Malaysia

KLIA Aerotrain contractors hit with RM9.1 million penalty for project delays

Malaysia Airports imposes daily fines on Alstom IJM-Pestech Joint Venture after new KLIA aerotrain project failed to meet completion deadlines

Updated 7 months ago · Published on 27 Feb 2026 9:19AM

KLIA Aerotrain contractors hit with RM9.1 million penalty for project delays
Independent assessment confirms safe operational status - February 27, 2026

MALAYSIA Airports Holdings Bhd (MAHB) has imposed a total liquidated and ascertained damages (LAD) penalty of RM9.1 million on contractors Alstom IJM Construction Sdn Bhd and Pestech Technology Sdn Bhd (IJMC-Pestech Joint Venture) for delays in delivering the new aerotrain system at Kuala Lumpur International Airport (KLIA).

The Ministry of Transport (MOT) confirmed that the penalties cover 91 days, from 1 April to 30 June 2025, calculated at RM100,000 per day in accordance with contractual terms.

“As stipulated in the contract, the LAD imposed amounts to RM100,000 per day, totalling RM9.1 million,” the ministry said in a written response posted on the Dewan Rakyat website.

The statement was made in response to a question from Khoo Poay Tiong (PH-Kota Melaka) regarding the penalty imposed by MAHB on the joint venture for failing to deliver the KLIA aerotrain project satisfactorily.

Earlier, MAHB stated that an independent rail assessor had confirmed that the KLIA Aerotrain system is operating as intended. The assessor noted that service disruptions observed since the system began operating are common during the early operational phase of complex rail systems.

“The assessor found that these disruptions do not pose safety risks, as structural engineering controls and continuous monitoring are in place to manage issues effectively,” MAHB said.

The LAD imposition underscores the government’s enforcement of project delivery obligations, while independent evaluations reassure that operational safety and engineering standards at KLIA remain uncompromised despite the delays. - February 27, 2026

Spotlight

Malaysia

JPJ temporarily suspends VTA and registration for Chery Omoda 5

Malaysia

Eligibility for PTPTN repayment deferment to be verified with LHDN

Malaysia

Budget allocates two rounds of cash aid to millions of Malaysians in 70th Merdeka year

Malaysia

No Malaysians killed or injured in Riyadh airport attack, says Wisma Putra

Malaysia

JAIS probes viral religious ritual footage, says AI manipulation not ruled out

Malaysia

10-tonne truck ploughs into 11 vehicles: Police probe possible brake failure

World

Trump weighs joining Saudi strikes after deadly Houthi attack on Riyadh airport

You may be interested

Malaysia

Zara Qairina’s mother: No doctors recorded injuries consistent with being beaten

Malaysia

Indonesia deploys 60,000 personnel to contain fires as haze threat persists

Malaysia

Malaysia, Egypt seek higher-level partnership after 67 years of diplomatic ties

Malaysia

Budget 2027 debate begins as MPs press government on healthcare, exports and unpaid KPF shares

Malaysia

19-year-old charged with murdering student in Kuantan

Malaysia

One of five suspects arrested over helmet attack on 23-year-old in Sabah

Malaysia

Used-car buyers lose RM25k after paying fake middlemen in Miri

Malaysia

Tiger spotted by roadside on Fraser’s Hill–Kuala Kubu Bharu route