Malaysia

Senior engineers express concern over viability of Penang LRT

Prasarana Malaysia Bhd’s first CEO Datuk Ridza Abdoh Salleh the present alignment would encounter many hurdles during the construction phase.

Updated 1 year ago · Published on 21 Jan 2025 4:54PM

Senior engineers express concern over viability of Penang LRT
The LRT project, which has the full support of both the federal and state governments, has been hit with criticisms since it was first conceptualised - January 20, 2025

by Ian McIntyre

TWO senior engineers have expressed concerns over the project viability of the proposed Mutiara Light Rail Transit (LRT) line, citing acute land shortage on the island and a flawed ridership projection as among their main issues.

Prasarana Malaysia Bhd’s first chief executive officer (CEO) Datuk Ridza Abdoh Salleh took to social media to express his doubts about the LRT, underlining that its present alignment would encounter many hurdles during the construction phase.

The LRT project, which has the full support of both the federal and state governments, has been hit with criticisms since it was first conceptualised by former Chief Minister Lim Guan Eng in 2014.

Now over a decade later with approval to commence earthworks obtained for the special vehicle platform, some quarters from the engineering fraternity continue to express their reservations about it.

 Ridza posted that the Penang LRT is facing a major huddle to locate the depot at the "Pesta Pulau Pinang" site in Sg Nibong - a strategic proposed station for the 29km long first phase which snakes from Komtar, George Town to the now under reclamation island - Silicon Island off Batu Maung, near the Penang International Airport in Bayan Lepas.

"The dilemma is not going to stop here. More will come, especially with the alignment, location, and footprint of the stations, substations, parking facility, and access to stations for public and maintenance vehicles, and crew. During construction, access for cranes, launchers, and erectors require space, but at the same time, the public (life) must be uninterrupted," said Ridza, who blogs on public transport alternatives.

"Penang LRT is a project just too big, especially for the island side. Once completed, it will struggle to find passengers to fill the cars from 6 am to midnight. With a 700,000-plus population, where can you find 200,000 to 300,000 ridership daily? If you cannot, the LRT will be operating below cost and will require heavy financial subsidy by the federal government year on year."

The traffic congestion will not disappear easily, said Ridza.

"It may get worse. A lot of spaces are taken up by the LRT system and the station, and the available spaces for buses, cars, motorcycles, and pedestrians will become much less," he said.

Summarising that it is not a viable project, Ridza said that having the power to commission any project is not sufficient. 

A white elephant in the making?

"It must come with the commitment to safeguard the society and the public from being exposed to harmful side effects. It looks like a whiter-than-white elephant is about to be manufactured, and it's in progress."

Former Penang chief engineer Lim Thean Heng echoed what Ridza said, stressing that there is a need to upgrade the transport system here with a comprehensive public network but the LRT is not the "game-changer,"  the state should want or need.

He claimed that the ridership figures were inaccurate, and the project looked "rushed" without due consideration to the present needs of the road users here.

The construction stage may also cause commuters on the island to endure a nightmare experience for at least the next five years, he pointed out.

He also challenged the media to speak to the Institute of Engineers about the project.

From the start of 2013 following the now overlooked Penang Transport Master Plan (PTMP) by Halcrow Consultants, a touted civil engineering firm, the LRT project was a "disaster" in the making, said Lim.

Although the project is destined to commence later this year, as the developer - MRT Corp Bhd has finalised the first phase in appointing the contractor, Lim claimed that there was no open - tender practised and it was tendered out to SRS Consortium, who was the initial project delivery partner, said Lim.

Claiming that the Halcrow group is now disbanded, Lim said that the PTMP advocated the concept of "moving people, not vehicles" in the fragile ecology of Penang Island.

SRS Consortium was awarded the first phase of the project, stretching 24 km from Komtar to the Silicon Island of the Penang South Reclamation project. 

The contract involves 19 stations and other related facilities.

"This is intended to simplify and expedite the implementation and initial execution of the project,” Transport Minister Anthony Loke Siew Fook reportedly said after a signing ceremony for the contract earlier this month.

The contract has a ceiling of RM8.31 billion, Loke noted.

The long overdue project is expected to alleviate severe traffic congestion in Penang Island. 

Once the notice to proceed is issued, Gamuda will have six years to complete the contract, according to a statement from the company.

Loh Phoy Yen Holdings Sdn Bhd and Ideal Property Development Sdn Bhd each own 20% of SRS. 

MRT Corp is the project developer and asset owner of the Mutiara Line.

The tender for the second phase of the project, which runs from the Macallum in George Town to the Penang Sentral Station in Butterworth, is expected to be called in July.

Overall, the line will feature 21 stations covering a total distance of 29.5km. - January 21, 2025.

Related News

Malaysia / 1w

Aerotrain at KLIA Terminal 1 resumes 24-hour operations from June 1 - Loke

Malaysia / 1w

Bus driver with 29 traffic summonses arrested on suspicion of reckless driving (video)

Malaysia / 1w

LRT train derailment: Serious action must be taken - Anthony Loke

Opinion / 2w

Improvement in making Hari Raya Haji travel more bearable

Malaysia / 2w

3.3 million vehicles expected to flood highways in conjunction with Aidiladha, school holidays – LLM

Malaysia / 2w

1.9 million vehicles expected to enter Penang for long holidays starting this week

Spotlight

Malaysia

4WD driver who drove backwards on highway nabbed, positive for drugs (video)

By Ian McIntyre

Malaysia

Seven in ten Malaysian workers earn RM5k or less - economist

Malaysia

PAS ends political cooperation with Bersatu

Malaysia

BN banking on Malay vote strategy that delivered 40-seat Johor win, says analyst

By Alfian Z.M. Tahir

World

Southern Philippines quake kills at least 19, triggering minor tsunami waves (video)

Malaysia

Music teacher claims trial to 14 charges of sexual assault against 6 students in Sabak Bernam

Malaysia

‘Be more cautious when issuing statements’ – Fahmi

Malaysia

BERSAMA opens candidate applications, invites Malaysians to step forward

You may be interested

Malaysia

'Id rather not hold the MB position than sit at the same table with DAP' - Onn Hafiz

Malaysia

Chow and Lim come together to resolve infrastructure issues

By Ian McIntyre

Malaysia

Govt reaffirms OPEC+ commitment as global energy markets face heightened volatility, transition pressures

Malaysia

Crackdown on World Cup betting syndicates as police warn of influencer-led gambling promotions

Malaysia

Govt rejects ‘emotion-driven’ refugee policy amid growing public pressure

Malaysia

MACC undergoes senior shake-up as new Chief Commissioner begins reform push

Malaysia

Tsunami alert: Stay calm and obey instructions from the authorities – Hajiji (video)

Malaysia

‘Be more cautious when issuing statements’ – Fahmi