Bukit Begunan section of Pan Borneo Highway to be ready in Nov: Nanta

Postponement from June due to landslides making redesign with different materials necessary, says minister

Updated 3 years ago · Published on 06 Feb 2023 6:27PM

Bukit Begunan section of Pan Borneo Highway to be ready in Nov: Nanta
A view of the Pan Borneo Highway project, which Works Minister Datuk Seri Alexander Nanta Linggi was informed is 88.5% completed. – Bernama pic, February 6, 2023

SRI AMAN – Phase One of the Pan Borneo Highway (LPB) project from Simpang Pantu to Batang Skrang in the Bukit Begunan section here is set to be completed in November, said Works Minister Datuk Seri Alexander Nanta Linggi.

He said, according to the original plan, the project in the area was scheduled to be ready in June but a time extension became necessary following landslide incidents which required the project’s structure to be re-designed using different building materials.

“Previously, the project design for this section used earthfill as an embankment but there was a failure in the project and it was changed to a design using rockfill after a detailed study was carried out,” he told a media conference after surveying the Bukit Begunan section here today.

Nanta said the use of boulders weighing 721,000 cubic metres for the embankment project was 50% complete, thus, resulting in the federal government’s additional allocation of about RM70 million.

Earlier, Pan Borneo Highway unit head of the Sarawak Public Works Department Awang Mohamad Fadillah Awang Redzuan briefed Nanta on the latest status of the highway project in the area.

According to Awang Mohamad Fadillah, the construction work for the stone embankment, which started on April 8, 2022, would increase its stability for the LPB construction as well as reduce the construction time.

Nanta was also informed that, so far, the overall LPB project was 88.5% completed. – Bernama, February 6, 2023

Related News

Malaysia / 1d

Sabah and Sarawak can become 'kingmakers', determine who will lead Federal government

Malaysia / 4d

Haze getting worse, five areas in Sarawak record unhealthy API readings – DOE

Malaysia / 1mth

Abang Jo: Bintulu Port strengthens Sarawak’s position as strategic maritime, industrial hub

Malaysia / 1mth

Minister: Sarawak made right decision to reject entry of Rohingya refugees in 2017

Malaysia / 2mth

Sarawak seeks China collaboration to fix growing doctor shortage

Malaysia / 2mth

What matters: Policies that truly understand the rakyat

Spotlight

Malaysia

Sarawak schools told to halt outdoor activities as haze pushes air quality into unhealthy range

World

Indonesia haze forces schools to close as wildfires intensify amid severe dry season

Malaysia

PN walkout over Tabung Haji debate a political misstep, says analyst

By Alfian Z.M. Tahir

Malaysia

51 witnesses to testify at inquest into death of 10-year-old boy found unconscious in school toilet

Malaysia

Female student arrested for allegedly hurting classmate with kerambit at school

World

Colombia quake death toll hits 111 as rescue teams race to find survivors

World

Trump secretly switched to third aircraft in Türkiye over Iran assassination threat

Malaysia

Anwar questions PN’s priorities after Tabung Haji RCI walkout

Malaysia

MACC, police probing TH after RCI findings as govt warns no one will be spared

By Alfian Z.M. Tahir

You may be interested

Malaysia

RoS probes Bersatu complaint over position in Perikatan Nasional

Malaysia

Guan Eng questions Penang PH's stance on UMNO

Malaysia

Muhyiddin urges end to political appointments in Tabung Haji leadership

Malaysia

Myanmar agrees to take back 5,000 refugees from Malaysia by sea

Malaysia

Nine-year-old tahfiz pupil allegedly bullied, beaten by senior student

Malaysia

Malaysian dies while transiting in Bangkok to Japan (video)

Malaysia

BN Melaka ready to discuss cooperation ahead of state polls

By Alfian Z.M. Tahir

Malaysia

Speaker informs EC of Subang parliamentary seat vacancy