Earthworks for LRT project in Penang to start in fourth quarter of 2026

Before the construction can begin, the contractor needs to start a soil investigation along the LRT alignment

Updated 1 year ago · Published on 26 Apr 2025 3:35PM

Earthworks for LRT project in Penang to start in fourth quarter of 2026
Chow said the swearing in of Tun Ramli Ngah Talib as the Penang's ninth Yang di-Pertua Negri would be done on May 1 - April 26, 2025

by Ian McIntyre

PENANGITES can expect earthworks to commence on the RM10 billion Mutiara Light Rail Transit (LRT) line project in the fourth quarter of next year.

Contrary to reports which indicated that work will commence this year, the project owner - Mass Rapid Transit (MRT) Corporation Sdn Bhd's chief executive officer Datuk Mohd Zarif Hashim stressed that major construction will start in the fourth quarter of next year.

Before the construction can begin, the contractor needs to start a soil investigation along the LRT alignment, he pointed out.

"In the past, this type of soil investigation has already been done. So, the data is already there. It's not a new thing, but, it's possible that there are some situations or locations that the contractor needs to first address" he said after attending the Mutiara Line LRT Hari Raya Aidilfitri open - house here.

Penang Chief Minister Chow Kon Yeow was the guest of honour.

The last soil investigation was done around 2018; hence, he said that the contractor needs to do another round of soil investigations in the area.

He said that once the soil investigation is completed, the contractor will be able to finalise the design, as it needs to take the soil conditions into account.

"Then, once the design is finalised, the first step is to assess whether there are any utilities at the site that need to be relocated," he said.

He said some of the utilities on the road reserve will need to be relocated first.

During the relocation, which Zarif expects to start this year, small machinery will be seen working to relocate the utilities.

"However, for the big scale of construction, like the viaduct, I think you can see it taking shape by quarter four next year. Next year is only 2026. With the target delivery date on Dec 31, 2031. we still have five years to go," Zarif said.

He said it is normal that during the initial years, projects like the LRT line would follow an S-curve once it reaches critical mass.

“It is not like a spike and therefore, you will see slow progress until sometime next year.

And I would say the S-shape will come in after 2027, 2028, where you can see the slope of the curve. By the time we reach 2029, it is already at that top of the S curve and that brings us for another two years until the end of 2031," he said.

Zarif said MRT Corp was doing its best in order to expedite the project.

On another matter, Chow revealed that the swearing in of Tun Ramli Ngah Talib as the Penang's ninth Yang di-Pertua Negri would be done on May 1 at the historic Dewan Sri Pinang complex in George Town.

Ramli, aged 84, succeeds Tun Ahmad Fuzi Abdul Razak, who will step aside after serving one - term as the state's governor since 2021.

Ramli will also assume his term from May until April 30, 2029.

"Tun Ramli is an experience administrator and has served both the nation and Perak well during his tenure as mentri besar and a deputy federal minister, as well as the Dewan Rakyat Speaker," said Chow.

The state will also organise a mega appreciation dinner for Ahmad Fuzi on April 28, as a gesture of gratitude towards his services for Penang. - April 26. 2025.

Related News

Malaysia / 1w

‘No problems here. We are still united and strong’ – Penang CM

Malaysia / 1w

Penang: CM defends allocations after claims from Kedah MB that it is just a ‘small state’

Malaysia / 2w

PSR project, respect court decision – Penang CM

Malaysia / 3w

Video of foreigner urinating on MRT station escalator goes viral (video)

Malaysia / 1mth

Video of individuals, believed to be Rohingyas, sleeping in MRT goes viral

Events / 1mth

Penang launches sharing integrative platform to reduce shortage in key high-skilled areas

Spotlight

Malaysia

‘No such thing as Bangkok Move or Dubai Move’ – Ahmad Zahid

Malaysia

KSN: Rectify long waiting times, service challenges and workforce constraints at UMMC now

Malaysia

LGE trial: 4 to 5 meetings held before open tender bidding for road, undersea tunnel projects - witness

Malaysia

Najib marks 73rd birthday as legal battles continue from behind prison walls

Malaysia

Court orders police to probe foreign management institute

Malaysia

UMNO pushes back against Hamzah’s ‘PBN’ proposal, says BN-PN cooperation is not a new coalition

Malaysia

Form four student killed after car crosses into opposite lane in Setiu crash

World

France heatwave death toll rises to nearly 5,800 as extreme temperatures trigger record mortality

Culture

Penang: Three refurbished tourism attractions to be ‘reopened’ soon

By Ian McIntyre

You may be interested

Malaysia

UMNO pushes back against Hamzah’s ‘PBN’ proposal, says BN-PN cooperation is not a new coalition

Malaysia

Ministry boosts RE drive with 127.59mw Pasir Mas solar projects as green transition gains momentum

Malaysia

MACC records statements from 10 KWAP and MOF officials in RM200m eFishery investment probe

Malaysia

Court orders police to probe foreign management institute

Malaysia

Two-year-old girl killed after being hit by lorry driven by grandfather in Kedah

Malaysia

Ex-bank analyst sentenced to 3 years jail for unlicensed securities dealings and misusing UTC title

Malaysia

Police seize more than 7,400 yaba pills in two Kelantan drug busts

Malaysia

Johor appoints 10 deputy exco to strengthen administration