MPs want 92% complete Kota Kinabalu Skybridge to be finished

Project involving 950m pedestrian walkway in limbo despite supposed 2017 completion date

Updated 5 years ago · Published on 27 Nov 2020 12:00PM

MPs want 92% complete Kota Kinabalu Skybridge to be finished

by Neil Chan

KOTA KINABALU – Failure to comply with conditions set by the Public Private Partnership Unit (Ukas) of the Prime Minister's Department has meant that funds already approved for the suspended Kota Kinabalu Skybridge project have been put on hold. 

Kota Kinabalu MP Chan Foong Hin said Ukas had previously approved RM63 million to Sunsea Development to build the skybridge here.

Up until now, the full amount has not been channelled for the project, which is now 92% complete.

The Sabah DAP secretary said this was the reply that he received on November 2 to a question on the matter from the minister in the Prime Minister's Department in Parliament’s special chambers.

The 950-metre long skybridge in the heart of the state capital is meant to be a walkway connecting the Oceanus Waterfront mall, Warisan Square, Api Api Commercial Centre, Sabah Centre Point mall and Asia City.

The 950-metre long skybridge connects the Oceanus Waterfront mall, Warisan Square, Api Api Commercial Centre, Sabah Centre Point mall and Asia City. – The Vibes pic, November 27, 2020
The 950-metre long skybridge connects the Oceanus Waterfront mall, Warisan Square, Api Api Commercial Centre, Sabah Centre Point mall and Asia City. – The Vibes pic, November 27, 2020

Chan said that in September last year, Kota Kinabalu Mayor Datuk Nordin Siman had met then state ministers Datuk Frankie Poon and Phoong Jin Zhe in Putrajaya, with then finance minister Lim Guan Eng, to try to resolve the suspended skybridge issue.

He said the present Sabah government should no longer delay the project and take up the offer by the federal government, as initiated by Lim in 2019, to complete the project and split the cost 50:50.

The contract to build the skybridge was between landowner Kota Kinabalu City Hall (DBKK) and Sunsea Development. Subsequently, Sunsea Development appointed Petrofiq Sdn Bhd as a subcontractor to carry out construction work.

The initial commencement date was set for April 2017, meaning that the project should have been completed by the end of September that same year.

Chan said that according to the reply, Petrofiq refused to complete the construction as it had not received full payment from Sunsea Development. – The Vibes, November 27, 2020

The skybridge project should have been completed by the end of September 2017. – The Vibes pic, November 27, 2020
The skybridge project should have been completed by the end of September 2017. – The Vibes pic, November 27, 2020

Related News

Malaysia / 2d

Budget 2027: Sabah, Sarawak to receive RM34.9b in federal allocations next year

Events / 6d

Sarawak and Sabah play key roles in weathering climate change

Malaysia / 1w

Address security concerns and let concert proceed – former Sabah CM

Malaysia / 3w

A message from our publisher and chairman

Malaysia / 3w

Sabah leaders condemn priest and nun joke at UMNO PAU

Malaysia / 4w

UMNO-PAS relations. Are things as rosy as it seems?

Spotlight

Malaysia

JPJ temporarily suspends VTA and registration for Chery Omoda 5

Malaysia

Eligibility for PTPTN repayment deferment to be verified with LHDN

Malaysia

Budget allocates two rounds of cash aid to millions of Malaysians in 70th Merdeka year

Malaysia

No Malaysians killed or injured in Riyadh airport attack, says Wisma Putra

Malaysia

JAIS probes viral religious ritual footage, says AI manipulation not ruled out

Malaysia

10-tonne truck ploughs into 11 vehicles: Police probe possible brake failure

World

Trump weighs joining Saudi strikes after deadly Houthi attack on Riyadh airport

You may be interested

Malaysia

Budget 2027: Anwar appears mindful of GE16, says analyst

By Alfian Z.M. Tahir

Malaysia

Not a single corruption scandal during Aminuddin's administration - Anthony Loke

Malaysia

Resident injured after crane topples onto nursing home

Malaysia

Selangor records moderate air quality, Johor extends school closures as haze persists

Malaysia

AMK slams Eric See-To for using the Quran as a tool for political attacks

Malaysia

Sinkhole forces closure of Gua Musang-Kota Bharu highway section

Malaysia

Eligibility for PTPTN repayment deferment to be verified with LHDN

Malaysia

Budget 2027 cuts taxes for M40 and SMEs, lowers threshold for 30% rate to RM1m