Penang LRT project progressing as scheduled, says project owner

MRT Corp, as the asset owner and project developer of the Mutiara Line, said over the past three months, it has been actively driving the project forward. 

Updated 1 year ago · Published on 22 Apr 2025 12:22PM

Penang LRT project progressing as scheduled, says project owner
One of the key activities undertaken was securing necessary approval for advance works - April 22, 2025

by Ian McIntyre

THE proposed Penang Mutiara Line Light Rail Transit (LRT) project remains on track and is on schedule despite concerns over possible delays.

Mass Rail Transit (MRT) Corporation Sdn Bhd, the project owner assured that the project is on schedule and expressed its gratitude to the public for their concern.

MRT Corp, as the asset owner and project developer of the Mutiara Line, said over the past three months, it has been actively driving the project forward. 

One of the key activities undertaken was securing necessary approval for advance works under Section 20A of the Town and Rural Planning Act 1976.

This approval was finally cleared recently on April 15, this year.

MRT Corp has also made significant headway in the land acquisition process, having secured access to 86 plots of land to date and the gazette of Section 8 under the Land Acquisition Act 1960. 

This progress, earlier than the targeted date of October 2025, forms a key milestone in keeping the project on track.

Meanwhile, SRS Consortium Sdn Bhd (SRS), the appointed civil main contractor for Package 1 of the project, has been working to fulfil several post-award conditions outlined in the contract. 

The official Notice to Proceed (NTP) can only be issued to SRS once these conditions are satisfactorily met.

As the design and build civil contractor for Package 1, SRS will need to finalise designs and construction drawings for civil structure within the project scope after the issuance of the NTP. 

Another critical aspect of pre-construction work is the relocation of utilities, which must be completed before any station or viaduct related construction activity can take place.

"We appreciate the public’s continued support and understanding as we advance through this initial phase of project development."

The project that will cost an estimated RM13 billion, and consists of 21 stations, running from the ongoing reclaimed Silicon Island to Penang Sentral in Butterworth, covering a track distance 29.5km.

It is billed as the largest ever inland infrastructure undertaking in Penang. - April 22, 2025

Related News

Places / 1w

Penang LRT: Traffic diversions imposed for major roadworks

Malaysia / 1mth

MRT suddenly stops at Bukit Bintang and all went dark (video)

Community / 2mth

Penang: Mutiara Light Rail Transit project: key delivery milestones achieved

Malaysia / 3mth

Video of foreigner urinating on MRT station escalator goes viral (video)

Malaysia / 3mth

Video of individuals, believed to be Rohingyas, sleeping in MRT goes viral

World / 4mth

Rat spotted scurrying around on Singapore East-West Line MRT train (video)

Spotlight

Malaysia

Tuanku Muhriz to focus on state affairs; Will not attend Conference of Rulers meeting

Malaysia

Sarawak projects record RM15.09b revenue, budgets RM10.1b for development in 2027

Malaysia

Sultan Nazrin: Delay in environmental action places future generations at risk

Malaysia

Woman allegedly raped at KL shopping centre after being threatened with intimate video

Malaysia

Jordan’s King confers highest civilian honour on Sultan Ibrahim

Malaysia

Driver monitoring aims to stop commercial vehicle crashes before they happen

Malaysia

KTMB heritage sites set for tourism makeover, says Loke

Malaysia

Zara Qairina’s mother: No doctors recorded injuries consistent with being beaten

You may be interested

Malaysia

One of five suspects arrested over helmet attack on 23-year-old in Sabah

Malaysia

RM5b JENDELA allocation to expand internet access in rural Malaysia

Malaysia

Government project contracts to be disclosed from next year - Anwar

Malaysia

JPJ temporarily suspends VTA and registration for Chery Omoda 5

Malaysia

PAS Senator comes forward in defence of Eric See-To

Malaysia

MACC warns data leaks could expose witnesses, derail corruption probes

Malaysia

Students can express views or criticism without fear of prosecution - PM Anwar

Malaysia

Express bus crashes into school surau at site of fatal SUV accident