Malaysia

Bukit Kukus project delayed again, this time due to fault lines

Highway opening pushed back 5 months to October after inspection authority discovers fissures spanning 2km along route

Updated 5 years ago · Published on 11 Apr 2021 10:00AM

Bukit Kukus project delayed again, this time due to fault lines
The Bukit Kukus Highway was found to cut through several fault lines, one of which is the Sg Air Putih-Sg Dondang fissure. – RACHEL YEOH/The Vibes pic, April 11, 2021

by Rachel Yeoh

GEORGE TOWN – The opening of the Bukit Kukus Highway will be delayed by another five months to October this year instead of May, partly waylaid by the movement control order as well as the discovery of fault lines at a hill the expressway cuts through.

Soil expert and scientist Kam Suan Pheng said the fault lines, which span a 2km stretch of the Bukit Kukus Highway, is a warning of things to come, such as the construction of the Pan Island Link 1 (PIL1) under the Penang Transport Master Plan.

The Bukit Kukus Highway is located at the southern end (location roughly highlighted in red) of a fault line that runs up north. It is called the Sg Air Putih-Sg Dondang fault line (light blue dotted line). – File pic, April 11, 2021
The Bukit Kukus Highway is located at the southern end (location roughly highlighted in red) of a fault line that runs up north. It is called the Sg Air Putih-Sg Dondang fault line (light blue dotted line). – File pic, April 11, 2021

According to the PIL1 Environment Impact Assessment (EIA) report, the highway, represented by the green line on the map, intersects with more than one fault line.

“Fault lines are fissures in the rock formed when molten magma from the hot interior of the earth solidifies to form rock. Geologically, Penang island is essentially made of granitic rock.

“Some fault lines are shallow; others are deep into the bedrock and require geotechnical investigations deep into the bedrock to be detected.

“In the Bukit Kukus Highway’s case, either the geotechnical investigations were not done, or were done but not deeply enough,” she said.

She added if the original alignment hits a fault line, then there needs to be a realignment, which is a costly affair and will inflict environmental damage.

She said fault lines constitute a weakness in the rock structure, which makes it possible for groundwater to enter the fault line and further weaken the rock.

State exco for infrastructure and transport Zairil Khir Johari assures there is no need to worry, as this is why Environment Impact Assessment studies are done: to ensure the project route is safe and workable. – RACHEL YEOH/The Vibes pic, April 11, 2021
State exco for infrastructure and transport Zairil Khir Johari assures there is no need to worry, as this is why Environment Impact Assessment studies are done: to ensure the project route is safe and workable. – RACHEL YEOH/The Vibes pic, April 11, 2021

“Imagine if the fault lines had already started cutting the hill slopes, and if workers had already began digging underground for the tunnel and hit a fault line. They would have had to realign the road or tunnel, leading to more cutting or digging and abandoning what has already been (worked on).

“Or, at best, they may have to utilise some engineering remedy, which will hike up the construction cost at the expense of taxpayers’ money, which is precisely what’s happening now with the Bukit Kukus Highway.

“This will add to delays and increased costs, while inconveniencing road users as the construction work drags on.”

State exco for infrastructure and transport Zairil Khir Johari assured there is no need to worry as all steps needed to ensure safety to future users and the environment have already been taken.

This delay is justified and unavoidable.

“That’s why we have EIA studies, geotechnical consultants, geologists and others.

“Obviously, steps will be taken to mitigate the situation during the designing stage, but sometimes things happen beyond our control. What we can do is to minimise the risk by taking all possible steps,” he told The Vibes.

“There is no way to find these fault lines other than what we did, which is to check after cutting through the hill at a certain gradient.

“This is what we did – take precautions.

“Hence, this delay is justified and unavoidable.” – The Vibes, April 11, 2021

Related News

Malaysia / 1mth

163 unauthorised non-Muslim places of worship identified on public land in KL – Hannah Yeoh

Malaysia / 3mth

Anwar reminds all parties to stick to the laws when preaching, building houses of worship

Events / 6mth

PM to launch two major projects in Penang over the weekend

Malaysia / 8mth

Penangites told to brace for ‘higher congestion rate’ as LRT project begins

Malaysia / 10mth

Guan Eng urges MOF to suspend SST on construction sales, commercial property rentals

Culture / 1y

Penang Hospital undergoing major upgrades to provide better services

Spotlight

Malaysia

Former head of a ministry's corporate communications unit acquitted of bribery charge

Malaysia

Two sisters die trapped in Johor house fire as escape routes cut off by flames

Malaysia

NS election speculation intensifies as Aminuddin granted audience with state ruler

Malaysia

Teenager who drove recklessly, causing death remanded for further investigation

Malaysia

Police looking for trio involved in violent armed robbery in Penang (video)

Malaysia

Family of five killed as car crashes into water pipe in Serian

Malaysia

'I was once spat on by a pakcik' — Marina denies fear of contesting Malay-majority seats

Malaysia

Jewellery shop among six premises destroyed in fire (video)

You may be interested

Malaysia

‘What wrong did I do?’ – asks PKR MP after loss of MyKhas access

Malaysia

Schoolteacher denies multiple counts of physical, digital sexual assault against 2 teens

Malaysia

Negeri Sembilan PH state assemblymen meet at MB's residence

Malaysia

Jewellery shop among six premises destroyed in fire (video)

Malaysia

Baby boy thrown from car in AMJ highway crash survives

Malaysia

Retiree loses nearly RM100k in TikTok investment scam after fraudsters target pension savings

Malaysia

Man who wanted to borrow RM500k, scammed of over RM400k

Malaysia

Cops dismantle 3 international fraud syndicates in Penang, arrest 32 suspects