Limited capacity will continue until the bypass line from Kimanis to Sandakan is completed within 2 days, said Sabah Electricity

Updated 10 months ago · Published on 14 Sep 2025 11:36AM

Collapsed tower triggers massive blackout in Sabah’s east coast
Sabah Electricity says a collapsed high-voltage transmission tower due to a landslide behind the major power outage in six east coast districts and affected millions of residents - September 14, 2025

by Jason Santos

A HIGH-VOLTAGE transmission tower that collapsed during a landslide after heavy rain on Saturday evening has been identified as the cause of a widespread blackout across Sabah’s east coast.

The tower, which was identified as Tower 5, was part of the 275kV Kolopis–Segaliud line, which transmits electricity from power plants on the west coast to intake substations in Sandakan that supply the entire east coast.

The outage, which began at 5.05pm on Saturday, affected Sandakan, Lahad Datu, Kinabatangan, Kunak, Semporna and Beluran.

The tower located in Kampung Sarapung near the Kolopis Main Intake Substation in Penampang, gave way after days of relentless rain undermined its foundation, Sabah Electricity Sdn Bhd (SESB) Chief Executive Officer Mohd Yaakob Jaafar said on Sunday.

Once the conductors fell to the ground, the line could no longer be re-energised, he added.

“When the tower slid, the wires touched earth. The system will always trip back in that condition, so it cannot be switched on again until the structure is rebuilt,” he told reporters at a briefing in Kota Kinabalu.

Mohd Yaakob said about 230,000 registered users, representing nearly 1.2 million residents, were affected by the blackout.

Around 70,000 of these users will continue to face rotational outages during peak hours until bypass works are completed.

In the meantime, he noted partial supply had been restored by restarting generation units in Sandakan and Tawau, but capacity would remain limited until a bypass from Kimanis to Sandakan is completed within two days and emergency towers are installed at the collapsed site within the next eight days.

According to him, more than 50 technical staff and contractors have been deployed to the site, working around the clock in difficult terrain where mud, fallen trees and damaged access roads have slowed progress.

A permanent replacement tower is expected to take around three months to build, he added.

“This was a natural disaster. Continuous heavy rain caused soil erosion that led to the failure of the structure,” he said.

The collapse is Sabah’s most serious transmission failure in a decade, recalling a similar tower incident in Lahad Datu in 2015 and Sabah Electricity is considering early-warning technology, including satellite imaging and geological monitoring, to detect landslide risks along its transmission routes, said Mohd Yaakob. - September 14, 2025

Spotlight

Malaysia

PRNNS: Loke: 'We must win all 11 seats to help PH form state government'

Sports & Fitness

Spain ends Argentina’s World Cup reign with extra-time triumph to reclaim global crown

World

Cat found alive after being buried under Venezuela quake rubble for days (video)

Malaysia

“Resign if you attack fellow Unity Government partners,” Anwar enforces discipline

Malaysia

PH youth wing calls on BN ministers to quit cabinet over PN electoral alliance

Malaysia

Rosmah asks for prayers as Najib prepares for medical procedure

Malaysia

Woman at a loss after fake Hong Kong lawyer offers to recover money from previous scam

You may be interested

Malaysia

Klang Valley storm claims motorist's life as flash floods hit Petaling Jaya (video)

Malaysia

BN-PN understanding puts Barisan in strong position for NS polls

Malaysia

PRN Negeri Sembilan: Four seats in focus, battle expected to be tougher than Johor

Malaysia

Syed Saddiq completes 170km Thanksgiving Charity Run after acquittal, surpassing fundraising target

Malaysia

SKDS diesel subsidy rollout in Sabah and Sarawak gains momentum

Malaysia

PRNNS: Loke: 'We must win all 11 seats to help PH form state government'

Malaysia

PRN Negeri Sembilan: Handshake between Hadi Awang and Asyraf Wajdi centre of attention

Malaysia

BN-PN pact in Negeri Sembilan polls centred on stability and full 36-seat victory target