That is why part of the scope of the project is to send in geologists,” he said.

He said the consultant had to redesign and move the highway alignment in the affected areas for safety reasons, and construction is ongoing again.

This affected part of the highway, which is to have two segments, is now estimated for launch on October 23. It is part of the whole project covering more than 5km. 

According to Zairil, the completion cannot be determined because the two segments are being done by private developers who are currently affected by cash flow issues.

The overall progress of the Bukit Kukus Highway project in Penang is slightly behind schedule, while the state government insists its financial costs have not exceeded allocated funds. – ringgitplus.com pic, April 9, 2021
The overall progress of the Bukit Kukus Highway project in Penang is slightly behind schedule, while the state government insists its financial costs have not exceeded allocated funds. – ringgitplus.com pic, April 9, 2021

The whole highway is jointly undertaken by Penang Island City Council (MBPP) (2.8km), Geo Valley Sdn Bhd (800m), and PLB Land Sdn Bhd (1.4km).

 The PLB Land and Geo Valley sections have encountered delays. The PLB construction is currently 30% complete and the Geo Valley portion is 12% complete.

To navigate these delays, an additional RM4 million link road is being built to allow those using the MBPP section of the highway to connect to Jalan Paya Terubong. 

Zairil stressed that the total expenditure is still within the stipulated budget despite the additional link road.

“It is quite a fantastic project and very challenging at the same time because of the rocks. But everything is being done properly and as far as the council is concerned, everything is on time.”

He said the delay could not have been predicted or avoided.

According to consultant engineer GEA (M) Sdn Bhd, whose representative only wanted to be known as Koo, the project is being executed with diligence though there are many challenges, especially when it involves big boulders.

“We had to do rock blasting, but we cannot do it during the MCO period. We also needed the blasts to be very controlled as there are residents further down the road.

“So we had to be even more controlled in an already controlled situation. To do this project properly and safely will take time,” he said.

The overall project progress is at 94.83%, compared with 95.11% as scheduled. 

Once completed, this highway will qualify for the Malaysia Book of Records as having the tallest highway pier at 60m from the pile cap or foundation on the ground. – The Vibes, April 9, 2021

Related News

Community / 5h

More attention needed to care for the aged, says consumer association

Malaysia / 6h

Declining birth rate among the Chinese community worrying, says Penang Exco

Community / 2d

Penang introduces self-service cutlery return initiative at food court

Community / 2d

Penang urged to plant new trees before felling those deemed rotten

Community / 3d

Burst pipe affects 130,790 consumers in Penang

Malaysia / 3d

Penang Exco: More effort needed to identify, treat mental health and depression cases

Spotlight

Malaysia

Haze: MOH issues strict guidelines to ensure public health

Cocaine in shoes: Invited on vacation to Japan, only to end up as drug mules

Malaysia

PDRM awaits Philippine confirmation on alleged politician’s role in 521kg drug seizure

Malaysia

Elderly man dies after being beaten repeatedly

Malaysia

Preliminary report on helicopter crash in Long Lellang released; probe ongoing

Malaysia

‘Am I not the Tuanku?’ Tuanku Muhriz tells off Ismail Lasim (video)

By Alfian Z.M. Tahir

Malaysia

Donating to Najib: ‘One of the most foolish things I have seen’ – UM student

Malaysia

AKPS officer was seeking divorce before alleged killing, says brother

By Alfian Z.M. Tahir

You may be interested

Malaysia

PAS puts UMNO first in push for electoral pact ahead of next GE

Malaysia

Penang Islamic Affairs Department probes Muslim workers’ involvement in temple clean-up

By Alfian Z.M. Tahir

Malaysia

Najib’s house arrest: Home Ministry must clarify legal basis – Mahfuz

Malaysia

Retiree loses RM42,580 to fake ustaz’s RM300k money-doubling scam

Malaysia

PKR finalises Melaka election preparations, to contest nine state seats

Malaysia

E-wages dashboard to track compliance of RM2k minimum wage hike from June 2027

Malaysia

Man found dead with 70 per cent burns beside Johor railway tracks

Malaysia

Agong warns against using social media to spread hatred, insult others