Malaysia

A-G report: DBKL yet to reach flood mitigation goals

Review also notes weaknesses in programme management

Updated 3 years ago · Published on 03 Aug 2022 8:27PM

A-G report: DBKL yet to reach flood mitigation goals
A man stands at Dataran Merdeka during flash floods that hit the Klang Valley in December last year. – The Vibes file pic, August 3, 2022

KUALA LUMPUR – Kuala Lumpur’s flood mitigation management has not yet achieved its objectives based on the scope and audit samples covering six of the 23 (or 26.1%) of the flood mitigation projects under the Kuala Lumpur City Rainwater Management Drainage System Master Plan (Master Plan), as well as flash flood hotspots.

According to the Auditor-General’s Report 2021 Series 1, Kuala Lumpur City Hall has not fully implemented the proposed short-term flood mitigation measures (2018-2022) under the Master Plan, causing the problem of flash floods to remain unresolved.

“In addition, flash floods keep recurring even after the implementation of flood mitigation projects.

“Furthermore, there are weaknesses in aspects of programme management, including appointment of contractors, contract administration, maintenance work as well as components and configurations of the flood reservoirs and recreation ponds,” said the report.

To overcome the weaknesses highlighted and to ensure they do not recur in the future, the auditor-general has proposed that city hall implement flood mitigation projects in a balanced and consistent manner – by taking into account the consultants’ proposals and the requirements of hotspot projects, so that the implementation of flood mitigation programmes are more comprehensive and holistic.

The auditor-general also proposed that local authorities conduct an outcome evaluation of the mitigation programme based on city hall’s standard operating procedure in terms of its effectiveness in dealing with floods.

“Review the components and configurations of flood reservoirs and recreation ponds owned by city hall and carry out scheduled maintenance works to ensure that the flood reservoirs and recreation ponds are functioning optimally.

“Maintain timely records of assets or infrastructure of rivers and flood reservoirs and recreation ponds, as well as improve on-site monitoring methods for project supervision and project maintenance,” it said. – Bernama, August 3, 2022

Related News

Malaysia / 1mth

PJ MP slammed for ‘media statements without solutions’

Malaysia / 1mth

Heavy rains trigger flash floods in several locations around the Klang Valley (video)

Malaysia / 1mth

Jalan Kuchai Lama hit by floods again after four years (video)

Malaysia / 4mth

KL Mayor ordered to fix weaknesses in DBKL contract management

Malaysia / 6mth

Hatyai floods: Over 1,000 Malaysian vehicles stranded, submerged in hotel underground parking

Malaysia / 6mth

1,248 Malaysians in Southern Thailand have been rescued as of 4pm

Spotlight

Malaysia

Bersatu-PH tie-up a possibility as coalition seeks Malay support, analyst says

By Alfian Z.M. Tahir

Malaysia

Woman molested on her way home from work (video)

Malaysia

Court allows Daim's daughter to permanently keep passport

Malaysia

Santiago pokes holes in data centre hype, asks: Who really benefits?

By Alfian Z.M. Tahir

Malaysia

Jeweller vows to pursue Rosmah until ‘every penny’ is recovered as RM67.5m battle enters enforcement phase

Malaysia

Ambulance carrying two injured men crashes en route to hospital after MPV collision in Besut

Malaysia

Man blames 'lack of love' for sexual assault on teens

Business

BNM's OPR to stay at 2.75 pcent in 2026 amid strong domestic demand - Kenanga IB

Malaysia

Missing jewellery: Rosmah ordered to pay RM67.5 million

You may be interested

Malaysia

Police rule out bullying, schoolgirl’s fall from building in Pontian under investigation

Malaysia

Zero tolerance for corruption as JPJ faces fresh bribery allegations - Minister warns

Malaysia

Simpang Renggam tragedy: Teenager released on police bail

Malaysia

EPF to shut all remittance counters nationwide from July 1 in major digital services push

Malaysia

Johor and NS polls first major test of post PAS-Bersatu political order

Malaysia

Fiscal deficit target under pressure as surging subsidy costs test Malaysia’s consolidation plans

Malaysia

Undangs accused of clinging to power as directive raises questions over legitimacy

Malaysia

Anwar warns global order lacks direction, calls for renewed international cooperation