Phase one of Sarawak Pan Borneo Highway 86% complete: Fadillah

Several more sections expected to be opened this year, says minister

Updated 4 years ago · Published on 04 Sep 2022 9:10AM

Phase one of Sarawak Pan Borneo Highway 86% complete: Fadillah
Public Works Minister Datuk Seri Fadillah Yusof says another three sections of the Pan Borneo Highway in Sarikei, Bukit Begunan and Lambir are facing various challenges including a site that needs to be re-examined. – Bernama pic, September 4, 2022

KUCHING – Phase one of the Pan Borneo Highway project in Sarawak is now 86% complete, according to Public Works Minister Datuk Seri Fadillah Yusof.

He said several more sections of the highway are expected to be opened this year and three other sections in Sarikei, Bukit Begunan and Lambir are expected to be completed next year.

“The three sections are facing various challenges including a site that needs to be re-examined.

“There are even some that require reprocessing of the design due to the unsuitable terrain conditions,” he told reporters after attending the Sarawak Media Engagement programme here last night.

Phase one of the RM16.117 billion Pan Borneo Highway project involves the construction of a 786km stretch of road from Telok Melano to Miri.

Meanwhile, Fadillah said the Finance Ministry is also currently finalising the procurement aspect for the Sarawak-Sabah Link Road (SSLR) Phase 2 Project and the Trans Borneo Highway (LTB) Project and a ceiling allocation of RM12 billion has been set for both projects.

“We also hope to be able to finalise the awarding of contracts to contractors this year and by early next year this project will be able to start,” he said.

On August 7, Prime Minister Datuk Seri Ismail Sabri Yaakob said the federal government had approved the SSLR Phase 2 Project and the LTB Project, and construction would commence as early as next year.

Ismail Sabri said technical research for the Phase 2 SSLR and LTB project connecting Miri, Limbang and Lawas is now in the final stage, with construction expected to take three to five years.

The prime minister also said that the project would not only allow residents of northern Sarawak to reach Sabah through two road network options but also benefit residents in Mulu, Long Seridan, Nanga Medamit, Long Lopeng, Ba’kelalan and Merarap who currently rely on logging roads to commute. – Bernama, September 4, 2022

Related News

Malaysia / 4d

Sarawak’s snap polls: A clean sweep for Abang Jo’s GPS?

Education / 1w

Schools to get extra holidays for Deepavali

Malaysia / 1w

Election Commission to meet on Nov 6 to set key dates for Sarawak polls

Malaysia / 1w

Sarawak PRN: PAS almost certain of contesting in 3 DUNs

Malaysia / 1w

Abang Johari urges parties to respect law as Sarawak heads for polls

Malaysia / 1w

Sarawak DUN to be dissolved on Monday, October 26 – Abang Jo

Spotlight

Malaysia

Asyraf denies Najib ready to pay RM50m fine for house arrest

Malaysia

Malaysia’s average household size falls to 3.8 people

Malaysia

Najib's former wife Tengku Puteri Zainah in critical condition in ICU

Malaysia

More than 117,000 harmful online posts removed as government steps up enforcement

Malaysia

1,000 families receive Deepavali aid to ensure no one misses festive celebrations

Malaysia

Mother, daughter fined RM500 each for obstructing Muar council enforcement officers

Malaysia

Kelantan records 1,446 khalwat cases in three years

Malaysia

Negeri’s deposed Undang, chieftains fail to stop committal proceedings

You may be interested

Malaysia

Court of Appeal acquits Da’i Syed of rape charge

Malaysia

Anwar challenges Hadi over ‘Dajjal’ label

Malaysia

No special treatment for anyone involved in domestic violence – Penang Exco

By Ian McIntyre

Malaysia

Malaysia can prosecute foreign cybercriminals targeting local systems, victims

Malaysia

Malaysia favours diplomacy over legal action in tackling transboundary haze with Indonesia

Malaysia

Insurers must not use litigation to wear down accident victims, court rules

Malaysia

Student surprises Anwar with 44-year-old photograph of his first Permatang Pauh victory

Malaysia

Matrade exposes scam involving fake procurement orders, advance payment demands

By Alfian Z.M. Tahir